From Casetext: Smarter Legal Research

Penndot v. Driscoll Constr. Co., Inc.

Commonwealth Court of Pennsylvania
Jan 13, 1978
33 Pa. Commw. 296 (Pa. Cmmw. Ct. 1978)

Opinion

Argued December 9, 1977

January 13, 1978.

Public contracts — Board of Arbitration of Claims — Act 1937, May 20, P.L. 728 — Scope of appellate review — Findings of fact — Substantial evidence — Violation of law — Deletion of contract term — Questions not raised below.

1. Under the Act of 1937, May 20, P.L. 728, an order of the Board of Arbitration of Claims will be affirmed on appeal where necessary findings of fact are supported by substantial evidence and the order is not violative of statutory and constitutional law. [298]

2. Where a provision of a public contract providing for the removal of certain material by the contractor was deleted from the final proposal at the insistence of a prospective bidder and did not appear in the final contract, the Board of Arbitration of Claims could properly find that the contract did not require such removal and that a contractor should be paid for such work as an extra. [298]

3. Issues not raised in proceedings before the Board of Arbitration of Claims cannot be raised on appeal from an order of the Board. [298-9]

Argued December 9, 1977, before Judges WILKINSON, JR., ROGERS and DiSALLE, sitting as a panel of three.

Appeal, No. 2234 C.D. 1976, from the Order of the Board of Arbitration of Claims in case of Driscoll Construction Co., Inc. v. Commonwealth of Pennsylvania. Department of Transportation, No. 379.

Complaint in assumpsit before the Board of Arbitration of Claims seeking additional compensation under construction contract. Judgment entered in favor of plaintiff. Defendant filed petition for review with the Commonwealth Court of Pennsylvania. Held: Affirmed.

Arthur H. Marateck, Assistant Attorney General, with him Robert W. Cunliffe, Deputy Attorney General, and Robert P. Kane, Attorney General, for petitioner.

Joseph J. Carlin, with him Harold J. Conner, for respondent.


The Commonwealth's Department of Transportation (PennDOT) has filed a Petition for Review of a judgment rendered by the Board of Arbitration of Claims against it and in favor of Driscoll Construction Company, Inc. in the amount of $85,278.10 with interest from December 31, 1975.

Driscoll was awarded a contract for the construction of sewers under the Delaware Expressway in Philadelphia. The original bid proposal submitted to prospective bidders contained the following Special Requirement:

(4) Unsuitable Material — Where it is necessary, at the direction of the Engineer, to excavate unsuitable material and replace it with sand, stone, or rough board to provide a base for the placement of concrete, no payment will be made for such excavation below the approved limit of excavation shown on the drawings.

At a pre-bid conference a prospective bidder complained that the quoted provision was ambiguous and that it would allow PennDOT's engineer to require excavation and the supply of materials without limit and virtually without compensation. PennDOT agreed to the removal of this provision and it did not appear in the bid proposal finally used or in Driscoll's contract.

In the course of construction, Driscoll encountered an area in which the soil was, by its witnesses' description, "soupy, sloppy silt," unsuitable for pouring concrete sewers. After attempting unsuccessfully to dry the area by pumping, Driscoll excavated 1,722.79 cubic yards of unsuitable soil which it replaced with 1,722.79 cubic yards of crushed stone at a cost of $85,278.10.

Our scope of review in appeals from the Board of Arbitration of Claims is narrow. Section 8(c) of the Act of May 20, 1937, P.L. 728, as amended, 72 P. S. § 4651-8(c), provides that: "The findings of the board [of Arbitration of Claims] as to the facts, if supported by substantial evidence, shall be conclusive." In Santis Construction, Inc. v. Department of Transportation, 25 Pa. Commw. 460, 462, 361 A.2d 444, 445-46 (1976), we declared: "In appeals from Board orders, we are bound by the Board's findings of fact if such are supported by substantial evidence, and, if they are so supported, we must affirm the Board's order unless it violates applicable statutory and constitutional law."

PennDOT does not contend that the record does not support the Board's findings that Driscoll encountered unsuitable soil which it was required to excavate and replace with stone. It says that the Board erred by failing to conclude that a term of the contract requiring dewatering of the construction site in the Delaware river imported an obligation to remove and replace unsuitable material, despite the admitted fact that a provision spelling out this duty of the contractor had been removed from the final proposal at a prospective bidder's insistence. The circumstances clearly support the Board's explicit conclusion that the contract did not include the removal of unsuitable material and its replacement and that the contractor should be paid for this work as an extra.

PennDOT also raises a question based on a provision of the contract requiring a written order as a condition to recovering for extra work. This issue was not raised in the proceedings before the Board of Arbitration of Claims and will not be considered here. General State Authority v. Loffredo, 16 Pa. Commw. 237, 328 A.2d 886 (1974).

We affirm the judgment below.

ORDER

AND NOW, this 13th day of January, 1978, the judgment entered by the Board of Arbitration of Claims in favor of Driscoll Construction Company, Inc. and against the Commonwealth of Pennsylvania, Department of Transportation, is affirmed.


Summaries of

Penndot v. Driscoll Constr. Co., Inc.

Commonwealth Court of Pennsylvania
Jan 13, 1978
33 Pa. Commw. 296 (Pa. Cmmw. Ct. 1978)
Case details for

Penndot v. Driscoll Constr. Co., Inc.

Case Details

Full title:Commonwealth of Pennsylvania, Department of Transportation, Petitioner v…

Court:Commonwealth Court of Pennsylvania

Date published: Jan 13, 1978

Citations

33 Pa. Commw. 296 (Pa. Cmmw. Ct. 1978)
381 A.2d 516

Citing Cases

Commonwealth v. E. J. Albrecht Co.

The parties have stipulated to the number of cubic yards actually removed. Our scope of review is a narrow…