From Casetext: Smarter Legal Research

Northwest Mechanical v. Public Utilities Com'n

Supreme Court of Minnesota
Aug 24, 1979
283 N.W.2d 522 (Minn. 1979)

Summary

holding even those impermissible contacts or dealings that "might create an impression of possible bias" suffice to show evident partiality

Summary of this case from Balchova v. Bassovski

Opinion

No. 49165.

August 24, 1979.

Appeal from the District Court, St. Louis County, C. L. Eckman, J.

Smith, Currie Hancock and Patrick A. Thompson, Atlanta, Ga., Hanft, Fride, O'Brien Harries and Tyrone P. Bujold and John D. Kelly, Duluth, for petitioner, appellant.

Jerry H. Ketola, City Atty., Virginia, for respondent.

Heard before SHERAN, C. J., SCOTT and MAXWELL, JJ., and considered and decided by the court en banc.


This is an appeal by Northwest Mechanical, Inc. ("Northwest") from the orders of the District Court of St. Louis County denying its petition to vacate an arbitration award issued in a contract dispute with the Public Utilities Commission of the City of Virginia ("Commission") and confirming the award. We reverse.

In 1975, the Commission contracted with Northwest for the installation of piping in a power plant to be located in Virginia. The project was delayed through the fault of neither Northwest nor the Commission, and Northwest's costs were increased. A dispute arose over the amount to be added to Northwest's contract, and it was agreed the matter would be submitted to arbitration pursuant to the arbitration clause of the contract. The arbitration clause provided that each of the parties would select one arbitrator, and these two would select a third.

Northwest chose James A. Loosen, the Commission selected John D. Lenci, and these two then chose Robert F. Berger. On January 12, 1978, the arbitrators made their award to Northwest. Berger and Lenci concurred in the award; Loosen dissented.

After the award was made, Northwest began to investigate the business relationships between Lenci and Berger and the City of Virginia. A number of connections were discovered which formed the basis of this suit. Specifically, Northwest has presented evidence that Lenci is the president of one corporation and a member of the board of directors of another that in the two years prior to the arbitration performed substantial construction work under contract for the City of Virginia, and Berger represented the City of Virginia in at least four cases in the ten years preceding the arbitration. Though Lenci's past membership on the predecessor to the Commission and his company presidency were acknowledged in a letter to Loosen prior to the arbitration, there is no evidence that these connections were disclosed to Northwest.

Northwest, in addition, has presented evidence of additional connections that appear to us irrelevant. These include the activities of Lenci's son and the relationship of Berger to the company headed by Lenci's son, Lenci's past membership on the predecessor to the Commission, and the representation by Berger's law firm of Virginia's liability insurance company.

The trial court found these contacts insufficient to overturn the award, and this appeal followed.

We note at the outset that these relationships are neither uninterrupted nor of a magnitude making bias inevitable. Indeed, one could hardly expect any less interrelationship in a city the size of Virginia. Nor is there any claim of fraud or attempted concealment or any challenge to the merits of the award. Nonetheless, because of the following circumstances we believe Commonwealth Coatings Corp. v. Continental Casualty Co., 393 U.S. 145, 89 S.Ct. 337, 21 L.Ed.2d 301 (1968), to which we accede, applies to this case and requires reversal.

1. Though two Minnesota entities are parties to this arbitration, the federal arbitration statute, 9 U.S.C. § 1 et seq., applies to this case because construction materials for this project came from all over the country. Electronic Missile Facilities, Inc. v. U.S., 306 F.2d 554 (5th Cir. 1962), rev'd on other grounds, 374 U.S. 167, 83 S.Ct. 1815, 10 L.Ed.2d 818 (1963).

2. Though the Commission may have a legal status in some ways independent of the City of Virginia, in practical effect they are a single entity and contacts with the city must be considered dealings with the Commission.

3. The contacts between Berger and Lenci and the City of Virginia, even if not producing any actual prejudice, are "dealings that might create an impression of possible bias" as the phrase is used in Commonwealth Coatings, 393 U.S. 149, 89 S.Ct. 339, 21 L.Ed.2d 305.

4. These contacts were not disclosed to the parties as required by Commonwealth Coatings.

Reversed.

TODD, J., took no part in the consideration or decision of this case.


Summaries of

Northwest Mechanical v. Public Utilities Com'n

Supreme Court of Minnesota
Aug 24, 1979
283 N.W.2d 522 (Minn. 1979)

holding even those impermissible contacts or dealings that "might create an impression of possible bias" suffice to show evident partiality

Summary of this case from Balchova v. Bassovski

reversing an arbitration award on the grounds that dealings between two of the arbitrators and one of the parties "might create an impression of possible bias"

Summary of this case from KINN v. ALASKA SALES SERVICE, INC

In Nw. Mech., Inc., one of the arbitrators was president of a construction firm that did construction under a contract with the city, which was in "practical effect" the same entity as a party to the arbitration, the public utilities commission for the city.

Summary of this case from ITRON, INC. v. WEB CONSTR., INC

stating that the two entities were practically the same, although the commission for the city may have had a "legal status in some ways independent of the city" itself

Summary of this case from ITRON, INC. v. WEB CONSTR., INC

using de novo standard of review

Summary of this case from Pirsig v. Pleasant Mound Mut. Fire Ins. Co.
Case details for

Northwest Mechanical v. Public Utilities Com'n

Case Details

Full title:NORTHWEST MECHANICAL, INC., petitioner, Appellant, v. The PUBLIC UTILITIES…

Court:Supreme Court of Minnesota

Date published: Aug 24, 1979

Citations

283 N.W.2d 522 (Minn. 1979)

Citing Cases

ITRON, INC. v. WEB CONSTR., INC

1989) (emphasis added). WEB also cites Pirsig v. Pleasant Mound Mut. Fire Ins. Co., 512 N.W.2d 342 (Minn.App.…

Pirsig v. Pleasant Mound Mut. Fire Ins. Co.

Whether the conduct challenged constitutes "evident partiality" is reviewed de novo. See Northwest…