Naiman v. Flickinger Assoc

Colorado Court of Appeals. Division III
Oct 18, 1979
605 P.2d 63 (Colo. App. 1979)

Opinion

No. 78-523

Decided October 18, 1979. Opinion modified and as modified petition for rehearing denied November 15, 1979. Certiorari denied January 14, 1980.

Defendant in an action for negligent performance of a contract appealed the dismissal of his third-party complaints against two of his subcontractors.

Reversed

1. INDEMNIFICATIONActions Against Architect — Third-Party Claims — Against Subcontractors — Sounded in Indemnification — Material Issue of Fact — Allocation of Liability — Entry — Summary Judgment — Error. Where, in action against architect for negligent preparation of contract, the architect asserted third-party claim against certain of its subcontractors, that claim sounded in indemnification, and a material issue of fact existed relative to those claims, namely the proper allocation of liability between the architect and its subcontractors; consequently, the trial court erred in entering summary judgment dismissing the third-party claims.

2. Oral Contract — Between Architect and Subcontractors — Conceded — Legal Relationship Existed — Preclude Summary Judgment — Indemnification Claim. Since it was conceded that an oral contract between defendant architect and third-party defendants constituted a legal relationship, there existed the necessary obligations between the architect and the third-party defendants to preclude summary judgment as to the architect's claims that any liability he had to the plaintiff for negligent performance of a contract was secondary to the primary liability of the third-party defendants.

Appeal from the District Court in and for the City and County of Denver, Honorable Robert T. Kingsley, Judge.

Deisch and Marion, P.C., Michael B. Marion, for defendants-third party, plaintiffs-appellants.

Calkins, Kramer, Grimshaw Harring, Richard L. Harring, David M. Berrett, for third party defendant-appellee Sol Flax and Associates, Inc.

The law firm of Margaret Bates Ellison, Joann G. Ward, for third party defendant-appellee Riley Engineering Corporation.


Jack Naiman and others instituted an action against Warren A. Flickinger Associates and Warren A. Flickinger for negligent performance of a contract. Flickinger filed third-party complaints against Sol Flax and Associates and Riley Engineering Corporation alleging that they were or may have been liable to him for all or part of the Naiman claim. The trial court entered summary judgment, dismissed the third-party complaints against Flax and Riley, and entered an order pursuant to C.R.C.P. 54(b). Flickinger contends on appeal that this ruling was erroneous. We agree, and therefore reverse.

Flickinger provided architectural services, including plans and specifications for the electrical, mechanical, and structural designs of an industrial complex. Flickinger orally contracted with Sol Flax and Associates, electrical engineers, to provide the electrical plans; and with Riley Engineering Corporation, mechanical engineers, to provide the mechanical plans. Both engineering firms completed the appropriate work, and Flickinger incorporated substantially all of their plans into the overall architectural design for the project.

In their complaint, the plaintiffs alleged that the plans and specifications for electrical, mechanical, and structural designs were negligently prepared. Flickinger answered denying that the designs were defective. At the same time, however, Flickinger filed a third-party complaint alleging that if the designs were in any manner defective, then Flickinger was entitled to indemnification from the subcontractors.

In response to interrogatories propounded by the appellee third-party defendants, Flickinger stated that there were no defects in mechanical and electrical plans and specifications, with the exception of one item which had been corrected. Since Flickinger failed to contend that the third-party defendants were negligent in their performance of the subcontract, the court found that there was no material issue of fact, and dismissed the third-party complaints.

On appeal, Flickinger argues that the existence of a factual dispute between itself and Naiman, the principal plaintiff, regarding the allegation of negligence is enough to sustain Flickinger's action over against third-party defendants. We agree.

[1] Where a plaintiff's injuries result from the primary fault of one party, but the plaintiff seeks recovery from another party, the second party may hold the party primarily at fault as an indemnitor. Jacobson v. Dahlberg, 171 Colo. 42, 464 P.2d 298 (1970). In the instant action, Flickinger claims that if the designs were negligently prepared, then the primary fault lies with the third-party defendants. Thus, the substantive claim between Flickinger and the third-party defendants sounds in indemnification.

C.R.C.P. 14(a) provides a mechanism for disposing of multiple claims arising from a single set of facts in one action, where a third party may be liable to the defendant for all or part of the plaintiff's original claim. United Bank v. Shavlik, 189 Colo. 280, 541 P.2d 317 (1975). A principal, such as Flickinger, whose agent may have violated its duties, may cause the agent to be made party to an action brought by a third person against the principal. Schledewitz v. Consumers Oil Cooperative, Inc., 144 Colo. 518, 357 P.2d 63 (1960). Under the circumstances, the material issue of fact to be determined is the appropriate allocation of liability between the principal, Flickinger, and the agents, the third-party defendants.

Riley Engineering contends that a claim for indemnification was nevertheless inappropriate because Flickinger has failed to show that the relationship between Flickinger and the third-party defendants allowed for the indemnification of one tortfeasor by another. Riley recognizes that indemnification between tortfeasors is appropriate only where a tortfeasor who is secondarily negligent has sought recovery from a tortfeasor who is primarily negligent, but urges that Flickinger cannot show its negligence was secondary to that of the third-party defendants, without alleging that they were negligent. We do not agree.

[2] For one tortfeasor to be in a position of secondary responsibility to another, there must have been either some preexisting legal relationship between them, or, some duty on the part of the primary tortfeasor to protect the secondary tortfeasor. Ringsby Truck Lines, Inc. v. Bradfield, 193 Colo. 151, 563 P.2d 939 (1977). Since Riley concedes that the oral contract between Flickinger and the third-party defendants constituted a legal relationship, this alone is sufficient to entitle Flickinger to seek indemnification. Ringsby Truck Lines, Inc. v. Bradfield, supra. The allocation of liability, if any, among the parties is a determination for the fact-finder.


The judgment is reversed, and the cause is remanded with directions to reinstate the third-party complaints.

JUDGE RULAND and JUDGE BERMAN concur.


Summaries of

Naiman v. Flickinger Assoc

Colorado Court of Appeals. Division III
Oct 18, 1979
605 P.2d 63 (Colo. App. 1979)
Case details for

Naiman v. Flickinger Assoc

Case Details

Full title:Jack Naiman, d/b/a The Naiman Company, 3950 Sorrento Valley Blvd., San…

Court:Colorado Court of Appeals. Division III

Date published: Oct 18, 1979

Citations

605 P.2d 63 (Colo. App. 1979)
605 P.2d 63

Citing Cases

Johnson Realty v. Bender

As the trial court recognized, a common law duty to indemnify may arise based on a pre-existing legal…