Morris v. C & F Builders Inc.

Supreme Court, Appellate Division, Third Department, New York.
Aug 4, 2011
87 A.D.3d 792 (N.Y. App. Div. 2011)

Opinion

2011-08-4

Jeremy MORRIS, Appellant,v.C & F BUILDERS, INC., Respondent, et al., Defendants.

Stanley Law Offices, Syracuse (Robert A. Quattrocci of counsel), for appellant.Shantz & Belkin, Latham (Derek L. Hayden of counsel), for respondent.


Stanley Law Offices, Syracuse (Robert A. Quattrocci of counsel), for appellant.Shantz & Belkin, Latham (Derek L. Hayden of counsel), for respondent.

MERCURE, J.P.

Appeal from an order of the Supreme Court (Reynolds Fitzgerald, J.), entered October 26, 2010 in Delaware County, which, among other things, partially granted a cross motion by defendant C & F Builders, Inc. for summary judgment dismissing the complaint.

Defendants James Meehan and Rachel Meehan hired various contractors to construct a residence, including defendant George C. Squires, an electrical contractor. Squires, in turn, employed plaintiff, who was injured at the work site when he fell through an opening in the floor where a staircase was to be installed. Plaintiff commenced this action alleging claims of common-law negligence and violations of Labor Law §§ 200, 240 and 241 against, among others, defendant C & F Builders, Inc., the framing contractor on the project. Following joinder of issue and discovery,

plaintiff moved for partial summary judgment on his Labor Law § 240(1) claim, and C & F Builders cross-moved for summary judgment dismissing the complaint and all claims against it. As is relevant here, Supreme Court granted C & F Builders' cross motion to the extent of dismissing plaintiff's Labor Law §§ 200, 240 and 241 claims against it.

Plaintiff appeals and we affirm.

Supreme Court's denial of a separate summary judgment motion by the Meehans is not at issue on this appeal.

There is no question that “the absolute liability imposed upon owners and general contractors pursuant to Labor Law § 240(1) and § 241(6) does not apply to prime contractors having no authority to supervise or control the work being performed at the time of the injury” ( Hornicek v. William H. Lane, Inc., 265 A.D.2d 631, 631–632, 696 N.Y.S.2d 557 [1999]; see Russin v. Louis N. Picciano & Son, 54 N.Y.2d 311, 317–318, 445 N.Y.S.2d 127, 429 N.E.2d 805 [1981]; Soskin v. Scharff, 309 A.D.2d 1102, 1104, 766 N.Y.S.2d 248 [2003] ). Likewise, liability cannot be imposed under Labor Law § 200 where a defendant lacked “the authority to control the activity bringing about the injury” ( Russin v. Louis N. Picciano & Son, 54 N.Y.2d at 317, 445 N.Y.S.2d 127, 429 N.E.2d 805; see Rizzuto v. L.A. Wenger Contr. Co., 91 N.Y.2d 343, 352, 670 N.Y.S.2d 816, 693 N.E.2d 1068 [1998]; Soshinsky v. Cornell Univ., 268 A.D.2d 947, 947, 703 N.Y.S.2d 550 [2000] ).

Here, C & F Builders was a prime contractor and did not coordinate or supervise the electrical work on the premises. Indeed, both Squires and James Meehan testified that Squires was solely responsible for how the electrical work was done and could come and go as he pleased. Moreover, while it is far from clear that C & F Builders had any workers on the site when plaintiff was injured, plaintiff indicated that they played no role in his work when they were present. Inasmuch as C & F Builders had no control over plaintiff's work and had no duty, contractual or otherwise, to enforce safety standards at the work site, we agree with Supreme Court that it was entitled to partial summary judgment dismissing plaintiff's Labor Law §§ 200, 240 and 241 claims against it ( see Cook v. Thompkins, 305 A.D.2d 847, 847–848, 760 N.Y.S.2d 251 [2003]; Decotes v. Merritt Meridian Corp., 245 A.D.2d 864, 866, 666 N.Y.S.2d 763 [1997]; cf. Paolangeli v. Cornell Univ., 296 A.D.2d 691, 693, 745 N.Y.S.2d 593 [2002] ).

Plaintiff's remaining contentions are rendered academic in light of the foregoing.

ORDERED that the order is affirmed, with costs.

ROSE, LAHTINEN, KAVANAGH and GARRY, JJ., concur.


Summaries of

Morris v. C & F Builders Inc.

Supreme Court, Appellate Division, Third Department, New York.
Aug 4, 2011
87 A.D.3d 792 (N.Y. App. Div. 2011)
Case details for

Morris v. C & F Builders Inc.

Case Details

Full title:Jeremy MORRIS, Appellant,v.C & F BUILDERS, INC., Respondent, et al.…

Court:Supreme Court, Appellate Division, Third Department, New York.

Date published: Aug 4, 2011

Citations

87 A.D.3d 792 (N.Y. App. Div. 2011)
928 N.Y.S.2d 154
2011 N.Y. Slip Op. 6180

Citing Cases

Trombley v. DLC Electric, LLC

Plaintiff appeals, and we affirm. Supreme Court properly granted summary judgment dismissing the complaint…

Vasquez v. Manhattan Coll.

(Walsh v.Sweet Assoc, 172 A.D.2d 111,113, 577 N.Y.S.2d 324 [3d Dept. 1991] [citations omitted]). "There is no…