From Casetext: Smarter Legal Research

Miller v. Ketcham

Supreme Court, Appellate Term
Mar 1, 1900
30 Misc. 788 (N.Y. App. Term 1900)

Summary

In Ketcham v. Miller, 104 Ohio St. 372, 136 N.E. 145, the court held that punitive damages were not recoverable in an action for breach of contract.

Summary of this case from Armstrong v. Feldhaus

Opinion

March, 1900.

E. Ketchum, for appellant.

Miller, Decker Miller, for respondent.


The contract between Reid and the defendant provided, among other things, that the work was to be done in a good and workmanlike manner to be approved by E.K. Bourne, architect. The complaint is based on a substantial performance of the work, mentioned in the contract, by Reid, and a failure to complete the portion of the work, not completed, which failure was caused by the act of the defendant. The defendant now contends that the plaintiff cannot recover because he has failed to secure the approval of the work by the architect. We are of the opinion that this contention is not well founded. Plaintiff's evidence excuses the failure to obtain the certificate of the architect. Weeks v. Little, 89 N.Y. 566; Elting v. Dayton, 17 N.Y.S. 849; Same v. Same, 67 Hun, 425; Weeks v. O'Brien, 141 N.Y. 199.

The complaint also contains the allegation that on March 2, 1899, the sum of $200 was due and owing to said Reid by the defendant. This allegation is denied by the defendant. The witness Reid testified that the defendant had paid him but $425. This evidence was not denied by the defendant. The trial justice in effect found, and his finding was warranted by the evidence, that Reid's failure to complete was caused by the defendant. If defendant caused the failure, of course he is not entitled to damages because of the failure.

Present: TRUAX, P.J.; SCOTT and DUGRO, JJ.

Judgment affirmed, with costs.


Summaries of

Miller v. Ketcham

Supreme Court, Appellate Term
Mar 1, 1900
30 Misc. 788 (N.Y. App. Term 1900)

In Ketcham v. Miller, 104 Ohio St. 372, 136 N.E. 145, the court held that punitive damages were not recoverable in an action for breach of contract.

Summary of this case from Armstrong v. Feldhaus

In Ketcham v. Miller, supra, cited by the trial court, the plaintiff sought to claim that the breach of the contract was wilful and malicious. Here the breach of the contract was not claimed to be malicious; the later conduct of the defendant in forcibly snatching the check from the plaintiff was a malicious act.

Summary of this case from Wheaton v. Chandler
Case details for

Miller v. Ketcham

Case Details

Full title:CLIFFORD L. MILLER, Respondent, v . EDGAR KETCHAM, Jr., Appellant

Court:Supreme Court, Appellate Term

Date published: Mar 1, 1900

Citations

30 Misc. 788 (N.Y. App. Term 1900)

Citing Cases

Saberton v. Greenwald

The record presents the question whether the action of the trial court and the approval of such action by the…

White, Inc., v. Metr. Mer. Mart, Inc.

Exemplary damages, such as the plaintiff seeks to recover under the second count of the complaint, are not…