Metro. Switch Bd. Mfg. Co. v. B & G Elec. Contractors, Div. of B & G Indus., Inc.

Supreme Court, Appellate Division, Second Department, New York.
Jun 6, 2012
96 A.D.3d 725 (N.Y. App. Div. 2012)

Summary

noting that breaching party is nevertheless entitled to "the unpaid balance of what was due to it under the contract" at the time of its breach

Summary of this case from SBIW, Inc. v. Gen. Elec. Co.

Opinion

2012-06-6

METROPOLITAN SWITCH BOARD MANUFACTURING COMPANY, Inc., appellant, v. B & G ELECTRICAL CONTRACTORS, DIVISION OF B & G INDUSTRIES, INC., respondent.

Beck & Strauss, PLLC, Uniondale, N.Y. (Leland Stuart Beck of counsel), for appellant. Farrell Fritz, P.C., Uniondale, N.Y. (Jason S. Samuels and Michael A.H. Schoenberg of counsel), for respondent.



Beck & Strauss, PLLC, Uniondale, N.Y. (Leland Stuart Beck of counsel), for appellant. Farrell Fritz, P.C., Uniondale, N.Y. (Jason S. Samuels and Michael A.H. Schoenberg of counsel), for respondent.
MARK C. DILLON, J.P., THOMAS A. DICKERSON, L. PRISCILLA HALL, and SANDRA L. SGROI, JJ.

In an action to recover in quantum meruit, the plaintiff appealsfrom a judgment of the Supreme Court, Suffolk County (Baisley, Jr., J.), entered October 4, 2011, which, upon a decision of the same court dated September 26, 2011, made after a nonjury trial, is in favor of the defendant and against it on the defendant's counterclaim alleging breach of contract in the principal sum of $99,370.92.

ORDERED that the judgment is modified, on the law, by reducing the award from the principal sum of $99,370.92 to the principal sum of $4,370.92; as so modified, the judgment is affirmed, without costs or disbursements, and the matter is remitted to the Supreme Court, Suffolk County, for the entry of an appropriate amended judgment.

In reviewing a determination made after a nonjury trial, the power of this Court is as broad as that of the trial court, and this Court may render the judgment it finds “warranted by the facts,” bearing in mind that in a close case, the trial judge had the advantage of seeing the witnesses and hearing the testimony ( Northern Westchester Professional Park Assoc. v. Town of Bedford, 60 N.Y.2d 492, 499, 470 N.Y.S.2d 350, 458 N.E.2d 809).

The Supreme Court properly found that the plaintiff failed to establish a claim in quantum meruit. The plaintiff could not recover in quantum meruit in light of the existence of an enforceable contract governing the subject matter ( see Clark–Fitzpatrick, Inc. v. Long Is. R.R. Co., 70 N.Y.2d 382, 388–389, 521 N.Y.S.2d 653, 516 N.E.2d 190;cf. A. Montilli Plumbing & Heating Corp. v. Valentino, 90 A.D.3d 961, 962, 935 N.Y.S.2d 647;Wehrum v. Illmensee, 74 A.D.3d 796, 797, 902 N.Y.S.2d 607).

The Supreme Court properly determined that the defendant was entitled to recover damages from the plaintiff on its counterclaim alleging breach of contract. The defendant showed, by a preponderance of the credible evidence, that the plaintiff breached its contract with the defendant ( see Tri–Mar Contrs. v. Itco Drywall, 74 A.D.2d 601, 602, 424 N.Y.S.2d 737). Consequently, the defendant is entitled to be made whole and should recover the cost of completing the work that was the subject of the contract and correcting the defects in the plaintiff's work ( see Kaufman v. Le Curt Constr. Corp., 196 A.D.2d 577, 578, 601 N.Y.S.2d 186;Tri–Mar Contrs. v. Itco Drywall, 74 A.D.2d at 602–603, 424 N.Y.S.2d 737). At the same time, the plaintiff may set off, against the defendant's recovery, the unpaid balance of what was due to it under the contract ( see Tri–Mar Contrs. v. Itco Drywall, 74 A.D.2d at 603, 424 N.Y.S.2d 737). Here, we determine that the defendant was entitled to recover the principal sum of $4,370.92, representing the difference between the contract price and the defendant's total cost, and we modify the judgment accordingly ( id.).

The plaintiff's remaining contentions are without merit.


Summaries of

Metro. Switch Bd. Mfg. Co. v. B & G Elec. Contractors, Div. of B & G Indus., Inc.

Supreme Court, Appellate Division, Second Department, New York.
Jun 6, 2012
96 A.D.3d 725 (N.Y. App. Div. 2012)

noting that breaching party is nevertheless entitled to "the unpaid balance of what was due to it under the contract" at the time of its breach

Summary of this case from SBIW, Inc. v. Gen. Elec. Co.
Case details for

Metro. Switch Bd. Mfg. Co. v. B & G Elec. Contractors, Div. of B & G Indus., Inc.

Case Details

Full title:METROPOLITAN SWITCH BOARD MANUFACTURING COMPANY, Inc., appellant, v. B & G…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Jun 6, 2012

Citations

96 A.D.3d 725 (N.Y. App. Div. 2012)
946 N.Y.S.2d 178
2012 N.Y. Slip Op. 4324

Citing Cases

Kieran v. Sinetos

Remittal, however, is not necessary because the evidence presented was legally insufficient to establish the…

Aquatic Pool & Spa Servs., Inc. v. WN Weaver St., LLC

However, the Supreme Court should have granted those branches of the defendant's motion which were for…