Petitioner brings this mandamus proceeding to compel respondents to grant him a preference in obtaining an apartment in the Seward Park Housing Project.

The claim is based upon a provision in the contract between the City of New York and the owners of the project which provides: "Tenants on the site of this project shall, without discrimination, * * * be given preference in the completed project, provided such tenants meet and comply with all Housing Company's uniform requirements as to rental and otherwise affecting all tenants."

The contract also provides that the city shall use its best efforts to co-operate and assist in removal and relocation of tenants.

As respondents point out however, the contract contains a section which provides that no person, other than the parties thereto and other specifically named persons, have any rights under it.

It is clear therefore, as respondents maintain, that in the absence of such a provision, at best, petitioner's rights, if any, would be enforcible in a plenary action should he assert his right as a third-party beneficiary under the contract.

In no event, however, may petitioner seek to enforce his rights under a mandamus proceeding such as this. No lengthy discussion is deemed necessary in the well-established rule that mandamus is a remedy available only to a person as a member of the public to compel the performance by public officials of acts clearly mandated by law ( Matter of Newman v. Smith, 263 App. Div. 85, affd. 289 N.Y. 545).

Section 72-k Gen. Mun. of the General Municipal Law, cited by petitioner in support of his claim for priority, does not avail him. There is no provision in this section which compels the city to force a sponsor of a housing project to give priority to a tenant about to be displaced.

Petitioner has failed to establish that he has been denied a substantial constitutional right as he contends, or that he is entitled to bring this proceeding in the form adopted by him.

Consequently the application is denied and the cross motion to dismiss the petition is granted.


Summaries of

Matter of Waxenbaum v. Seward Park Corp.

Supreme Court, Special Term, New York County
Apr 13, 1960
24 Misc. 2d 35 (N.Y. Misc. 1960)
Case details for

Matter of Waxenbaum v. Seward Park Corp.

Case Details

Full title:In the Matter of SAM WAXENBAUM, Petitioner, against SEWARD PARK HOUSING…

Court:Supreme Court, Special Term, New York County

Date published: Apr 13, 1960

Citations

24 Misc. 2d 35 (N.Y. Misc. 1960)
201 N.Y.S.2d 849

Citing Cases

Matter of Scott v. Rockaway Corp.

Thus, this action is actually one to enforce private rights against a private corporation based in contract…

Martin v. Dayton Seaside Corp.

Accordingly, the plaintiff has no right whatsoever as a third-party beneficiary under said contract. ( Matter…