From Casetext: Smarter Legal Research

Matter of Diamond Asphalt Corp. v. Sander

Court of Appeals of the State of New York
Jul 9, 1998
92 N.Y.2d 244 (N.Y. 1998)

Opinion

Argued June 3, 1998

Decided July 9, 1998

Appeal from the Appellate Division of the Supreme Court in the First Judicial Department.

Graubard Mollen Miller, New York City ( Milton Mollen, Scott E. Mollen and John P. Sheridan of counsel), for appellant. Michael D. Hess, Corporation Counsel of New York City ( Lewis S. Finkelman, Pamela Seider Dolgow, Bob Bailey and John Hogrogian of counsel), for respondents.

Davis Polk Wardwell, New York City ( Guy Miller Struve and Gina Caruso of counsel), Robert P. Slevin, Richard W. Babinecz and Andrew J. Czerepak for intervenors-respondents.



Two interrelated law questions are presented on this appeal. Does private utility interference work constitute "public work" under General Municipal Law § 103 (1), when municipalities determine the "lowest responsible bidder" by combined assessment of amounts bid for utility interference work and street reconstruction work? Additionally, in satisfaction of General Municipal Law § 103 (1), does bypass contractor selection authority survive solely as the Mayor's responsibility, under revised New York City Charter § 313(b)(2)? We answer both questions in the negative.

Petitioner Diamond Asphalt Corp. sued to annul the award of certain public works contracts to competitors. Affected utility companies moved to intervene in the lawsuit. Supreme Court granted the intervention, denied annulment of the contracts, and dismissed the lawsuit. The Appellate Division affirmed. This Court granted Diamond leave to appeal and we now reverse and grant declaratory relief only.

I.

This case involves the legal classification and public works nature of reconstruction work on New York City streets in conjunction with related utility interference work. It is undisputed that private utility companies serving the City and its residents have a practical and historic statutory and common-law obligation to pay all costs associated with protecting their facilities during street repair projects; these obligations include the removal, protection and relocation of their utility equipment ( see, Administrative Code of City of N.Y. § 19-143[b]; § 24-521[b]; see also, Matter of Consolidated Edison Co. v. Lindsay, 24 N.Y.2d 309, 316; New York Tel. Co. v. City of Binghamton, 18 N.Y.2d 152, 159-160; Transit Commn. v. Long Is. R.R. Co., 253 N.Y. 345, 351). This unique obligation is a precondition to the "privilege" to use City streets for the purpose of installing and maintaining utility equipment ( Transit Commn. v. Long Is. R.R. Co., supra, 253 N.Y. at 351).

It is further undisputed that until 1992, utility interference work was considered private work and was separately contracted for by the utility companies. The process worked generally as follows: the City would select the lowest bidder contractor to perform the necessary street reconstruction work and then notify affected utility companies, who would in turn hire their own contractors to perform the related utility work. The utility interference work was not included in the public works contract between the City and its selected contractor; the agreement between the latter was, as customary, governed by the "lowest responsible bidder" restrictions.

According to the arguments of the City and the utilities before us, this arrangement resulted in lengthy delays to public improvement projects and inflated costs to utility companies. They explain that affected utility companies would customarily contract with the City's contractors, who often submitted artificially low bids to the City, expecting to adjust and recoup from the utility companies with respect to profits or losses resulting from the low bid used to win the contract.

Related to the matter at hand, the City entered into a joint bidding agreement in 1992 with Con Edison, New York Telephone, and Empire City Subway. The joint bidding agreement covers City construction projects "mutually agreed upon" between the City and the utility companies. Under the arrangement, the City solicits bid specifications for all aspects of the work involved in a public project, including utility interference work. The City issues a "Special Notice to Bidders" which advised bidders that work for various utilities is included in the contract, and that the contractor is responsible for all utility work affecting the utility facilities.

Under the agreement, the City is required to award the contract to the contractor submitting the lowest aggregate bid, irrespective of the discrete costs associated with the formerly public work street portion alone. The City is obliged to pay the successful contractor for the entire project, including the necessary utility interference work. The utility companies, in turn, must reimburse the City for the amount allocated by the contractor for the utility interference work. Additionally, the utilities must pay the City a pro rata portion of the contractor's enumerated general expenses and a 5% administrative charge.

Importantly, the accepted over-all low bidder is often not the lowest bidder for the City's share of the work; rather, the rejected bids include lower amounts for City reconstruction work. This is what occurred in the instant case — Diamond submitted the lowest bid on the City work portion alone, but its discrete portion for utility interference work bumped Diamond above the lowest bid in the aggregate.

The aggregate bidding arrangement does not fully protect against scenarios which may be potentially adverse to the taxpayers. For example, the agreement does not require utilities to reimburse the City for the difference between the accepted over-all low bidder's higher price for public street work and the lowest bid received for City work. Therefore, under the formal aggregate bidding agreement, the City may be required to accept a bid for the traditional public work which is not the "lowest" bid, solely because the aggregate bid spreads out as an over-all lowest bid.

The City rationalizes its acceptance of bids for City work which are not the "lowest" bids, by reference to what it has termed "commitment letters." These postbid letters, appended to the specific transactions challenged in this proceeding, were sent by the New York City Department of Transportation to the various utility companies. In the respective letters, the Roadway Engineering Bureau informs the utilities that the subject contract will be awarded to the named contractor. The letters add that the cost of the utility's share of the work includes a "pro-rated adjustment based on the difference between the overall low bidder's price for the City's share of the work and the lowest price received on the City's share of the work." The respective utilities are required to sign and return an attached duplicate copy of the letter in order to confirm acceptance of this informal payment rearrangement. Critically, these letters, which make no reference to the joint bidding agreement, were sent after the bids were solicited and after they were made public. Therefore, the utilities had an opportunity to learn the composition of the bids before accepting the added obligations proposed by the City in the informal side addendum. In fact, the "commitment letters" stated the actual differential for which the City sought reimbursement.

II.

In 1996, the City solicited public bids on three reconstruction projects for streets in Brooklyn and Queens. Prospective bidders were provided with proposed contracts for each project. They included a "Special Notice to Bidders" which expressly provided that "[t]he Contractor is responsible for all Utility Work for the affected Utility Facilities and shall be paid by the City for such work based on the prices bid." The bid schedule required each contractor to state separate amounts for each of the itemized bid components, which expressly included specifications for utility interference work, in addition to the gross sum for the entire work project.

Appellant Diamond submitted a substantially higher over-all bid compared to those submitted by other bidders. Diamond, however, submitted the lowest bid on the traditional public street work portion of each contract. The high utility work portion of its bid raised its aggregate bid above the competing bids. The City awarded each contract to the lowest aggregate bidder for the corresponding project.

Thereafter, the City Chief Procurement Officer informed Diamond by letter that it was not selected. Candidly, the respective letters for each of the contracts stated as follows:

"Pursuant to Section 313(b)(2) of the New York City Charter and Section 3-02(u) of the Procurement Policy Board (PPB) Rules, a City agency letting a contract by competitive sealed bidding shall award the contract to the lowest responsive and responsible bidder, unless the Mayor determines that it is in the best interest of the City that a bid other than that of the lowest responsive and responsible bidder be accepted. The Mayor has delegated this authority to the City Chief Procurement Officer.
"In the matter of the above contract let by the Department of Transportation (DOT), I have determined that it is in the best interest of the City to award the contract to * * * a firm that is the overall lowest responsive and responsible bidder for the combined City and Utility interference construction work, although the price allocated * * * to the City's work is greater than that incorporated into your firm's bid" (emphasis added).

He added that the selection was "based on" the agreement reached in the "commitment letters executed by the City and the utility companies."

In this format, the City expressly invoked its bypass authority in awarding the respective contracts to contractors that were not the lowest bidders for the City public street portion of the work ( see, City Charter § 313[b][2] [when a contract is awarded to other than the lowest bidder, notice must be given to the lowest bidder]). Significantly, this diversionary exercise of the award was not explicitly based on the theory the City now advances — that private utility work may be defined as "public work" for purposes of lowest bidder assessment in public works contracts, when conjoined with the purely public street work.

Diamond immediately commenced this CPLR article 78 proceeding challenging the City's selection of other contractors. It sought a preliminary injunction to prevent the certification of the let contracts. The municipal respondents opposed in all respects and moved to dismiss the petition. In the interim, intervenor-respondent utility companies entered the case and joined the effort to dismiss the petition.

Supreme Court denied preliminary injunction relief and granted the motions to dismiss. Supreme Court held that the utility interference work in each contract was not "public work" within the meaning of General Municipal Law § 103 (1) and, thus, the City could not consider the amount bid by each contractor for utility interference work in the aggregate as a method to determine which contractor was the "lowest responsible bidder" under that statute. Justice Freedman summarized as follows:

"The statute unequivocally states that the 'lowest responsible bidder' shall be awarded 'contracts for public work,' i.e., work done on behalf of the City and citizenry. The Utility Work included in the project contracts is not 'public work'; the Utility Work directly benefits and is on behalf of privately-owned Utilities, and any benefit to the City is indirect. To claim that bidders to project contracts are not 'responsible' under GML § 103(1) merely because they fail to submit the lowest joint bids begs the question as to whether considering the Utility Work price in awarding the contract is legal under GML § 103(1)" (citing Matter of HHM Assocs. v. Appleton, 157 Misc.2d 759).

Nonetheless, Supreme Court held that the Mayor enjoys a "bypass" authority, pursuant to Charter § 313(b)(2), to award contracts to higher bidders.

The Appellate Division affirmed ( 238 A.D.2d 197). The court agreed that "the Mayor possesses and lawfully exercised his bypass authority under New York City Charter § 313(b)(2) in awarding the contracts to bidders who, although not the lowest bidders on the public work portion of the contracts, were the lowest bidders on both the public work and utility interference portions in the aggregate" ( id., at 198). The court reasoned that "[t]he exercise of such authority did not violate General Municipal Law § 103 (1), since bypass authority was established prior to September 1, 1953 and was merely revised and restated upon its transfer to the Mayor when the Board of Estimate was abolished" ( id.).

In addition, and contrary to Supreme Court's holding, the Appellate Division upheld the joint bidding agreement protocol, finding that "examination of the '"total character of the arrangement"' convinces us that the utility interference work called for in the contracts did constitute 'public work' within the meaning of General Municipal Law § 103 (1)" ( id., quoting Matter of Citiwide News v. New York City Tr. Auth., 62 N.Y.2d 464, 472).

III.

We first address two threshold matters. While this injunctive proceeding is moot because the work under the contracts at issue is completely or substantially done, we are satisfied that we should convert this proceeding into a declaratory judgment action ( see, CPLR 103 [c]; Matter of Lewis Tree Serv. v. Fire Dept., 66 N.Y.2d 667, 669). Conversion is prudent and appropriate in this case because the issues presented by Diamond effectively constitute a clear legal challenge to the validity of the relatively new and pervasive public bidding regimen being used by the City.

A question also has been raised concerning nonpreservation. Diamond contends that the City and the intervenor respondents argued only for the first time to the Appellate Division that "interference work" is "public work." Diamond argues that the City made this argument in response to the trial court's analysis, and that consequently the Appellate Division erroneously considered and ruled on this additional basis for affirming the dismissal of the lawsuit.

The City, in response, points to the assertion in its answer that "[e]ach of the contracts which are the subject of this proceeding was awarded to the lowest responsible bidder in accordance with General Municipal Law § 103." It urges that this statement sufficiently alerted its adversary and the trial court to its over-all claim that utility interference work constitutes "public work" in this "combined" work and bidding ritual.

We are satisfied that the public work argument is sufficiently preserved under these unusual circumstances, since both courts plainly ruled on it, and everyone was manifestly aware of its potential significance.

IV.

Turning to the merits, Diamond argues that utility interference work does not constitute "public work" under General Municipal Law § 103 (1) because utility work is inherently private and solely benefits utility companies. Diamond urges that municipalities may not consider the discrete amounts bid for utility interference work and City street work in the aggregate to determine which bidder is the "lowest responsible bidder" on a contract for public work. Rather, it suggests that the City must choose the lowest bidder on the public portion of the work, as it did before 1992 when the bidding arrangements were kept separate.

Both the City and the utilities, in turn, contend that utility interference work may be fitted into the statutory framework of "public work." Initially, they propose that utility interference work included in City contracts is "public work," which is itself subject to competitive bidding requirements under City Charter § 310(1). They note that section 310(1) mandates competitive bidding by the City for projects paid with moneys under the control of or collected by the City. Additionally, they propose that utility work constitutes "public work" because it is functionally inseparable from the street reconstruction work and has public consequences. Their theory is interwoven with policy considerations, essentially that aggregate bidding calculations eliminate the potential third-party haggling over costs between contractors and utilities, which may cause extensive delays in the completion of work covered by contracts between the City and contractors.

The governing statute is General Municipal Law § 103 (1). It provides that all contracts for "public work" must be awarded to the "lowest responsible bidder." Neither the statute nor legislative history provide a definition of "public work." Therefore, in determining whether traditional private utility work may be deemed and converted into "public work" for purposes of General Municipal Law § 103 (1), it is useful to examine the nature of the public bidding process in precedential context. This Court from time to time has been called upon to determine whether a particular contract constitutes "public work." In making these rulings, the Court has articulated and applied the purposes of the competitive bidding statutes.

Matter of Signacon Controls v. Mulroy ( 32 N.Y.2d 410), for example, held that a contract to provide a county-wide fire alarm reporting system fell within the "specific wording" and "spirit" of General Municipal Law § 103 (1) ( id., at 412, 414). The Court reasoned as follows:

"The agreement made between the county and [a private company] also opens the door to fraud, corruption, and favoritism, albeit there is no sign of such a situation in the case at bar. One of the purposes of the competitive bidding statutes is to eliminate the opportunity for fraud, favoritism or corruption by office holders. And no matter how one views this agreement, it is still a public contract given to a private contractor without competitive bidding. A wayward public official could use the secrecy and ambiguity inherent in any agreement not requiring public advertising and bidding to do great mischief." ( Id., at 415 [citations omitted].)

The Court concluded that "[t]o exempt this type of agreement from the competitive bidding requirements of section 103 of the General Municipal Law would allow public officials to do indirectly what they cannot do directly" ( id., at 416). We cautioned that "[s]uch an exemption would make it quite simple for most sellers and public officials, who wish to avoid the statute's requirement, to adopt an 'arrangement' whereby the governmental unit would pay no money but would be used as a rental or percentage conduit through which a seller could make large profits without having to subject his wares and price to the salutary effect of competitive bidding" ( id.).

Next, in Matter of Exley v. Village of Endicott ( 51 N.Y.2d 426), the Court reviewed "whether a municipality violated [General Municipal Law § 103], when it did not offer competitors of the New York Telephone Company the opportunity to bid for the right to provide the municipality with certain telephone terminal systems" ( id., at 429). The petitioners there argued that "the modern tariff system under which the equipment was to be provided rendered the transaction the functional equivalent of a sale, and brought it within the strictures of the competitive bidding statute" ( id.).

The Court in Exley began its analysis by noting that section 103 of the General Municipal Law must be read in conjunction with the underlying purpose set forth in Signacon — to "safeguard the public interest" by "invit[ing] competition, and discourag[ing] favoritism, improvidence, extravagance, fraud and corruption" ( id., at 431). The Court noted, however, that "it also must be recognized that competitive bidding statutes constitute a substantial imposition on the activities of municipal governments," and thus the Court should " not extend the coverage of the statute into areas unintended by the Legislature" (id. [emphasis added]).

The Court in Exley held that "the acquisition of the phone system [could not] without contextual strain be classified as a public work contract" ( id.). The Court reasoned that "the installation of the system was not a substantial aspect of the contract, and the contract did not otherwise involve performance of services or specialized skills" ( id.). Moreover, although the agreement had attributes of both a lease and a sale, the Court looked to the "total character of the arrangement" and concluded that the agreement was not a "purchase contract" within the scope of the competitive bidding statute because the transaction was "in the nature of a true lease" ( id., at 432-433).

Matter of Citiwide News v. New York City Tr. Auth. ( 62 N.Y.2d 464, supra) builds the precedential instruction, in relation to Public Authorities Law § 1209(1). That statute provides that a contract for "public work in excess of a specified cost may be entered into by the [Transit Authority] only after competitive bidding procedures have been followed" ( id., at 468). The issue in Citiwide was whether a license agreement, focusing primarily on the operation of newsstands in the New York City subway system, was subject to competitive bidding requirements where the agreement provided that the licensee must improve and rehabilitate existing facilities on the property ( id.). In Citiwide News, an unsuccessful applicant for the license argued that the maintenance and improvement provisions of the license agreement rendered the agreement a contract for "public work" and thus subjected it to competitive public bidding requirements ( id., at 468-469). The Court rejected this theory and held that the subject there was not "public work."

The Court found it "appropriate to look to the 'total character of the arrangement' in determining whether the master license, having attributes of both a typical license and a public work contract, falls within the scope of the competitive bidding statute" ( id., at 472, citing Matter of Exley v. Village of Endicott, 51 N.Y.2d 426, supra). We concluded that "[n]otwithstanding the fact that an indirect expenditure of public money [was] involved, the Authority was not required to follow competitive bidding procedures before making the contract, inasmuch as the 'total character of the arrangement' [was] clearly that of a license agreement for the maintenance and operation of newsstands and not that of a 'contract for public work'" ( id., at 470). Therefore, the issue in Citiwide was whether the contract as a whole was even subject to competitive bidding procedures.

Notably, the Court stated that neither the Public Authorities Law (at issue there) nor General Municipal Law § 103 (at issue here) "offers any definition of 'contract for public work' or otherwise indicates the specific nature of the contracts falling within the public bidding requirement" ( id.). The Court determined, however, that the expenditure of public money is a factor to be weighed ( id.). We stated: "'A contract which provides for a lesser income to a governmental unit than a competing contract might provide, is an "expenditure" within the meaning of [the competitive bidding statute]'" ( id., at 471, quoting Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 416, supra). Emphatically, this Court reiterated its "expressed concern [in Signacon] that public officials not be permitted to do indirectly what they may not do directly, and that the salutary purposes of the public bidding statutes not be evaded by merely altering the nature of an arrangement to bring it technically outside the scope of the requirements" ( id.). This admonition cogently directs the analysis and informs the disposition of the instant case.

Furthermore, the Court in Citiwide stressed that, in ascertaining the reach of public bidding requirements, it is important to ensure "full compliance with such statutes, which have as their aims the elimination of extravagance and improvidence, as well as prevention of the opportunity for fraud, favoritism or corruption in the awarding of public contracts" ( id., at 472, citing Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 414-415, supra). The Court again cautioned, on the other hand, that "[b]alanced against this important policy * * * is the equally important recognition that competitive bidding requirements impose a substantial restriction upon the activities of public entities and must be extended no further than reasonably contemplated by the Legislature" ( id., citing Matter of Exley v. Village of Endicott, 51 N.Y.2d 426, 431, supra). A key factor of this overview is that the Legislature is uniquely invested with the responsibility of definition as to who and what are covered. It would be unwise to shift such power into the engine and control of the regulated municipality, solely through its chief executive branch officer or designee.

Most recently, in Matter of AT/Comm, Inc. v. Tufo ( 86 N.Y.2d 1), the issue was "whether the New York State Thruway Authority was required to seek public bids, under Public Authorities Law § 359, for installation of a provisional electronic toll-collection service [E-ZPass]" ( id., at 4). The petitioner there argued that the electronic toll collection system installed by NYSTA constituted an "improvement" of the Thruway within the meaning of Public Authorities Law § 359, thus mandating public bidding ( id., at 5). The Court concluded that the contract did not require public bidding ( id., at 4). The Court reasoned that "[t]he aim of the E-ZPass system was not to improve the roadway but to improve the flow of traffic on it" ( id., at 6).

The Court acknowledged that under Citiwide it is necessary to examine "the 'total character of the arrangement' to determine whether the projects under review fall within the ambit of competitive bidding statutes" ( id.). In applying this standard, we again stressed the need to consider the underlying purposes of the public bidding statute ( see, id.). The Court concluded that the nature of the contract there was more similar to a "procurement" contract — one "for the acquisition of goods or services" ( id., at 6-7). Therefore, in defining and applying "public work" concerns, this Court has always preeminently emphasized that the values underlying the competitive bidding process must not be violated.

V. A.

The rationales in our precedents substantially pave the way for our conclusion that private utility work does not constitute "public work" in this case. We have bound the courts to construe public bidding statutes strictly in order to encourage, participate in and enforce the achievement of the stated objectives of the Legislature. The Legislature has in no way indicated an intention or authorization for the City to unilaterally and informally determine, define and alter the contours of "public work" matters. Quite to the contrary, the purposes of the competitive bidding process are placed in jeopardy when a municipality is permitted to unilaterally alter the terms of the accepted process. To be sure, this Court has more than once cautioned against allowing public officials to "indirectly" circumvent public bidding policies and prescriptions by "Lego-like" rearrangements of the pieces of traditional contractual relationships and obligations ( see, Matter of Citiwide News v. New York City Tr. Auth., 62 N.Y.2d 464, 471, supra; Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 416, supra). The means to the end are important, as is the need to subject the whole and the pieces of the transaction to careful scrutiny, especially in light of this Court's firm admonitions about protecting a fastidious bidding process.

The City concedes that utility work, prior to the creation of the joint bidding technique in 1992, did not constitute "public work." The City essentially argues then that the joint bidding agreement and the side addendum with the utilities effected a transformation of this part of such work projects and its scope into "public work." We disagree. Practical and unilaterally perceived policy objectives, however desirable, cannot bring about that legal conversion by endorsement from the courts — only the Legislature is empowered to effect policy-driven changes of this magnitude. Irrespective of the asserted "integration" aspect of the public contracts, and any direct, incidental or indirect benefits to the City derived from aggregate bidding, the nature of the utility work remains unchanged — it is private, and for the essential benefit of a private entity.

Notably, the Legislature has exercised its appropriate power in analogous circumstances. For example, in the Gas Facility Cost Allocation Act (GFCAA), the Legislature authorized the City to enter into agreements with gas utilities to share the costs of gas line interference work necessary to perform water and sewer projects (GFCAA, L 1988, ch 357, § 4, reprinted in McKinney's Cons Laws of N.Y., Book 47, Public Service Law § 66, at 164). The statute provides for joint bidding for water and sewer projects (GFCAA, L 1988, ch 357, §§ 4, 5[3], reprinted in McKinney's Cons Laws of N.Y., Book 47, Public Service Law § 66, at 164, 166). Conversely, the "Wicks Law" expressly precludes joint bidding (General Municipal Law § 101). It mandates "separate and independent bidding" for enumerated portions of the required work (General Municipal Law § 101). The City and dissent urge that merely because the Legislature has expressly made joint bidding a part of the cost-sharing scheme in other contexts does not indicate that the City cannot unilaterally implement joint bidding without legislative involvement in circumstances such as are presented here. The cited legislative parallels cogently demonstrate that these bidding schemes must be authorized by the Legislature, not devised and implemented by the municipalities on their own.

Additionally, the dissent attempts to distinguish the GFCAA by arguing that "[t]he agreements at issue in this case do not contemplate a cost-sharing scheme;" rather, utility companies remain responsible for the cost of interference work and "for the difference between the actual cost of the reconstruction portion of the contract and the low bid submitted for that work" (dissenting opn, at 271, 272, n). To the contrary, critical reliance on the informal letters is very troublesome, due to the possible playouts under which the City would be left to absorb the cost of a higher bid for street reconstruction work.

Assuming that this Court were to sanction the City's novel reorganization of the contractual relationships and responsibilities, this would be the first judicial approbation in theory and as applied; the holding would invest the City with unusual authority for these public bidding agreements. The authorization for this unconventional and unlimited process could thus become the template for all future multimillion dollar dealings. That sweeping consequence would contradict this Court's express warnings and pertinent prohibitions, and its respectful acknowledgment of the distinctive legislative prerogatives governing this area of governmental authority.

B.

Furthermore and appropriately, we are concerned that the City's creative formulation, including the side letter agreements between the City and the private utility companies, could "open the door to fraud, corruption, and favoritism, albeit there is no sign of such a situation in the case at bar" ( Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 415, supra). The values associated with the competitive bidding process are seriously jeopardized by informal arrangements which permit one party to unilaterally alter the terms or conditions of the agreement. These concerns are not unfounded "dire predictions" (dissenting opn, at 272), but rather rest on the realistic wariness taught by this Court's undeviating precedents.

For example, the City argues that there is no additional expenditure of public money as a result of the joint bidding scheme ( see, Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 416, supra ["A contract which provides for a lesser income to the governmental unit than a competing contract might provide, is an 'expenditure' within the meaning of section 103."]). Its argument is premised on the "commitment letters," by which the utility companies agreed to reimburse the City for the differential between the lowest bid for City work and the cost of City work in the accepted lowest joint bid. We perceive a considerable hole in this purported security blanket, both legally and practically.

As noted, this "agreement" was not made part of the formal joint bidding agreement and does not even reference it. Rather, the letter exchange is an informal postbid addendum, entered into by separate parties (the City and the utilities). Thus, utility companies are given an opportunity to review the accepted bid and the differential in the constituent parts of the bid before signing onto the side-bar letter. This appendage is inherently contradictory to the public bidding process and provides an open invitation to manipulation and other temptations. Allowing an informal, postbid agreement between the City and a private company to affect or dictate the public bidding regularities between the City and its contractor is bad policy, bad law and may even be bad business, though that is not a direct concern or within the expertise of the courts.

Curiously, if the utilities were to refuse to "commit" to the informal postbid proposition or thereafter flatly refuse to reimburse the City for the difference between the public work bids, it is unclear how, if at all, the City would enforce reimbursement for the differential, except perhaps through litigation or other dispute resolution mechanisms. In this eventuality, the City might end up awarding a City contract to a contractor who submitted a bid on the public work portion which far exceeds that of the lowest responsible bidder for City work, ultimately to the detriment of the taxpayers. This example demonstrates the uncertainty and inappropriateness of the City's proposed reinforcement of its scheme. Notably, the "commitment letters" are only pertinent to the instant case, and thus the future of this over-all process is even more unclear because the formal agreement allows for the acceptance of a bid for City work that is demonstrably not the "lowest," possibly leaving the public fisc holding the bag.

The dissent urges that "on the facts before us there is no sign of any evil at work in this case, nor does the Court identify any" (dissenting opn, at 272-273). The dissent disregards, however, this Court's definitive declaration that there need not be fraud or even a "sign" of fraud in a particular case; rather, the competitive bidding statutes are intended to guard against the "opportunity" for fraud ( Matter of Signacon Controls v. Mulroy, 32 N.Y.2d 410, 415, supra). In our view, the comprehension of how the agreement in the instant case "opens the door to fraud" is plain to see ( id.). The dissent instead would accept the City's agreement for reimbursement as an acceptable practice "memorialized" in the commitment letters (dissenting opn, at 268-269). We are wary of giving these commitment letters such legitimatizing force and justification.

Moreover, even assuming the existence of a provision in the joint bidding agreement which attempts to protect against the unlawful expenditure of public funds by requiring reimbursement for any differential, the City's scheme still falters because it improperly allows the City to unilaterally allocate and direct the funds obtained and paid during the public bidding process. That fundamentally alters the nature of the process. Pushing the envelope to its extreme, the City goes even further in the joint bidding agreement by agreeing to consult with the utilities regarding bids. The agreement between the City and the utilities states: "[t]he City agrees to consult with the Companies as to what constitutes an excessive or unbalanced bid and as to what action the City, in its discretion, should take in the event of the submission of an excessive or unbalanced bid."

Providing private companies with such an interactive, consultative role in the public bidding process is contrary to the generally above-the-board nature of the process. The General Municipal Law and this Court's precedents forbid or should deter the City from playing with such fire. Otherwise, the process could be manipulated by private, investor-owned, profit-seeking third-party companies, such as utilities and contractors, perhaps in collaboration against the interests of the City.

C.

The dissent further urges that the entire scheme in the instant case is one for "public work" solely because, in its view, "the total character of the arrangement is of a 'public work' nature" — i.e., utility interference work is "incidental" to and a "necessary component" of street reconstruction projects ( see, dissenting opn, at 270). We believe that the dissent has omitted a vital part of the requisite analysis.

Although the "total character of the arrangement" test has been used by this Court to determine whether a particular contract is a public works contract, in each application the Court has stressed the importance of ensuring that the underlying purposes of the competitive bidding statutes are not violated — i.e., that there is no potential for fraud and that the Legislature's objectives are complied with. In AT/Comm, Citiwide and Exley, the Court confidently concluded that there was no potential for fraud and that the Legislature had not intended to include such contracts within the ambit of the respective public bidding statutes. The Court in each case, therefore, determined that the competitive bidding requirements did not apply at all.

The situation in the instant case is quite different. Here, there is an obvious potential for fraud and the Legislature has in no way indicated an intent to allow such informal bidding agreements to trump the public bidding process. The core of the subject transactions here are public works and are unquestionably subject to public bidding requirements under the General Municipal Law. The wide twist in the analytical road and precedential path then is whether the City may unilaterally transform the well-settled public bidding process by devising an informal scheme, whereby the City may accept a bid from a contractor that is not the "lowest" bid for City reconstruction work or "public work," by artfully combining traditionally public work with formerly undisputedly private work to arrive at an enlarged public work project.

Under the City's and the dissent's proposed theory, anything could be deemed a public work simply by including it in a public work contract. Indeed, the essential character of this arrangement was merely the joinder of bids for the purely private work with those for the public work. That cannot as a matter of law convert, as the dissent suggests, what has historically been considered substantial private work into public work. As evidenced by the City's requirement that bids be apportioned between the utility interference and the street reconstruction work, and more importantly by the fact that the City did not expend funds for any portion of the utility work, both the private and the public parts of the project manifestly remained separate and distinct.

The public bidding process must be protected from creative efforts by a municipality, as here, to skate around the process, however well intentioned the City's policy, fiscal or practicality grounds.

VI.

Having concluded that utility interference work does not constitute "public work," we must now address the alternative ground invoked by both lower courts to sustain the City's actions. We believe that bypass authority, under New York City Charter § 313(b)(2), is not continued in these circumstances under General Municipal Law § 103 (1) (i.e., transferred from the defunct New York City Board of Estimate to the Mayor alone).

Prior to 1989, bypass authority was vested in the Board of Estimate under a different Charter provision. That Board was abolished after its structure was found unconstitutional by the United States Supreme Court ( see, New York City Bd. of Estimate v. Morris, 489 U.S. 688). Thereafter, in 1989, Charter § 313 was approved by New York City voters. It granted procurement powers to the Mayor and specified City agencies. Charter § 313(b)(2) provides that:

"The agency letting the contract may reject all bids if it shall deem it for the interest of the city so to do; if not, it shall, without other consent or approval, award the contract to the lowest responsible bidder, unless the mayor shall determine in writing, justifying the reasons therefor, that it is in the best interest of the city that a bid other than that of the lowest responsible bidder shall be accepted."

The dispute in the instant case springs out of General Municipal Law § 103 (1). It clearly provides that all contracts for "public work" must be awarded to the lowest responsible bidder, "[e]xcept as otherwise expressly provided by an act of the legislature or by a local law adopted prior to [Sept. 1, 1953]."

Diamond argues that because Charter § 313(b) was passed by the electorate in 1989, it constitutes a law adopted after September 1, 1953 and thus cannot qualify under the local law exemption set forth in General Municipal Law § 103. The City retorts that Charter § 313(b) is a mere "revision, simplification, consolidation, codification or restatement" of a pre-September 1, 1953 local law and, as such, fits within the explicit reservation of power under the General Municipal Law.

Diamond points to Matter of Seabury Constr. Corp. v. Department of Envtl. Protection ( 160 Misc.2d 87), which found that General Municipal Law § 103 renders the Mayor's bypass authority invalid. In Seabury, the court concluded that the New Charter is not a "'mere revision, simplification, consolidation, codification or restatement'" of the Old Charter ( id., at 95). The court stated that "although the bypass authority continued in the New Charter is in theory the same as that contained in the Old Charter, the fact that the decision-making process with respect to such authority has been transferred from the Board of Estimate to the Mayor alone represents a significant departure from the balance of power originally provided for under the Old Charter" ( id.). The court reasoned that "[u]nder the Old Charter, the bypass authority could only be triggered by a 'super majority' vote of the Board of Estimate," whereas "the New Charter vests the power to implement the bypass authority in a single individual, namely the Mayor or the Mayor's appointee" ( id.).

The City relies on trial court authority which concludes that "§ 313(b) of the current Charter retains its viability after the recodification of the Charter in 1989 and may, for purposes of GML § 103, be considered a local law adopted prior to September 1, 1953" ( Trocom Constr. Corp. v. Giuliani, NYLJ, Aug. 1, 1996, at 22, col 3, at 23, col 1; see, Matter of HHM Assocs. v. Appleton, 157 Misc.2d 759, 767, 769, supra [but concluding that "the Joint Bidding Agreement might well result in a violation of the 'lowest responsible bidder' rule"]; see also, United States v. City of New York, 799 F. Supp. 1308, affd 972 F.2d 464). This theory is based on the rationale that both Charters were based on the same principle: "under certain conditions, the municipality is empowered to waive the 'lowest bidder' rule" ( Matter of HHM Assocs. v. Appleton, supra, 157 Misc.2d at 769; see, Trocom Constr. Corp. v. Giuliani, supra, NYLJ, Aug. 1, 1996, at 23, col 4 ["(i)t is the continuation of the bypass power, rather than who may exercise it, that is critical"]). Finally, the State Comptroller has opined that "the Legislature [did not intend] to preclude a charter law adopted after September 1, 1953 which is essentially a mere revision, simplification, consolidation, codification or restatement of a pre-September 1, 1953 special law or local law" (1981 Opns St Comp No. 81-109, at 111).

The Legislature has not classified Charter § 313 as a mere "revision, simplification, consolidation, codification or restatement" of the Old Charter. We do not believe it can be so easily labeled since it effects a substantive power reallocation with substantive legal effects and dispensative avoidance of generally applicable and important regulatory and fiscal principles. The transfer of bypass authority from the Board of Estimate to the Mayor would represent a major shift in the balance of authority originally provided for under the defunct Charter. Therefore, we hold the view that to override the plain language of the General Municipal Law, an express or definitive declaration would be required to establish that the Legislature intended to continue and transfer bypass authority of such sweeping proportions and nature, as is presented in this case, solely to the chief municipal executive or designee.

Even assuming Charter § 313 constitutes a mere revision or recodification, neither this Court nor the Legislature has seen fit to answer the second step of necessary analysis — that such enactments fit within the General Municipal Law exception. That determination would also demand some express action or more reasonably definitive direction by the Legislature. We see none. Finally, it is wholly unpersuasive to buttress this claim of a unilateral authority shift on the fallback ground that the Mayor is nevertheless subject to scrutiny by public notification requirements and judicial review under CPLR article 78.

Since the respective rationales offered by the City and intervenors, and employed by the Appellate Division and the Supreme Court, do not sustain the validity of the City's actions and legal position in this case, we reverse and grant relief to Diamond only insofar as declaring the bid selection process unauthorized and unlawful.

Accordingly, the order of the Appellate Division should be reversed, with costs, the proceeding converted to a declaratory judgment action and judgment should be granted declaring that the bid selection procedures at issue violate General Municipal Law § 103 (1).


Judges TITONE, SMITH, LEVINE and CIPARICK concur with Judge BELLACOSA; Chief Judge KAYE dissents and votes to affirm in a separate opinion in which Judge WESLEY concurs.

Order reversed, etc.


We conclude, as did the Appellate Division, that based on a review of the total character of the arrangement presented, the utility interference work here was "public work" within General Municipal Law § 103 (1). Given that determination, which is dispositive, we do not reach the second, bypass authority issue.

Resolution of the law question properly begins with the facts at issue. Beneath the streets of New York City lie miles and miles of gas pipelines, water, steam and sewage conduits, electrical wiring, and telephone and television cables. When the City undertakes a street reconstruction project, these subsurface facilities — crucial components of a system that delivers vital utility services — often stand in the path of the City's proposed work, and measures must be taken to protect or relocate them. Without such utility work, street reconstructions cannot proceed. By the same token, but for the City street construction, the incidental utility work would not be necessary.

In general, utility companies have a legal duty to ensure the continuation of their services by arranging and paying for this type of work, referred to as "utility interference work" because it prevents construction efforts from interfering with utility lifelines located under affected streets. Prior to 1992, street reconstruction contracts let out for bid by the City did not include provision for the performance of utility interference work. Rather, following the City's award of a contract for the street reconstruction work, notices would be issued to the utility companies, informing them that their subsurface facilities needed to be protected or relocated in order for the City's project to go forward.

As described in City affidavits, and undisputed by petitioner, the utility companies found it impractical and prohibitively expensive to hire separate crews for this work. Instead, they separately negotiated agreements for the utility work with the contractor awarded the City's street reconstruction contract. The result, however, was that the City's work was often substantially delayed. Piecemeal contract negotiations between the City work contractor and the utilities slowed the progress of projects, as did disputes among the parties during the work. These conflicts often centered on the extent, impact and value of the utility interference work, as well as the actual time required to clear the interferences. Because these considerations had not been included in the City's contract, contractors often requested, and were granted, extensions of time due to the "extra work." As a result, on some major reconstruction projects the City was compelled to extend completion dates in order to accommodate the utility interference work, adding cost and public inconvenience.

This system, additionally, at times imposed excessive costs upon the utility companies, which they then passed on to their customers. Aware that they represented the utility companies' most practical means of accomplishing the required utility work, the City work contractors held a superior bargaining position, presenting an opportunity for gouging the companies for the necessary utility work. The utility companies, with no viable alternative, were compelled to pay.

In 1992, the City took action in its own interest. Seeking to eliminate unnecessary delays, uncertainties and costs surrounding street reconstruction projects, the City entered into a "Joint Bidding Agreement" (the Agreement) with Consolidated Edison, New York Telephone and Empire City Subway. The Agreement provides that, for certain City construction projects (mutually agreed upon between the City and the utility companies which are parties to the Agreement), the necessary utility interference work is to be included in the public contracts when they are let out for bid. The City is then required to award the contracts to the lowest responsible bidder for the entire project — including both the construction work and the utility interference work. Under the terms of the Agreement, the City must pay the successful contractors for the entire project, including the necessary utility interference work, and in turn the utility companies must compensate the City for the bid amounts attributable to the utility interference work, plus a contract administration charge of 5%.

Pursuant to the Agreement, in 1996 the City invited bids on three street reconstruction contracts. The specifications notified bidders that utility interference work had been included in the contracts and that the bids would be compared on the basis of total price. Although petitioner was the low bidder on the construction portions of each project, it had the highest total bid for all three contracts. This irregular outcome was attributable to petitioner's high bids on the utility work required under each contract. Indeed, petitioner's bid for the utility work for one of the projects — the Brookline Boulevard contract — was more than 15 times higher than the other nine bids submitted for the project.

Under the Agreement, the lowest total bidder for each of the three projects was to be compensated for its work by the City. In turn, the utility companies agreed to reimburse the City for the cost of the utility interference work, as well as the difference between the actual street reconstruction work cost and the lowest bid received for that work. The terms of the arrangement were memorialized in commitment letters executed by the utility companies.

The legal issue presented here is whether the three contracts providing for both the street reconstruction work and the incidental utility interference work were properly awarded in accordance with the competitive bidding requirements of General Municipal Law § 103 (1). We conclude that they were.

Competitive bidding on public contracts has long formed a part of New York law, having originated in local charters and ordinances as far back as the 1850's ( see, e.g., Brady v. Mayor of City of N.Y., 20 N.Y. 312; People ex rel. Smith v. Flagg, 17 N.Y. 584). In 1953 the Legislature enacted General Municipal Law § 103 to codify the diverse legislation that was then on the books regarding competitive bidding, and declared:

"this article shall be construed in the negotiation of contracts for public works and public purchases to which political subdivisions or [any] district therein is a party so as to assure the prudent and economical use of public moneys for the benefit of all the inhabitants of the state and to facilitate the acquisition of facilities and commodities of maximum quality at the lowest possible cost" (General Municipal Law § 100-a).

To that end, section 103(1) of the General Municipal Law provides that all contracts for "public work" involving an expenditure of more than $20,000 shall be awarded to the lowest responsible bidder. The majority concludes that the contracts under review here cannot be awarded pursuant to the competitive bidding requirements of General Municipal Law § 103 (1) because the utility interference work included in those contracts does not constitute "public work." We disagree.

Neither the General Municipal Law nor its legislative history defines the term "public work." This Court has, however, previously determined when an agreement involving both municipal and private work should be considered a contract for a "public work" under the competitive bidding statute. Our test for determining a "public work" in that context should control here.

As we held in Matter of Exley v. Village of Endicott ( 51 N.Y.2d 426, 432), where a contract has some attributes that could be subject to public bidding requirements and some that would traditionally be exempt from the competitive bidding statute, it is "the total character of the arrangement which controls." At issue in Exley was whether a municipality had violated General Municipal Law § 103 (1) by failing to offer New York Telephone's competitors the opportunity to bid for the right to provide a phone system. Although the arrangement between New York Telephone and the municipality was seemingly in the form of a lease, the contract also had elements of a sale "purchase contract" subject to competitive bidding requirements. To determine whether this "hybrid" agreement fell within the scope of General Municipal Law § 103 (1), the Court reviewed its terms and conditions and ascertained that its "total character" was "in the nature of a true lease" and therefore "not within the ambit of the competitive bidding statute" ( id., at 433).

That same test was applied in Matter of Citiwide News v. New York City Tr. Auth. ( 62 N.Y.2d 464), where this Court again had to determine whether an agreement providing for the performance of both private work (a license to install, operate and maintain newsstands) and public work (the construction of newsstands) was subject to the competitive bidding statute. Finding that the focus and purpose of the agreement was "to provide for the maintenance and operation of newsstands in the subway system, "the Court concluded that the "total character of the arrangement" was that of a private license agreement exempt from section 103(1)'s requirements ( id., at 471-472, 473). The fact that, in addition to payment of license compensation fees in excess of $60 million, proper performance of the agreement required $2 million worth of work rehabilitating City-owned facilities and constructing newsstands on City property, did not transform its essential character from that of a license agreement into a "public work" ( id., at 473). The Court most recently applied that same test in Matter of AT/Comm, Inc. v. Tufo ( 86 N.Y.2d 1) to determine whether a contract for the installation of an electronic toll-collection service should have been subject to the public bidding requirements of Public Authorities Law § 359.

Here the total character of the arrangement is of a "public work" nature. The single, overriding goal of the contracts at issue is to reconstruct the City's streets. The incidental utility interference work — less than 10% of the cost of the street reconstruction projects — is a necessary component of that work and does not alter the public purpose of the projects. The utility interference work is not an end unto itself, but merely a necessary means to achieve the public purpose. Indeed, the utility interference work has no independent usefulness to the City or the utility companies.

Nor does the fact that the law requires the utility companies, and not the City, to pay for the interference work determine the nature of that work. Although the majority, citing Citiwide (supra) and Matter of Signacon Controls v. Mulroy ( 32 N.Y.2d 410), stresses that a key factor in determining what constitutes a contract for "public work" is whether it is funded out of the public coffers, the "expenditure of public funds, direct or indirect, * * * is not sufficient by itself to trigger the requirements of [the competitive bidding statute]" ( Matter of Citiwide News v. New York City Tr. Auth., 62 N.Y.2d at 471, supra; see also, Matter of Signacon Controls v. Mulroy, 32 N.Y.2d at 416, supra; 19 Opns St Comp, 1963 No. 63-226, at 164 [construction of village water system on property owned or leased by village is subject to competitive bidding even though the cost of such facilities will be paid either by reimbursement or directly by a private utility company]). Indeed, as we recognized in Signacon itself, the fact that a large portion of the costs of a municipal fire control system were to be paid by parties other than the municipality did not remove the contract for that system from the realm of section 103 (1)'s bidding requirements ( 32 N.Y.2d at 415, supra). Regardless of ultimate responsibility for funding, the utility interference work at issue here is undeniably an integral, necessary — though incidental — component of the City street reconstruction project, and therefore may qualify as a "public work" subject to the competitive bidding statutes.

Nor does the Gas Facility Cost Allocation Act (the GFCAA) (L 1988, ch 357) signal that only the Legislature can authorize the City to make utility interference work part of a "public work" contract (majority opn, at 259-260). Significantly, the GFCAA authorized the City to enter into complex agreements with gas utilities for the purpose of sharing the costs of gas line interference work necessary to perform City water and sewer projects. The legislative history reveals that the GFCAA was the end product of long-running negotiations between the City and Brooklyn Union Gas over who should bear the cost of such gas line interference work. The GFCAA replaced the common-law rule requiring gas utilities to pay for the costs of the interference work and allowed an agreement between the City and Brooklyn Union Gas — establishing "a roughly 50%-50% division of costs" between them — to go forward (Bill Jacket, L 1988, ch 357, Mem of Legislative Representative James Brenner, Office of Mayor of City of N.Y., reprinted in 1988 McKinney's Session Laws of N.Y. at 2030; Letter of Assemblyman G. Oliver Koppell; Mem of New York State Department of Public Service).
The agreements at issue in this case do not contemplate a cost-sharing scheme, nor do they shift the financial responsibility for the utility interference work, which, by law, must be borne by the utility companies. Indeed the utility companies not only remain responsible for the cost of the interference work but must also compensate the City for the difference between the actual cost of the reconstruction portion of the contract and the low bid submitted for that work.

We see no material distinction between this case and the prior "hybrid" contract cases in which this Court has consistently looked to the total character of the arrangement in order to determine the relevance of section 103(1). Were the Court's clear, consistent test applied, the Appellate Division order would be affirmed. The majority's contrary conclusion is, quite frankly, not only difficult to comprehend on the facts presented but also leaves uncertain for the future just when our "total character of the arrangement" test remains relevant.

In the end, the majority's conclusion rests entirely on dire predictions which are wholly without basis.

First, on the law, it is a curious argument that subjecting these City street reconstruction projects to competitive bidding as public works under General Municipal Law § 103 (1) — as we would do — multiplies the opportunities for corruption, fraud and favoritism. The opposite is true. As is plain from the majority's own references, the underlying purpose of such bidding is to safeguard the public interest ( see, e.g., majority opn, at 256); the public bidding requirements are more, not less, onerous to assure that objective ( see, e.g., majority opn, at 257-258).

The majority's reliance on this Court's fraud discussion in Signacon ( 32 N.Y.2d 410, supra) is illustrative (majority opn, at 260-261). There, the municipality sought to circumvent compliance with General Municipal Law § 103 (1) by characterizing an agreement as a "gift" and awarding it to a private contractor without competitive bidding. The Court, however, concluded that the arrangement opened the door to fraud, corruption and favoritism. Noting that "[o]ne of the purposes of the competitive bidding statutes is to eliminate the opportunity for fraud, favoritism or corruption by office holders," the Court concluded that, because the contract had been awarded without competitive bidding, a "wayward public official could use the secrecy and ambiguity inherent in any agreement not requiring public advertising and bidding to do great mischief" ( id., at 415). It was the municipality's failure to submit the contract to the public bidding process that provided "the opportunity for dishonest or unthinking officials to betray their public trust" ( id., at 415-416).

Second, beyond the ample case law establishing the salutary effects of public bidding, on the facts before us there is no sign of any evil at work in this case, nor does the Court identify any. To the contrary, the City and the utility companies in the circumstances presented have a single, common interest, which is that the work — incidental to City street reconstruction and serving no independent private purpose — be accomplished most economically and most efficiently.

The majority, moreover, makes much of the purported inadequacies of the commitments executed by the utility companies, characterizing them as risky security blankets (majority opn, at 261-262). By signing the commitment letters, the utility companies contractually bound themselves to the terms set forth thereunder, including the obligation to pay "the difference between the overall low bidder's price for the City's share of the work and the lowest price received on the City's share of the work." The majority's perceived risks, again, are unfounded. The utility companies have powerful incentives to assure the success of these arrangements, among them their continuing relations with the City (as owners of the underground pipelines, conduits, wiring and cables) and their desire to avoid reverting to the prior situation. The joint arrangements are advantageous to them as well as to the City.

Finally, there is no foundation for the prediction that these arrangements will have sweeping consequences, and will become the "template for all future multimillion dollar dealings" (majority opn, at 260). The test that defines the matter before us as a "public work" was sufficient in Exley, Citiwide and AT/Comm — and remains sufficient — to identify arrangements that were in fact private. There can be no doubt that the inclusion of utility interference work in the publicly bid reconstruction contracts here is consistent with the public interest and assures "the prudent and economical use of public moneys for the benefit of all the inhabitants of the state" (General Municipal Law § 100-a; see also, Matter of Conduit Found. Corp. v. Metropolitan Transp. Auth., 66 N.Y.2d 144, 148 [public bidding statutes, which were "not enacted to help enrich * * * corporate bidders but, rather, were intended for the benefit of * * * taxpayers," should be "construed and administered 'with sole reference to the public interest.'"]).

By including all necessary work in one contract, the City ensured the timely and efficient completion of the public works projects at the lowest net construction cost available through competitive bidding. The fact that the utility companies also stand to benefit from the inclusion of utility work in these contracts does nothing to diminish the benefits received by City taxpayers. Indeed, allowing contractors to charge utility companies exorbitant rates for interference work necessitated by a public works project disserves the public interest and likely hurts the pocketbooks of millions of City residents who are also ratepayers. We would affirm the Appellate Division order.


Summaries of

Matter of Diamond Asphalt Corp. v. Sander

Court of Appeals of the State of New York
Jul 9, 1998
92 N.Y.2d 244 (N.Y. 1998)
Case details for

Matter of Diamond Asphalt Corp. v. Sander

Case Details

Full title:In the Matter of DIAMOND ASPHALT CORP., Appellant, v. ELLIOT G. SANDER, as…

Court:Court of Appeals of the State of New York

Date published: Jul 9, 1998

Citations

92 N.Y.2d 244 (N.Y. 1998)
700 N.E.2d 1203

Citing Cases

NYRCA Affiliates, LLC v. James

While the Joint Bidding Statute allows the City to include Utility Interference Work in a public contract,…

Gen. Contrs. Assn. v. Tormenta

A company receiving an Order Out Notice from the City may (1) perform the required Interference Work with its…