Appeal from the Supreme Court, Schenectady County (Walsh, Jr., J.).


Respondent is the bargaining agent and representative for police officers employed by petitioner. Pursuant to the terms of its collective bargaining agreement with petitioner, respondent filed a demand for arbitration on behalf of two of petitioner's police officers on May 8, 1987. The demand was filed on behalf of Sergeant J. Hoetker and Patrolman Louis Pardi. Hoetker had filed a grievance based upon Police Chief Richard Nelson's refusal to remove a derogatory letter which had been placed in Hoetker's file following his approval of a police officer's request for personal leave on November 28, 1985. Pardi's grievance was based upon the denial of his request for eight hours of personal leave on November 23, 1984. November 28, 1985 and November 23, 1984 were dates on which the annual Christmas parade was scheduled in the City of Schenectady. Both grievances involved the question of whether personal leave time should be granted during scheduled parade shifts.

Petitioner moved to stay the arbitration of Pardi's grievance and, alternatively, to sever the two grievances and direct that they proceed before different arbitrators. Respondent cross-petitioned for dismissal of the petition and an order compelling arbitration. Supreme Court denied petitioner's application to stay Pardi's grievance, compelled arbitration of that grievance and granted petitioner's request to sever the two grievances. Respondent appeals.

Respondent contends that Supreme Court exceeded its jurisdiction in ordering severance of the two grievances contained in the demand for arbitration. Matters of procedural arbitrability are for the arbitrator to consider along with the substantive issues involved in the arbitration claim (see, Matter of Long Is. Lbr. Co. [Martin], 15 N.Y.2d 380; Matter of Wells Fargo Armored Serv. Corp. [Office Professional Employees Intl. Union], 97 A.D.2d 75, 77). Whether the particular procedure falls within the jurisdiction of the courts or the arbitrators depends upon "whether it is in essence a prerequisite to entry into the arbitration process or a procedural prescription for the management of that process" (Matter of County of Rockland [Primiano Constr. Corp.], 51 N.Y.2d 1, 9). It is clear that courts have power to order consolidation of grievances (Matter of Chariot Textiles Corp. [Wannalancit Textile Co. — Kute Kiddies Coats], 18 N.Y.2d 793) and to sever arbitrable causes of action from nonarbitrable causes of action (Brennan v. A.G. Becker, Inc., 127 A.D.2d 951, 952-953; Harris v. Iannaccone, 107 A.D.2d 429, affd 66 N.Y.2d 728). With respect to the court's power to consolidate arbitration claims, a court is the only practical forum in which to effect a consolidation when arbitration disputes are commenced by separate demands and placed before separate arbitrators. The procedural issue of severance in cases such as Brennan and Harris involved, in essence, a prerequisite to entry into the arbitration process, i.e., whether there was an express and unequivocal agreement to arbitrate the issue.

On this appeal, there is no claim that either of the grievances are nonarbitrable. Where, as here, two grievances are presented to one arbitrator in a joint demand, the arbitrator can address the issues of procedural arbitrability in the management of the arbitration process. In light of the policy that courts should not become involved in the arbitration process until the conclusion of the proceeding (see, Susquehanna Val. Cent. School Dist. v. Susquehanna Val. Teachers' Assn., 101 A.D.2d 933, appeal dismissed 63 N.Y.2d 610) and the fact that the severance issue can be properly addressed by the arbitrator, we conclude that Supreme Court exceeded its power in ordering severance of the grievances.

Order modified, on the law, without costs, by reversing so much thereof as granted petitioner's application to sever the two grievances contained in the demand for arbitration; petitioner's application denied in its entirety; and, as so modified, affirmed. Weiss, J.P., Yesawich, Jr., Levine and Harvey, JJ., concur.


Summaries of

Matter of City of Schenectady

Appellate Division of the Supreme Court of New York, Third Department
Mar 24, 1988
138 A.D.2d 882 (N.Y. App. Div. 1988)
Case details for

Matter of City of Schenectady

Case Details

Full title:In the Matter of the Arbitration between CITY OF SCHENECTADY, Respondent…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Mar 24, 1988

Citations

138 A.D.2d 882 (N.Y. App. Div. 1988)

Citing Cases

Weiss v. Nath

However, courts have the power to sever arbitrable causes of action from nonarbitrable causes of action where…

Ruiz v. Revel Transit Inc.

icably interwoven, the proper course is to stay judicial proceeding? pending completion of the arbitration,…