From Casetext: Smarter Legal Research

Maryland Casualty Co. v. Shafer

Court of Appeal of California, Third District
May 4, 1922
57 Cal.App. 580 (Cal. Ct. App. 1922)

Summary

In Maryland Casualty Co. v. Shafer (1922) 57 Cal.App. 580, 584 [ 208 P. 192], the court stated that a provision in a construction contract with the county "for retention by the county of sufficient funds to pay claimants who filed verified claims... was for the protection of the surety as much as for that of claimants."

Summary of this case from United States Fid. Guar. v. Oak Grove Union SCH

Opinion

Civ. No. 2439.

May 4, 1922.

APPEAL from a portion of a judgment of the Superior Court of Tulare County. T. N. Harvey, Judge. Affirmed.

The facts are stated in the opinion of the court.

Middlecoff, Scott Ham, Farnsworth, McClure Burke, Lewis H. Smith, W. N. Gilliam, J. A. Chase, Marley Fisher, Perry F. Backus, Russell Heid, W. O. Tyler, Scarborough Bowen, Blakeley Hughes and W. C. Hamilton for Appellants.

Bicksler, Smith Parke and Franklin A. Plank for Respondent.


The county of Tulare and the defendant M. T. Shafer, on the 9th of February, 1918, entered into a contract by the terms of which Shafer agreed to construct a concrete highway for the county. Shafer completed the construction of the highway and the same was accepted by the county January 28, 1919. He failed, however, to pay many persons for labor, material, supplies, team hire, and rental of equipment employed, furnished, and used in the construction of the work. He also made assignments to various persons of sums due or to become due under the contract, and which remain unpaid. The plaintiff, as surety of the contractor, brought this action against the county, the contractor, and all claimants under the contract to secure an adjudication of their respective rights in and to the unpaid installments due from the county and the plaintiff's liability under its contracts of suretyship. The various claimants filed cross-complaints setting up their respective claims to the unpaid installments and their rights of recovery against the plaintiff. The county paid into court the balance due under the contract, $12,919.81, to be distributed in such manner and to such parties as the court might adjudge, and none of the parties are now claiming anything against the county. From the judgment rendered, three separate appeals are being prosecuted. This appeal is by Thompson Brothers from that part of the judgment denying recovery against the plaintiff and adjudging that other parties have superior rights to payment out of the unpaid installment.

The contract provides "that the contractor shall pay all bills for labor, team hire, material and supplies contracted for by him on account of the work herein contemplated, when the same becomes due and payable." By the terms of the contract Shafer was required to furnish "a good and sufficient bond and undertaking in the sum of $16,426.55 conditioned for the faithful performance of this contract by the contractor, according to the terms and provisions herein expressed." Pursuant to this requirement, Shafer and the plaintiff executed a "bond for faithful performance of contract" in the usual form, providing, among other things, that the contractor "shall in all things stand to and abide by and well and truly keep and perform the covenants, conditions, stipulations, contracts, agreements and obligations in the foregoing contract, . . . on his part to be kept or performed at the time and in the manner therein specified . . . and shall idemnify and save harmless the said county of Tulare."

[1] It is contended that the plaintiff is liable under the faithful performance bond for the claim of Thompson Brothers. In support of such contention the following cases are cited: French v. Farmer, 178 Cal. 218 [ 172 P. 1102]; Fuller v. Atturas School Dist., 28 Cal.App. 609 [ 153 P. 743]; Callan v. Empire State Surety Co., 20 Cal.App. 483 [ 129 P. 978, 981]. If the faithful performance bond were the only one furnished, appellant's position would seem to be invulnerable, but the contract required and Shafer and the plaintiff executed a separate bond in express compliance with the requirements of the act of 1897 (Stats. 1897, p. 201), and acts amendatory thereof, entitled "An act to secure the payment of the claims of materialmen, mechanics, or laborers, employed by contractors upon state, municipal or other public work."

Liability under a contract of suretyship, as under other contracts, is dependent upon the intention of the parties thereto. In the discussion of a similar question in French v. Farmer, supra, it is said: "If . . . any effect whatever is to be given to this clause in the condition of the bond, it must be held that it was the intention of the parties to benefit such third persons. . . . The courts of Nebraska Missouri, Iowa, Indiana, and Michigan seem to hold to the view that if it can be fairly said from either the contract or the bond, which are to be construed together, that the parties intended to and did agree to pay such third persons, a suit could be brought on such bond by such third person to recover upon the promise so made for his benefit." Here, in compliance with the contract and the statute, a separate bond was given to secure payment of claims of the character under consideration and it would be unreasonable to hold that the parties intended the faithful. performance bond to secure the same claims. The Statute of 1897 (as amended by Stats. 1911, p. 1422) provides that the claimants " shall, within ninety days from the time such contract is completed, file with the . . . board of supervisors . . . a verified statement of such claim." Concededly appellant failed to file such a claim and is therefore precluded from recovering on the bond given pursuant to the requirements of that statute. Such failure affords no ground for relief under the faithful performance bond manifestly intended for a different purpose.

[2] Pursuant to the provisions of subdivision 11 of section 2643 of the Political Code, the contract provides that the county shall retain twenty-five per cent of the estimated value of the work for thirty-five days after the acceptance thereof. The contract further provides that the county "may at its option, retain out of any amounts due the contractor, a sum sufficient to cover and pay any such unpaid bills and claims, provided that sworn statements of said bills and claims have been filed in the office of the board of supervisors on or before the date on which the final payment due the contractor under this contract, shall be made by the first party through its board of supervisors, as hereinafter set forth in article XIV of this contract, and not later than ninety days after the completion and acceptance of the work." As stated, the county retained, under this provision, $12,919.81 due under the contract, that sum being less than twenty-five per cent of the value of the work. The court found that valid claims, duly verified, were filed in due time with the board, aggregating more than the amount retained by the county. Appellant did not so file a verified claim but filed an order, signed by the contractor, for the amount of such claim. It is now contended that appellant was entitled to payment out of the moneys retained by the county and deposited in court as stated; that Shafer's order operated as an assignment of the sum retained by the county to the amount of the order; and that the plaintiff had no right or equity in the fund reserved in so far as it had been assigned by Shafer. In support of such contention appellant relies on the cases of Adamson v. Paonessa, 180 Cal. 157 [ 179 P. 880], and American Surety Co. v. Empire Securities Co., 185 Cal. 586 [ 197 P. 941]. The first case relates to a contract for street work under the Improvement Act of 1911 (Stats. 1911, p. 730), and the latter to similar work under the Vrooman Act (Stats. 1885, p. 147). In neither case did the contract provide for a reserve fund as in the case at bar. In Adamson v. Paonessa, supra, this distinction is clearly pointed out by the court. The provision of the contract for the retention of twenty-five per cent of the value of the work until the completion thereof became a part of the contract of suretyship and was as much for the indemnity of the surety as for the county. ( Prairie State Bank v. United States, 164 U.S. 227 [41 L.Ed. 412, 17 Sup. Ct., Rep. 142, see, also, Rose's U.S. Notes].) The further provision for retention by the county of sufficient funds to pay claimants who filed verified claims was equally a part of plaintiff's contract and was for the protection of the surety as much as for that of claimants. To the extent that such provision was observed, the liability of the surety was lessened. The fund retained was beyond the control of Shafer and no assignment by him could prejudice the rights of the parties for whose benefit the fund was created. To hold otherwise would be to nullify the stipulation of the contract for the retention of the fund and to destroy the security intended for the benefit of claimants bringing themselves within its terms as well as for the protection of the surety. ( Wasco County v. New England Equitable Ins. Co., 88 Or. 465 [Ann. Cas. 1918E, 656, L. R. A. 1918D, 732, 172 P. 126]; In re Scofield Co., 215 Fed. 45 [131 C. C. A. 353]; Derby v. United States F. G. Co., 87 Or. 34 [169 P. 500]; Henningsen v. United States F. G. Co., 208 U.S. 404 [52 L.Ed. 547, 28 Sup. Ct. Rep. 389, see, also, Rose's U.S. Notes]; Columbia Digger Co. v. Rector, 215 Fed. 618; Greenville Bank v. Lawrence, 76 Fed. 545 [22 C. C. A. 646].)

The court found that valid claims amounting to $14,419.50 were duly verified and filed with the board of supervisors and that such claimants in due time filed cross-complaints in this action and were entitled to judgment against the plaintiff for the respective amounts of their claims and that the plaintiff is entitled to have the whole of said $12,919.81 applied to the payment of such claims. The judgment against plaintiff awards such claimants the amounts of their respective claims and directs the clerk to pay them the amount of said fund in the proportion of their claims and on payment to the clerk by plaintiff of the remainder of the judgment, to pay the claimants in full upon satisfaction of the judgment by them. The judgment further provides that, upon payment by plaintiff to any of said claimants of the sums awarded them, the clerk shall pay plaintiff such part of the $12,919.81 as said claimants otherwise would be entitled to receive. Appellant contends that the findings are insufficient to support the judgment. Whatever grounds of objection may be available to other parties defendant, the findings clearly show that appellant, by reason of failure to file a verified statement of claim with the board of supervisors as provided by the contract, is not entitled to participate in the distribution of the fund reserved and, therefore, cannot be heard to complain of the disposition made thereof.

That part of the judgment appealed from is affirmed.

Hart, J., and Burnett, J., concurred.

A petition for a rehearing of this cause was denied by the district court of appeal on June 3, 1922, and a petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on July 3, 1922.

All the Justices concurred, except Wilbur, J., who dissented, and Lawlor, J., and Lennon, J., who were absent.

Shurtleff, J., was also absent and Richards, J., pro tem., was acting.


Summaries of

Maryland Casualty Co. v. Shafer

Court of Appeal of California, Third District
May 4, 1922
57 Cal.App. 580 (Cal. Ct. App. 1922)

In Maryland Casualty Co. v. Shafer (1922) 57 Cal.App. 580, 584 [ 208 P. 192], the court stated that a provision in a construction contract with the county "for retention by the county of sufficient funds to pay claimants who filed verified claims... was for the protection of the surety as much as for that of claimants."

Summary of this case from United States Fid. Guar. v. Oak Grove Union SCH
Case details for

Maryland Casualty Co. v. Shafer

Case Details

Full title:MARYLAND CASUALTY COMPANY (a Corporation), Respondent, v. M. T. SHAFER et…

Court:Court of Appeal of California, Third District

Date published: May 4, 1922

Citations

57 Cal.App. 580 (Cal. Ct. App. 1922)
208 P. 192

Citing Cases

United States Fid. Guar. v. Oak Grove Union SCH

(See Street v. Pacific Indemnity Co., supra, 79 F.2d 68, which so interprets section 2848, Civil Code; Castro…

Summerbell v. Weller

In view of the requirement and existence of the separate statutory bond herein before described we think that…