From Casetext: Smarter Legal Research

Mann et al. v. Schnarr

Supreme Court of Indiana
Nov 16, 1950
228 Ind. 654 (Ind. 1950)

Summary

In Mann, a contractor agreed to provide materials, labor, and supervisory services for the construction of a building pursuant to a "cost plus" contract which entitled him to payment for "materials and labor plus ten percent (10%) thereof."

Summary of this case from Premier Investments v. Suites of America

Opinion

No. 28,729.

Filed November 16, 1950.

1. APPEAL — Evidence — Weight and Sufficiency — Action for Breach of Building Contract and To Foreclose Mechanic's Lien — Evidence Sufficient To Sustain Verdict Against One Co-Defendant — Other Defendants' Interest Subject to Lien. — On appeal in an action by a contractor for breach of a contract for the construction of a building and to foreclose a mechanic's lien, Supreme Court found that the evidence was sufficient to sustain a personal judgment against only one of two defendants who owned the property as tenants in common, but that the interest of both could have been properly found to be subject to the mechanic's lien. Burns' 1940 Replacement, § 43-701. p. 662.

2. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost Plus Contracts — Provisions Not Necessarily Covered by Lien Statute. — All of the items which might properly be embraced within the provisions of a cost plus construction contract do not necessarily constitute labor, materials or machinery under the provisions of the mechanic's lien statute. Burns' 1940 Replacement, § 43-701. p. 662.

3. MECHANICS' LIENS — Right to Lien — Right Depends on Debt Arising From Contract. — A mechanic's lien cannot exist without the existence of the debt it secures which must arise out of a contract, express or implied. Burns' 1940 Replacement, § 43-701. p. 662.

4. MECHANICS' LIENS — Right to Lien — Right Is In Rem — No Personal Judgment Necessary. — The right to a mechanic's lien is one in rem and the lien may be declared and foreclosed without the recovery of a personal judgment. Burns' 1940 Replacement, § 43-701. p. 662.

5. APPEAL — Trial — Pleading — Complaint — Evidence — Variance — No Fatal Variance — Complaint Deemed Amended. — On appeal in an action for breach of a construction contract and for foreclosure of a mechanic's lien, where the complaint stated the contract was for "labor and materials plus 10 per cent" but the evidence showed the agreement to be for "cost, plus 10 per cent," the proof did not constitute a fatal variance, and the Supreme Court would regard the complaint amended to conform with the evidence. Burns' 1946 Replacement, § 2-3231. p. 663.

6. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost Plus Contracts — Lien Secures Only Items for Labor or Materials. — In an action by a contractor for breach of a cost plus construction contract and for foreclosure of a mechanic's lien, the lien could only secure such items of the contract as were for labor or materials even though the contractor was entitled to recover for every item under the contract which the evidence showed to be an essential cost. Burns' 1940 Replacement, § 43-701. p. 663.

7. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Personal Items — Not Secured by Lien. — Under a cost plus construction contract, items essentially personal in character are not materials under the mechanic's lien statute, in the absence of an intention that they are to be attached as permanent fixtures to the real estate. Burns' 1940 Replacement, § 43-701. p. 665.

8. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Superintendents and Architects Are Laborers Under Lien Statute. — The superintendent of a construction job and the architect who draws the plans are laborers under the mechanic's lien statute because one who labors with body or mind or both is a laborer. Burns' 1940 Replacement, § 43-701. p. 665.

9. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost Plus Contracts — Contractor's Profit Secured by Lien. — Under a construction contract for cost plus ten per cent, the ten per cent is regarded as compensation for the labor performed by the contractor himself and is secured by a mechanic's lien. Burns' 1940 Replacement, § 43-701. p. 665.

10. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost of Transportation of Materials and Dirt Could Be Secured by Lien. — Transportation costs for hauling materials and dirt could be so inseparably connected with the construction of a building that they would be included in the cost and would be labor for which a mechanic's lien could be acquired. Burns' 1940 Replacement, § 43-701. p. 666.

11. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost of Ice — Not Secured by Lien. — Under a cost plus construction contract the cost of ice provided by the contractor was not secured by a mechanic's lien as labor, even if used to cool drinking water for laborers, or as material, even if used to test the cold storage room. Burns' 1940 Replacement, § 43-701. p. 666.

12. EVIDENCE — Judicial Notice — Furnishing of Drinking Water by Contractor. — On appeal in an action for the breach of a cost plus construction contract, Supreme Court took judicial notice of the fact that it is customary for a construction contractor to furnish drinking water to his laborers in determining that the cost of ice could properly be allowed as a cost of the contract. p. 666.

13. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contracts — Workmen's Compensation Insurance, Employment Compensation Payments and Social Security Tax Are Costs. — Under a cost plus construction contract, workmen's compensation insurance, employment compensation payments and social security tax are allowable as costs since the amount of each depends on the payroll. p. 667.

14. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contracts — Gross Income Tax Is Not a Cost. — Under a cost plus construction contract, the Indiana gross income tax is not allowable as a cost because it is a direct tax on the contractor. p. 667.

15. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Workmen's Compensation, Employment Compensation, Social Security and Gross Income Tax Are Not Labor or Material Under Lien Statute. — Neither workmen's compensation insurance, employment compensation payments, social security tax nor the Indiana gross income tax is an item of labor or material under the mechanic's lien statute in a cost plus construction contract. Burns' 1940 Replacement, § 43-701. p. 667.

16. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contracts — Lights and Water — Properly Allowable as Costs. — Under a cost plus construction contract, items for light and water would be properly allowed as costs if the current was required to furnish light for the workmen and the water was used for drinking purposes or for mixing cement and water. p. 667.

17. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Light and Water Are Not Materials Under Lien Statute — Water Might Be Material If Used in Concrete or Mortar. — Under a cost plus construction contract, an item for lights would not be a material under the mechanic's lien statute, even though the current was required to furnish light for the workmen, nor would an item for water if the water were used for drinking purposes; however water used for mixing concrete or mortar would properly be a part of the material cost. Burns' 1940 Replacement, § 43-701. p. 667.

18. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Phone Calls and Telegrams Are Not Secured by Lien. — Under a cost plus construction contract, items for long distance phone calls and telegrams, although they could conceivably be direct costs, could in no event be secured by a mechanic's lien as a charge for materials. Burns' 1940 Replacement, § 43-701. p. 667.

19. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contracts — Rental for Concrete Mixer Allowable as Cost — Mechanics' Liens — Value of Work Secured by Lien. — Under a cost plus construction contract an item for a rental of a concrete mixer, if reasonable, would be allowable as a cost, and, since the machine is a labor saving device, the value of the work done by it would be secured by a mechanic's lien as a labor charge. Burns' 1940 Replacement, § 43-701. p. 668.

20. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Rental for Burlap Is Not Labor or Material Under Lien Statute. — Under a cost plus construction contract, an item for the rental of 200 pounds of burlap, although a direct operating cost if used for curing cement, is neither a cost of labor or of materials under the mechanic's lien statute. Burns' 1940 Replacement, § 43-701. p. 668.

21. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contract — Purchase of Broom Not Allowable as Cost — Mechanics' Liens — Broom Is Not Material Under Lien Statute. — Under a cost plus construction contract an item for the purchase of a broom is not allowable as a cost nor is it a material under the mechanic's lien statute, for brooms fall within the classification of small tools which the contractor should furnish. Burns' 1940 Replacement, § 43-701. p. 668.

22. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Cost of Light Bulbs Not Secured by Lien. — In an action for breach of a cost plus construction contract and to foreclose a mechanic's lien, the cost of a dozen light bulbs could not be secured by a lien because the bulbs were personal property, even though the evidence might show them to be a direct cost under the contract. Burns' 1940 Replacement, § 43-701. p. 668.

23. CONTRACTS — Construction and Operation — Compensation — Contracts for Buildings — Cost Plus Contracts — Charges for Padlock and Twine — Dependent on Evidence. — In an action for the breach of a cost plus construction contract, whether or not the charges for a padlock and some twine should be allowed as costs would depend on the evidence as to how they were used. p. 668.

24. MECHANICS' LIENS — Right to Lien — Services Rendered and Materials Furnished — Padlock and Twine Could Be Secured by Lien If Permanently Attached. — In an action to foreclose a mechanic's lien by a construction contractor, a padlock and some twine could be materials under the lien statute if the evidence showed them to be permanently attached so as to be part of the realty. Burns' 1940 Replacement, § 43-701. p. 668.

25. TENANCY IN COMMON — Rights and Liabilities of Co-Tenants as to Third Persons — Agency Between Co-Tenants — No Implied Agency Arising From Relationship — Co-Tenant May Ratify Contract of Other — Ratification May Be Implied by Active Consent. — While there is no implied agency on the part of one co-tenant in common to contract for or bind the interest of the other, when one co-tenant does contract for improvements on the real estate and the other, knowing of the improvements, makes no objection to those persons furnishing the labor and materials and commits any affirmative act consistent with consent to the improvements, the interest of the latter becomes subject to a mechanic's lien for the labor and materials furnished even though he is not liable on the contract. Burns' 1940 Replacement, § 43-701. p. 668.

26. MECHANICS' LIENS — Right to Lien — Consent of Owner — Implied Consent — Consent of Co-Tenant in Common to Contract Made by Other Co-Tenant. — Where a brother, who owned real estate as a tenant in common with his sister, alone contracted for improvements thereon, but the sister conferred several times with the contractor, received statements of labor and materials furnished, once objected to the high cost, and signed several checks in part payment, her acts were sufficient to bind her interest and make it subject to a mechanic's lien for the reasonable value of labor, materials and the contractor's services up to the contract price, notwithstanding the fact that she was not personally liable on the contract. Burns' 1940 Replacement, § 43-701. p. 668.

27. MECHANICS' LIENS — Proceedings To Perfect Lien — Notice to Owner — Form and Requisites — Mistake in Name — Property Sufficiently Identified — Notice Not Defective. — In an action against Nettie E. Bass as a tenant in common to foreclose a mechanic's lien, the statutory notice naming the owner as Nellie E. Bass was not so defective as to render her interest not subject to the lien where the property was sufficiently described in the notice and the charge in the complaint that Nettie E. Bass and Nellie E. Bass were one and the same person was not denied in the answer. Burns' 1940 Replacement, § 43-701. p. 670.

28. MECHANICS' LIENS — Proceedings To Perfect Lien — Notice to Owner — Form and Requisites — Description of Real Estate — Description Sufficient. — In an action to foreclose a mechanic's lien where the statutory notice described the real estate involved as "Lots 14 and part 13 15," and it was stipulated at the trial that defendants owned "the west 16.32 feet of lot 13, all of lot 14, and the adjoining 23.36 feet of lot 15," the trial court had the right to find the real estate stipulated to be owned by defendants was the same as that subject to the lien, making unnecessary a reformation of the notice. Burns' 1940 Replacement, § 43-701. p. 670.

29. MECHANICS' LIENS — Operation and Effect — Amount and Extent of Lien — Interest Is Secured by Lien. — In an action for breach of a construction contract and to foreclose a mechanic's lien where the contractor rendered a final itemized statement, and payment was unreasonably delayed, interest from the time of the rendition of the itemized statement, being incidental to the principal sum due and unreasonably withheld, was secured by the lien. Burns' 1950 Replacement, § 19-2003; Burns' 1940 Replacement, § 43-701. p. 671.

30. MECHANICS' LIENS — Enforcement — Attorneys' Fees — Judgment for Attorneys' Fees Not Personal. — In an action for breach of a construction contract and to foreclose a mechanic's lien, the trial court erred in finding defendants personally liable for attorneys' fees in spite of an agreement by defendants that the trial court could fix the attorneys' fees, because the judgment for attorneys' fees in a lien enforcement proceeding is not personal but one in rem to be paid out of the proceeds of the sale of the real estate. Burns' 1940 Replacement, § 43-707. p. 671.

From the Vanderburgh Circuit Court, Nat H. Youngblood, Judge.

Action by George E. Schnarr against Clarence E. Mann and Nettie E. Bass to foreclose a mechanic's lien against realty owned by defendants. From a judgment for plaintiff, defendants appeal. (Transferred from the Appellate Court pursuant to § 4-215, Burns' 1946 Replacement.)

Reversed and new trial ordered.

(Superseding the opinion of the Appellate Court reported in 88 N.E.2d 779.)

Milford M. Miller and William C. Welborn, both of Evansville, for appellants.

E. Menzies Lindsey, of Evansville, for appellee.


This is an appeal from a personal judgment against both appellants in the sum of $7,649.29, which included the principal sum of $6,586.58, interest in the sum of $316.41, and an attorney's fee in the sum of $746.30, for the payment of which real estate of appellants was ordered sold on foreclosure of a mechanic's lien. There was no special finding of facts, nor was there any motion to modify the judgment of the trial court, but since the cause must be retried, items which incidently affect the judgment will be considered. Difficult questions have been presented, and we feel constrained to note that we have not had proper assistance from the briefs in the determination of these matters.

The error assigned here is the overruling of a motion for new trial, which stated as causes therefor that (1) the decision of the court was not sustained by sufficient evidence, (2) was contrary to law, and (3) the recovery was too large.

The complaint in substance alleged that on or about May 1, 1946, appellee and appellants entered into a verbal contract by the terms of which appellee was to furnish all materials and labor for the construction of a brick building on appellants' real estate, in consideration of which appellants promised to pay appellee for materials and labor plus 10% thereof; that certain payments were made from time to time, leaving a balance due in the sum of $6,586.58 on which interest was due; that appellee filed a notice of his intention to hold a mechanic's lien which should be foreclosed to pay said sum plus reasonable attorney's fees. The prayer was for a personal judgment against each appellant for principal, interest and attorney's fees and the foreclosure of the lien.

Appellants' first paragraph of answer substantially denied the allegations of the complaint. The second paragraph of answer in substance alleged that (1) appellant Mann and appellee had an express oral contract for the construction of a brick building for $8,000, and (2) an express oral contract for construction of a storage room within the brick building for the sum of $2,500, and (3) an express oral contract for the construction of a garage and driveway for the total sum of $1,150; and that appellants had overpaid appellee in the sum of $1,051.57 for which recovery was prayed. The reply to this second paragraph of answer denied the allegations, except payment in the sum of $10,020.96.

Appellants also filed a counter-claim setting up the same express oral contracts alleged in their second paragraph of answer, overpayment, and defective workmanship for which recovery was prayed in the sum of $2,500. Appellee's answer to the counter-claim in substance admitted the amount paid to him, but denied all other allegations.

The finding of the court was against the appellants on their counter-claim and for the appellee on his complaint. The appellants were brother and sister, and will hereafter 1. sometimes be referred to as such; the appellee was a contractor, who will hereafter at times be so designated. When we consider the evidence most favorable to the prevailing party in the trial court, a personal finding against the brother on the cost plus contract was sustained by sufficient evidence. However, we do not find any fact in evidence or any reasonable inference therefrom which would authorize a personal finding and judgment against the sister, although from the facts in the record and reasonable inferences therefrom the trial court could properly have found that her interest as tenant in common in the real estate was subject to a mechanic's lien.

All the items which might properly be embraced within the provisions of a cost plus contract do not necessarily constitute labor, materials or machinery under the provisions of § 2-4. 43-701, Burns' 1940 Replacement, which grants the statutory right to a mechanic's lien. A lien cannot exist without the existence of a debt which, under the statute, it secures. The debt must arise out of contract, express or implied, but the right to the lien which the section of the statute grants is one in rem, and a lien may be declared and foreclosed without the recovery of a personal judgment. Peck and Wife v. Hensley (1863), 21 Ind. 344, 350. Thus, even though a personal judgment against the sister was not sustained by sufficient evidence, it does not follow that the lien did not attach to her interest in the real estate and be subject to foreclosure by a judgment in rem.

The contractor testified that he had a conversation with the brother in which "I agreed to do the job on the basis of cost, plus 10%. As a stipulated sum, I would not do it. That was 5. agreeable to Mr. Mann." A couple of weeks later the brother asked the contractor when he would get started and there was further conversation about the basis on which the building was to be constructed and it was stated it was to be "cost, plus 10%." Although the complaint stated the agreement was for labor and material plus 10%, the proof did not constitute a fatal variance and on appeal we will regard the complaint amended to conform with the evidence in this respect. Section 2-3231, Burns' 1946 Replacement. Curtis Storage Trans. Co. v. Rosenberg (1939), 106 Ind. App. 622, 21 N.E.2d 440; Esch v. Leithesier (1946), 117 Ind. App. 338, 69 N.E.2d 760. Nor was the recovery on quantum merit instead of an express contract.

Appellants assert that various items which were included in the finding were not costs within the contract, nor materials or labor under the lien statute. The trial court's finding was 6. based upon a cost plus contract, and the contractor was entitled to recover under this contract for every item which the evidence showed to be an essential cost of construction, but the lien could only secure such items as were labor or material under the lien statute.

The contract was general and did not define costs. We do not have the benefit of many cases or authorities on cost plus contracts. See Graske, War Contract Claims, ch. 4, § 44 et seq.; 9 Williston on Contracts (Rev. Ed.), ch. 4, § 44 et seq.; 2 A.L.R. 126; 27 A.L.R. 48. In the well considered case of Lytle, Campbell Co. v. Somers, Fitler Todd Co. (1923), 276 Pa. 409, 120 A. 409, 27 A.L.R. 41, the court construed a construction contract, where the plaintiff was a general contractor principally engaged in repairing, remodeling and altering buildings, with its main office in Pittsburgh, from which it supervised other construction contracts being performed at the same time. The contract under consideration provided for compensation "on a time and material basis, with ten per cent (10%) profit as compensation to the contractor, the records of the cost to be kept at all times in such a manner as to be checked and audited by the owners." The court clearly distinguished between overhead charges and operating costs. The court held that operating charges were items inseparably connected with the productive end and contained "all elements of labor and materials" and were "capable of being ascertained by those dealing with" the contractor. On the other hand, overhead, or general expense, which included salaries of executive or administrative officials, interest charges for floating bonds, carrying charges, depreciation, taxes and general office expense could not be allowed as an operating charge in a cost plus contract, in the absence of language bringing it within the term costs. In Lovell v. United States (1912), 47 Ct. of Cl. 361, the court held that the words "actual necessary cost" for extra work under paragraph 24 of the written contract, included liability insurance of laborers, depreciation of the plant, fixed charges and depreciation of warehouses, under the construction given the contract by the parties before the work was undertaken, although items for loss of board of men which were incurred to prevent a pay increase was not allowable as a cost item. In James Stewart Co. v. United States (1924), 59 Ct. of Cl. 295, the court held that the employment of expediters, war taxes on freight bills, telegrams, express charges and passenger fares incurred in the purchase of material and performance of the contract were allowable as costs after being agreed to and approved by the officer in charge of the work.

Different considerations are involved in determining whether items properly costs are within the definition of labor or materials of the lien statute. If articles are essentially 7-9. personal in character, and in the absence of an intention that they are to be attached as permanent fixtures to the real estate, they are not materials under the lien statute. Menzenberger v. American State Bank, Inc. (1935), 101 Ind. App. 600, 198 N.E. 819. However, the work and labor of superintending a construction job enters into the lien. Ferguson v. Despo (1893), 8 Ind. App. 523, 34 N.E. 575. In Beeson v. Overpeck (1942), 112 Ind. App. 195, 44 N.E.2d 195, the court reasoned that since "`one who labors with body or mind or both'" is a "`laborer,'" an architect who drew plans and specifications and did supervision of the construction, was a laborer under the lien statute. See 40 C.J. 81. In Wells v. Christian (1906), 165 Ind. 662, 76 N.E. 518, the court said, concerning a contract to lay a seven inch steam pipe from a boiler room into a public street, and to restore the street to its original condition, that "hauling of materials to be used in the performance of the work, and hauling away the surplus earth excavated, were incidental matters inseparably connected with the principal undertaking, and constituted items of labor for which a lien may be acquired." The Court of Appeals of Kentucky in Bond v. W.T. Congleton Co. (1939), 278 Ky. 829, 129 S.W.2d 570, considered a case very similar to the facts involved in this appeal. The contractor had an agreement with the owner for the construction of a building on his land under an agreement "to pay therefor the actual cost of labor and materials and, in addition thereto, 10 per cent of the total aggregate thereof." The court, in holding the 10 per cent to be secured by the lien, said:

"The contractor himself necessarily performs labor in the purchasing of and paying for material and in furnishing and paying for the necessary labor in the construction of a building and it appears reasonable to us that labor thus performed by the contractor is lienable to the same extent as any other labor that goes into the building where the contract provides for the payment of a definite percentage as compensation for this labor to be performed by the contractor.

"We reach the conclusion that appellee's claim for 10 per cent on the cost of materials and labor is a lienable claim under the statute." (Page 834.)

The brother's interest in the real estate was subject to the mechanic's lien for the cost of labor and materials, plus 10 per cent thereof.

There were a number of items allowed by the trial court for transportation costs in hauling materials and dirt. These could be incidental matters and so inseparably connected with the 10. principal undertaking that they would be included in the cost, as well as being labor for which a lien could be acquired. Wells v. Christian (1906), 165 Ind. 662, 76 N.E.2d 518, supra.

There were six separate items for ice, one being in the sum of $16.20, which were allowed by the trial court. Without further evidence we are unable to determine as to whether some or 11, 12. all of this was properly allowed either as cost or an item of labor or material. If the ice was used to cool the drinking water for the men on the job, it should be allowed as an item of cost, since we take judicial notice that it is customary to furnish drinking water to laborers on construction jobs. However, we do not believe it would be labor under the lien statute. If the ice was used to test the cold storage room it would not be a material under the lien statute.

The trial court included in the finding and judgment $215.12 for Workmen's Compensation insurance, $215.12 for Employment Compensation payments, $71.70 for Social Security tax and 13-15. $71.70 for Gross Income tax to the state. One of the purposes of the Workmen's Compensation Act is "to transfer from the worker to the industry in which he is employed and ultimately to the consuming public a greater portion of economic loss due to industrial accidents and injuries." 58 Am. Jur. 576, § 2. See In re Duncan (1920), 73 Ind. App. 270, 274, 127 N.E. 289. Its amount depended upon the payroll. This is a direct operating cost and not overhead on this job. Likewise the Employment Compensation payments and the Social Security tax were properly direct operating costs depending upon the payroll. The Gross Income tax paid to the state is a direct tax upon the contractor and not an operating cost, but rather an overhead charge. None of these items is either labor or material under the lien statute.

The items for lights and water would depend upon the evidence. If current was required to furnish light for the workmen it would properly be a direct operating cost, though not a 16, 17. material. If the water was used for drinking purposes it would be an operating cost, but not labor. If the water was used for mixing cement or mortar it would properly be a part of the material cost.

The items for long distance phone calls and telegrams could be direct costs of the particular job if the evidence so 18. disclosed, but in no event could they be secured by the mechanic's lien.

The item for rent of a concrete mixer was obviously for a labor-saving machine. In Potter Mfg. Co. v. A.B. Meyer Co. (1909), 171 Ind. 513, 86 N.E. 837, there was 19-21. a claim made for the rental price of a "Potter trench machine" by the lessor. The court, at page 517, said, "There could be no question that the contractor, J.J. Smith Company [the lessee of the machine], might have acquired a lien to the extent of the work done, including that done by this labor-saving machine." Therefore the rent of this machine, if reasonable, would be a direct operating cost, and the value of the work done by it would be secured by the lien as a labor charge. However, the rent of 200 pounds of burlap, if used for curing cement, would be a direct operating cost but neither labor nor material within the lien statute. The purchase price of a broom would fall within the classification of small tools which the contractor should furnish as a part of his services, and not cost or material.

As to whether or not the dozen light bulbs were a direct cost would depend upon the evidence. They were personal property and not properly the subject of a mechanic's lien. Waring v. 22-24. Burke Steel Co., Inc. (1947), 69 N.Y.S. 399. The charges for one padlock and some twine might or might not be direct costs, depending on the evidence. If the padlock were chained permanently to the building so that by intention it became a part of the realty it could be a material. Conceivably twine could be a material going into the building, but if it did not become a permanent part of the building it should be excluded from the lien.

The sister contends that her brother, who was co-tenant in common with her of the real estate, had no authority to contract for her and that her interest in the real estate is not 25, 26. subject to the lien under the evidence. It is true that there is no implied agency on the part of one co-tenant in common to bind the interest or encumber the interest of the other co-tenant. Wiedenhammer v. McAdams (1912), 52 Ind. App. 98, 98 N.E. 883; Metzger v. Huntington T.T. (1894), 139 Ind. 501, 37 N.E. 1084, 39 N.E. 235; Foltz v. Wertz (1885), 103 Ind. 404, 2 N.E. 950. But we think the same principles of law are applicable to this case that have been decided in the case of a husband binding his wife's interest in real estate. The case of Capp v. Stewart (1872), 38 Ind. 479, wherein the court laid down the rule that in order for the wife's interest in real estate to be subject to a lien she must have done such acts as would "bind her personally if she were free from coverture," must be held overruled by subsequent cases. It is the law that something more than mere inactive consent is necessary to bind the owner's interest. Snelling, et al. v. Wortman, Rec. (1940), 107 Ind. App. 422, 24 N.E.2d 791. The husband may be the agent for the wife in making an authorized contract, or she may by her acts ratify an unauthorized contract. Or if the wife knows the improvement is being made on the real estate and makes no objection to those furnishing the labor and materials, and does any affirmative act consistent with her consent to the improvement, she consents to the creation of the lien and her interest in the real estate is subject to the lien even though she may not be personally liable on the contract. Dalton v. Tindolph (1882), 87 Ind. 490; Wilson v. Logue (1892), 131 Ind. 191, 30 N.E. 1079; Taggart v. Kem (1899), 22 Ind. App. 271, 53 N.E. 651. The evidence in this case discloses the contract was made by the brother. However, the contractor saw the sister several times in their office, gave her statements of the labor and materials furnished. At one time she objected to the high cost of the job. She signed several checks in part payment of the contract. These acts are sufficient to bind her interest even though we find that under the evidence she is not personally liable on the contract. It would be inequitable to permit her to stand by and make no objection to the construction of the building when she had ample opportunity to do so, and act affirmatively consistent with her consent to the improvement without having her interest in the real estate subject to the lien. Since there was no privity of contract between the contractor and the sister, her interest in the real estate was only subject to a mechanic's lien for the reasonable value of labor and materials, plus the reasonable value of the contractor's services which were labor, not to exceed the contract price of 10 per cent for his services.

She also insists that her interest is not properly subject to the lien, since she was named in the statutory notice as Nellie E. Bass. Rhetorical paragraph two of the complaint 27, 28. charged that the defendant Nettie E. Bass was one and the same person as Nellie E. Bass. The first paragraph of answer did not deny that Nellie E. Bass and Nettie E. Bass were one and the same person. It was stipulated that appellants Clarence J. Mann and Nettie E. Bass were the owners of the real estate at all times involved in the lawsuit and the contractor testified that they were brother and sister and operated the Blue Ribbon Dairy. Notice of the intention to hold a lien was sufficient to identify the land. The owners knew the property intended to be described. Smith v. Newbaur (1896), 144 Ind. 95, 42 N.E. 40, 1094, 33 L.R.A. 685. The notice recited the contractor intended to hold a lien "on Lots 14 and part 13 15, Block 1, in Claremont Place, an addition to the City of Evansville, Indiana." The stipulation at the trial stated that appellants owned real estate in "Vanderburgh County, State of Indiana, to-wit: The west 16.32 feet of lot 13, all of lot 14, and the adjoining 23.36 feet of lot 15, all in block 1 in Claremont Place, an addition to the city of Evansville." From the evidence the court had the right to find this was the real estate subject to the lien and it was not necessary to reform the notice.

The trial court allowed interest on the principal amount remaining due. The contractor had rendered a final itemized statement to the appellants on March 31, 1947, and payment 29. was demanded several times. Section 19-2003, Burns' 1950 Replacement, allows interest after the rendition of such an itemized statement. There was unreasonable delay in the payment. Eastman v. Smith (1914), 56 Ind. App. 621, 105 N.E. 64. The interest, being an incident of the principal sum found remaining due and being withheld by unreasonable delay is secured by the lien. Merritt v. Pearson (1881), 76 Ind. 44.

The motion for a new trial challenged the finding against the defendants that they were personally liable for attorney's fees. It was stipulated by the parties "that the reasonable value 30. of attorney's services in this community and in this Court is at the rate fixed in the schedule of fees by the Evansville Bar Association, and that schedule of fees may be applied by the court in the assessment of any fee for the plaintiff's attorney in this action." This was a binding agreement by appellants that the trial court could fix the attorney's fees according to the bar association rate. Eastman v. Smith (1914), 56 Ind. App. 621, 105 N.E. 64, supra. However, the trial court erred in finding that appellants were personally liable for the attorney's fees. Section 43-707, Burns' 1940 Replacement, provides for recovery of a reasonable attorney's fees "as a part of the judgment in said suit." Hammond Hotel, etc. Co. v. Williams (1931), 95 Ind. App. 506, 176 N.E. 154, 178 N.E. 177; Grant County Lumber Co. v. Marley (1934), 100 Ind. App. 42, 192 N.E. 110. The judgment for attorney's fees is not personal, but in rem to be paid out of the proceeds of the sale of the real estate. Hubbard v. Burnet-Lewis Lumber Co. (1912), 51 Ind. App. 97, 98 N.E. 1011.

Judgment reversed and new trial ordered, with leave to appellee to amend his complaint.

NOTE. — Reported in 95 N.E.2d 138.


Summaries of

Mann et al. v. Schnarr

Supreme Court of Indiana
Nov 16, 1950
228 Ind. 654 (Ind. 1950)

In Mann, a contractor agreed to provide materials, labor, and supervisory services for the construction of a building pursuant to a "cost plus" contract which entitled him to payment for "materials and labor plus ten percent (10%) thereof."

Summary of this case from Premier Investments v. Suites of America

In Mann v. Schnarr (1950), 228 Ind. 654, 95 N.E.2d 138, the court considered the allocation of certain contractor's costs under the mechanic's lien statute.

Summary of this case from United Air Lines, Inc. v. Johnson

discussing Wells v. Christian, 165 Ind. 662, 665, 76 N.E. 518, 519, and Lytle, Campbell Co. v. Somers, Fitler Todd Co., 276 Pa. 409, 120 A. 409

Summary of this case from Ford v. Culp Custom Homes, Inc.

distinguishing in rem recovery which may be had against co-owners of realty not subject to personal judgment when for example contract executed by another co-owner, from in personam recovery, noting in rem judgment against land on lien foreclosure valid against all co-owners nonetheless

Summary of this case from John Wendt Sons v. Edward C. Levy Co.

In Mann, our supreme court held that ice used to cool drinking water for workers would not be labor under the lien statute.

Summary of this case from P P Oil Service Co. v. Bethlehem Steel

In Mann v. Schnarr (1950), 228 Ind. 654, 95 N.E.2d 138, the Indiana Supreme Court held that both interest and attorney's fees were secured by a mechanic's lien and were to be paid out of the proceeds of the sale of the real estate.

Summary of this case from Inter-City Contr. Srvs. v. Consumer Bldg. Indus
Case details for

Mann et al. v. Schnarr

Case Details

Full title:MANN ET AL. v. SCHNARR

Court:Supreme Court of Indiana

Date published: Nov 16, 1950

Citations

228 Ind. 654 (Ind. 1950)
95 N.E.2d 138

Citing Cases

Premier Investments v. Suites of America

Thus, we conclude that the erecting requirement of Indiana Code § 32-8-3-1 is some physical act of labor in…

United Air Lines, Inc. v. Johnson

In Department of Treasury v. Jackson (1941), 110 Ind. App. 36, 43, 37 N.E.2d 31, 34, the court said that the…