From Casetext: Smarter Legal Research

Malloy v. Cotton Mills

Supreme Court of North Carolina
Apr 1, 1903
43 S.E. 951 (N.C. 1903)

Opinion

(Filed 28 April, 1903.)

1. References — Findings of Court — Appeal.

The findings of fact by a referee, supported by evidence and sustained by the trial court, are not reviewable.

2. Contracts — References — Conclusions of Law — Damages.

The findings of fact by the referee in this case sustain the conclusions of law, that the time for the completion of the work was impliedly and necessarily enlarged, that plaintiffs are guilty of no unnecessary delay, that defendant cannot recover damages for failure to complete the work at the time specified, and that the defendant is indebted to plaintiffs in the sum found due by the referee, for work and labor in excavating and lowering the bed of a tail-race.

ACTION by Malloy Boggs against the Lincoln Cotton Mills, heard by Coble, J., and a jury, at September Term, 1902, of LINCOLN. From a judgment for the plaintiffs, the defendant appealed.

(433)

D. W. Robinson for plaintiffs.

Burwell Cansler and C. E. Childs for defendant.


This was an action to recover for work and labor in excavating and lowering the bed of the tail-race for the defendant. The defendant set up a counterclaim for damages caused by delay in completing the work. The appeal was practically narrowed in the argument to the counterclaim.

The briefs and the oral argument on both sides were able, full, and exhaustive, and after fullest consideration we think the referee found upon competent evidence that the defendant was to keep the water pumped out of said race and to keep the same dry and in proper condition for the work during the progress thereof; that the excavation of the tail-race (except as to the wall at the head thereof) was to be from the point where the branch emptied into the race, about 180 feet from the mill, to the point where the race emptied into the river; that the plaintiffs were to build a stone bulkhead at the east end of the dam; the work aforesaid to be done at the rate of $1 per cubic yard for excavating and $6.50 per cubic yard for work on walls; that the defendant (through its general manager) represented that it was only necessary for plaintiffs to excavate the tail-race from the point where the branch empties into the race to the mouth of the river, and that a great part of the bed of the race had been blasted and loosened up and the material could be easily removed, which proved to be incorrect; that plaintiff in making the contract relied upon said representations and inducements, as the water at that time covered and concealed the bed of the race; that the agreement was that the defendant was to pump the water from the race at its own expense; that the paper-writing "Exhibit `A'" contained only a part of the contract between the parties, the rest thereof being in parol and not (434) reduced to writing; that the work on the upper part of the race from the branch to the wheel pit was much more difficult, required more time in proportion, and was not contemplated in the original contract; the defendant accepted and used all of aforesaid work and is still using the same to its great advantage; there is no evidence that the defendant lost any orders on account of mill not beginning work at date first mentioned, and while there was no express stipulation for extension of time by reason of the above circumstances, it was an implied extension and the plaintiffs were not liable for damages for delay which was caused as aforesaid; that while no agreement was proved as to the price of excavation done from the branch to the wheel pit, the referee allowed $1 per cubic yard, on a quantum meruit, being the price agreed on for the other excavations.

The findings of fact by the referee are very full, the above being the most salient and most debated points. There was evidence to sustain each and every finding, and the same having been sustained in the trial court, are not reviewable here. See cases collected Clark's Code (3 Ed.), p. 564.

Upon said findings we must affirm his Honor's judgment sustaining the referee's conclusions of law, that the time for the completion of the work was impliedly and necessarily enlarged, that plaintiffs were guilty of no unnecessary delay, that the defendant cannot recover any damages for work not being completed at the date first specified, and is indebted to the plaintiffs in the sum found to be due by the referee.

Affirmed.

WALKER, J., having been of counsel, did not sit on the hearing of this case.

Cited: Brown v. R. R., 154 N.C. 302; In re Fowler, 156 N.C. 346; Caldwell v. Robinson, 179 N.C. 521.

(435)


Summaries of

Malloy v. Cotton Mills

Supreme Court of North Carolina
Apr 1, 1903
43 S.E. 951 (N.C. 1903)
Case details for

Malloy v. Cotton Mills

Case Details

Full title:MALLOY v. LINCOLN COTTON MILLS

Court:Supreme Court of North Carolina

Date published: Apr 1, 1903

Citations

43 S.E. 951 (N.C. 1903)
132 N.C. 432

Citing Cases

Thompson v. Smith

The referee is selected, in such cases, in place of a jury, and the judge so acts when he reviews the…

Davis v. Davis

This is required not only as a check upon the referee and a safeguard against any possible error on his part,…