From Casetext: Smarter Legal Research

Lauterbach v. Brown

Supreme Court of Wisconsin
May 5, 1959
96 N.W.2d 605 (Wis. 1959)

Opinion

April 8, 1959 —

May 5, 1959.

APPEAL from the judgment of the county court of Sauk county: ROBERT H. GOLLMAR, Judge. Reversed.

For the appellant there was a brief by Callahan Arnold of Columbus, and oral argument by E. Clarke Arnold.

For the respondent there was a brief by Hill, Miller Quale of Baraboo, and oral argument by James H. Hill, Jr.


Action for damages for breach of a contract. The plaintiff and her husband, Charles Lauterbach, entered into a written lease with the defendant for certain land in Columbia county for the purpose of allowing the defendant to remove gravel, sand, and fill dirt therefrom for a period of one year. By this lease the defendant agreed to pay $.08 per cubic yard for gravel and $.05 per cubic yard for sand and fill dirt taken from the premises. The point of starting the operations was to be mutually agreed upon and the defendant was to stop operations in any direction when ordered to do so by the lessors. The plaintiff had the right to check the books of the defendant, who had the right to keep on the premises such men, tools and machinery and other equipment as was necessary, and to store gravel and other material from time to time for removal. All trees necessary to be taken out were to be cut into convenient lengths and delivered to the lessors. There was a provision for extending the lease and for termination on thirty days' written notice. Upon termination of the lease the defendant was required to remove all equipment and processed material from the property within sixty days.

By a written amendment the lease was extended to July 12, 1954, and provisions made for furnishing to the plaintiff a daily record of material taken from the premises and for filling with waste material all water holes which might be made. Damages done to gates or other parts of the property were to be repaired by the defendant at his own expense. The price per cubic yard of gravel was increased to $.12.

The original lease also contained the following paragraph:

"(1) e. It is further understood and agreed by the parties that the party of the second part shall have the right to leave waste material and to dump said waste material along marsh near southwest side of premises."

The case was tried to the court which found the defendant owed the plaintiff a balance of $88.88 for removed material; that substantial quantities of waste material were left in windrows on the floor of the pit and around the upper perimeter of the pit; that the cost of removing said waste material and placing it in the marsh was $4,500; that water holes existed after the defendant ceased using the pit but these were filled by a subsequent tenant without cost to the plaintiff; that trees taken out by the defendant were not cut into lengths as required by the contract but plaintiff incurred no damages as a result. The trial court also found the above-quoted language of the lease relating to waste material was permissive and the failure of the defendant to dump the waste material along the marsh was not a ground for damages.

Judgment was entered for the plaintiff for $88.88 plus costs and disbursements on October 7, 1958. It is from this judgment that the plaintiff appeals.


The only question on this appeal is whether the defendant breached the lease by his failure to dump the waste material along the marsh. In construing a contract the court should give effect to all parts of the instrument and an interpretation which gives a reasonable meaning to all provisions is to be preferred to one which leaves part of the language useless or inexplicable. A construction which renders meaningless a provision expressed in the contract or results in surplusage should be avoided if possible. Knuth v. Fidelity Casualty Co. (1957), 275 Wis. 603, 83 N.W.2d 126; Bank of Cashton v. La Crosse C. S. T. M. I. Co. (1934), 216 Wis. 513, 257 N.W. 451; 3 Williston, Contracts (rev. ed.), p. 1781, sec. 619.

The apparent purpose of the lease in view of its other provisions indicates an intention of the parties that the pit would be left by the defendant in good, workable condition. The defendant was to remove the trees and deliver them in convenient lengths to the plaintiff. Upon termination all equipment and processed material were to be removed. Damage to gates and other parts of the property was to be repaired by the defendant at his own cost, and all water holes to be filled with waste material and made reasonably level.

In his brief the defendant points out most operators pile waste material outside the pit, which is detrimental to the owner of the premises. From this it is argued the quoted language meant the defendant had the right to either leave the waste material in the pit or he could dump it along the marsh, or do both. Leaving the waste material in the pit and around its upper perimeter, where it would later have to be removed upon further working of the pit, is not consistent with the general intention of the parties. Another difficulty with the defendant's construction is that it changes the language of the contract from the conjunctive to the disjunctive. No explanation is given why the defendant should have the right to leave the waste material in the pit and around its perimeter or anywhere on the premises of his choosing rather than dump it along the marsh, which was a part of the leased premises.

The real question is not whether the defendant had a permissive right or a choice between leaving the waste material anywhere on the premises or removing it but is whether, if the defendant did not remove the waste material from the premises, what is his right to leave the waste material on the premises? A fair and reasonable interpretation of the said language of the contract is that the defendant did not have to remove the waste material but if he left it, he had to dump it along the marsh. The language of the contract "shall have the right to leave waste material and to dump said waste material along the marsh . . ." expresses only one right and one idea, not two separate rights or alternative rights or a choice of rights. The phrase "dump said waste material" cannot reasonably be separated from the phrase "leave waste material." The words "said waste material" in the "dump" phrase refer to the identical waste material in the "leave" phrase. Leaving waste material is therefore contingent upon dumping it along the marsh.

This is the only construction of the particular language used which seems reasonable, gives effect to the apparent purpose of the contract, and does not leave any language surplusage.

By the Court. — Judgment appealed is reversed with instructions to the trial court to enter a judgment in favor of the plaintiff in the principal sum of $4,588.88, plus such costs and disbursements as the plaintiff is entitled to.


Summaries of

Lauterbach v. Brown

Supreme Court of Wisconsin
May 5, 1959
96 N.W.2d 605 (Wis. 1959)
Case details for

Lauterbach v. Brown

Case Details

Full title:LAUTERBACH, Appellant, v. BROWN, d/b/a BARABOO CONCRETE PRODUCTS COMPANY…

Court:Supreme Court of Wisconsin

Date published: May 5, 1959

Citations

96 N.W.2d 605 (Wis. 1959)
96 N.W.2d 605

Citing Cases

North Gate Corp. v. National Food Stores

This is the general rule but it has much less force where, as here, a standard form, designed for use in…

Nelson v. Boos

A construction which renders meaningless a provision expressed in the contract or results in surplusage…