From Casetext: Smarter Legal Research

Lake Placid v. Elizabethtown

Appellate Division of the Supreme Court of New York, Third Department
Nov 5, 1987
131 A.D.2d 159 (N.Y. App. Div. 1987)

Summary

denying cause of action

Summary of this case from 2314 Lincoln Pk. West Condo. v. Mann

Opinion

November 5, 1987

Appeal from the Supreme Court, Essex County, Dominick J. Viscardi, J.

Hancock Estabrook (Robert A. Small of counsel), for appellant.

Miller, Mannix, Lemery Pratt (Benjamin R. Pratt, Jr., of counsel), for Elizabethtown Builders, Inc., respondent.

Sugarman, Wallace, Manheim Schoenwald (Timothy J. Perry of counsel), for Wallace, McHarg, Roberts Todd, respondent.


Plaintiff is an unincorporated joint venture, the members of which are owners of residential condominium units in a four-building project in the Village of Lake Placid, Essex County, developed by Lake Placid Company (hereinafter the developer). Plaintiff's members either purchased directly from the developer or are successors in interest to the original purchasers. Plaintiff was formed solely for the purpose of prosecuting damage claims for structural defects and resultant damages with respect to the condominium units against defendant Elizabethtown Builders, Inc., the builder for the project (hereinafter the builder), and defendant Wallace, McHarg, Roberts Todd, the architectural firm (hereinafter the architects) which designed and supervised construction of 3 of the 4 buildings and whose plans were used for the construction of the fourth building. The complaint alleges causes of action for (1) breaches of the construction contract between the developer and the builder, and of the professional architectural contract between the developer and the architects for design and supervision of construction, and (2) negligence against the builder for alleged improper construction and against the architects for alleged improper design and supervision. After joinder of issue and pretrial discovery, defendants successfully moved for summary judgment dismissing the complaint. This appeal by plaintiff ensued.

There should be an affirmance. As to plaintiff's breach of contract claims, it is conceded that, since there was no contractual relationship between plaintiff's members and defendants, recovery is dependent upon a showing that plaintiff's members were third-party beneficiaries of the developer's contracts with defendants. In Fourth Ocean Putnam Corp. v Interstate Wrecking Co. ( 66 N.Y.2d 38, 44), it was held that the Restatement (Second) of Contracts (ch 14 [1979]) essentially summarizes New York law on the subject of contractual liability to third-party beneficiaries. Nonparty enforcement of a contractual promise is limited to an "intended" as contrasted with an "incidental" beneficiary (Restatement [Second] of Contracts §§ 302, 304). One is an intended beneficiary if one's right to performance is "appropriate to effectuate the intention of the parties" to the contract and either the performance will satisfy a money debt obligation of the promisee to the beneficiary or "the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance" (Restatement [Second] of Contracts § 302 [1] [a], [b]). There are no facts set forth in the complaint or plaintiff's papers on the motion establishing the existence of the developer's obligation to pay money to any of plaintiff's members. Likewise, plaintiff has failed to submit any evidence from the contractual language or other circumstances manifesting a mutual intent of the contracting parties to confer rights to performance on the ultimate owners of the units (see, Isbrandtsen Co. v Local 1291 of Intl. Longshoremen's Assn., 204 F.2d 495, 498, n 13; see also, 4 Corbin, Contracts § 776, at 18), nor is there any showing of an intent on the part of the developer to give such nonparties any benefits from the performances promised it by the builder and the architects. Indeed, there is nothing whatsoever in the record to suggest that the developer had in mind anything but the normal business motive to obtain a construction product of sufficient quality for ready marketability of the condominium units to potential customers. Such a motive is clearly not a basis from which to infer the requisite intent of the developer to bestow performance benefits upon the purchasers of the condominium units, let alone their successors (see, Fourth Ocean Putnam Corp. v Interstate Wrecking Co., supra, at 45; Restatement [Second] of Contracts § 302 [1] [b]), and explains why, ordinarily, construction contracts are not construed as conferring third-party beneficiary enforcement rights (see, Port Chester Elec. Constr. Corp. v Atlas, 40 N.Y.2d 652, 656). The fact that, once all of the condominium units have been sold, the developer might not have either a reason to sue for nonperformance or any cognizable damages does not change the result. The developer clearly would have had enforcement rights and remedies for nonperformance during the life of the contract before such sales or, if it was liable for construction defects, after sale. Consequently, this factor, relied upon by plaintiff, is insufficient to demonstrate the existence of an intended third-party beneficiary, as it would in the typical donee or gift beneficiary situation (see, Isbrandtsen Co. v Local 1291 of Intl. Longshoremen's Assn., supra, at 497; cf., Seaver v Ransom, 224 N.Y. 233, 239).

The record does not contain a copy of the written contract between the developer and the builder.

Supreme Court also was correct in granting summary judgment dismissing plaintiff's negligence cause of action. As shown by plaintiff's bill of particulars, the gravamen of its claim relates to a gradual deterioration of parts of the structure primarily due to leakage and seepage damage from the elements. Plaintiff has not alleged or submitted evidence that the defects in the construction of the condominium units created a dangerous condition posing a risk of accidental injury to persons or to property other than the physical deterioration attributable solely to the failure of the products of the construction (the dwelling units) themselves, and has not claimed any damages other than direct and consequential nonaccidental economic loss, i.e., the cost of repair to make the condominium units of expected habitable quality and loss of market value, for which there is no recovery in negligence (see, Butler v Caldwell Cook, 122 A.D.2d 559; Burnell v Morning Star Homes, 114 A.D.2d 657, 659; Hemming v Certainteed Corp., 97 A.D.2d 976, appeal dismissed 61 N.Y.2d 758; Queensbury Union Free School Dist. v Walter Corp., 94 A.D.2d 834; Schiavone Constr. Co. v Elgood Mayo Corp., 81 A.D.2d 221, 227-234 [Silverman, J., dissenting], revd on dissenting opn below 56 N.Y.2d 667; see also, Prosser and Keeton, Torts § 101, at 708-709 [5th ed]).

KANE, J.P., MAIN, MIKOLL and HARVEY, JJ., concur.

Order and judgment affirmed, without costs.


Summaries of

Lake Placid v. Elizabethtown

Appellate Division of the Supreme Court of New York, Third Department
Nov 5, 1987
131 A.D.2d 159 (N.Y. App. Div. 1987)

denying cause of action

Summary of this case from 2314 Lincoln Pk. West Condo. v. Mann

In Lake Placid, owners of condominium units sued the builder and architects of their condominium units, alleging breach of contracts between the project developer and the builder, and between the developer and the architects.

Summary of this case from In re Marcus Lee Associates, L.P.

In Lake Placid Club v. Elizabethtown Builders, Inc., 131 A.D.2d 159, 521 N.Y.S.2d 165 (1987), a condominium owners association brought suit against the builder and the architect of the condominiums for breach of contract and negligence.

Summary of this case from American Towers Owners Ass'n v. CCI Mechanical, Inc.

In Lake Placid Club Attached Lodges v Elizabethtown Bldrs. (131 A.D.2d 159, 161), the court defined an intended beneficiary as one whose "right to performance is 'appropriate to effectuate the intention of the parties' to the contract and either the performance will satisfy a money debt obligation of the promisee to the beneficiary or 'the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance' (Restatement [Second] of Contracts § 302 [1] [a], [b])".

Summary of this case from Alicea v. City of New York
Case details for

Lake Placid v. Elizabethtown

Case Details

Full title:LAKE PLACID CLUB ATTACHED LODGES, Appellant, v. ELIZABETHTOWN BUILDERS…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Nov 5, 1987

Citations

131 A.D.2d 159 (N.Y. App. Div. 1987)
521 N.Y.S.2d 165

Citing Cases

Sands v. Caliendo

One is an intended beneficiary if one's right to performance is appropriate to effectuate the intention of…

TJX Cos. v. Jacobs Eng'g Grp.

The outcome of this motion rests on whether plaintiff's claim is for malpractice or general negligence, and,…