From Casetext: Smarter Legal Research

Koch v. Fishburn

Court of Appeals of Indiana
Jan 29, 1929
164 N.E. 721 (Ind. Ct. App. 1929)

Summary

drilling of wells; well determined to be within statute

Summary of this case from Haimbaugh Landscaping, Inc. v. Jegen

Opinion

No. 13,156.

Filed January 29, 1929. Rehearing denied June 28, 1929. Transfer denied November 15, 1929.

1. MECHANICS' LIENS — For Drilling Well — "Well" Defined. — Under the provision of § 9831 Burns 1926, authorizing a mechanic's lien for "constructing" a well, one who was employed to drill a well on defendant's property at a specified rate per foot, including pipe and material furnished, is entitled to a lien on the land on which the work was done, a "well" being a hole dug in the ground in order to obtain water, though no water is, in fact, found. p. 289.

2. MECHANICS' LIENS — For Drilling for Water — Drilling Abandoned because of Stone. — One employed to drill for water at a specified rate per foot is entitled to compensation for the total number of feet drilled, although the drilling was stopped four different times by striking rock, and the effort to obtain water had to be abandoned because of the rock formation. p. 289.

3. MECHANICS' LIENS — Drilling for Well — Averment of Performance. — A complaint to foreclose a mechanic's lien for labor and material furnished at defendant's request in drilling and exploring for a well on defendant's land, under a contract that plaintiff was to be paid a specified sum per foot, which alleged that plaintiff had drilled a stated number of feet, and there was due him the sum of $310.80 sufficiently averred performance of the contract, as the contract did not require him to find or furnish water. p. 289.

From Marion Circuit Court (39,148); Harry O. Chamberlin, Judge.

Action by Simon Fishburn against Lura J. Koch. From a judgment for plaintiff, the defendant appealed. Affirmed. By the court in banc.

William V. Rooker, for appellant.

Charles L. Tindall and Means Buenting, for appellee.


This is an action by Simon Fishburn against Lura J. Koch to recover an amount alleged to have been owing the plaintiff for drilling and exploring for a well upon real estate owned by the defendant, and to foreclose a mechanic's lien. The complaint alleges that appellant is indebted to appellee for labor and material furnished at appellant's request, in drilling and exploring for a well on certain described real estate owned by appellant, for which drilling the latter agreed to pay appellee $1.40 per foot, including the pipe and material furnished; that, pursuant to such agreement, appellee drilled for a well and furnished 222 feet of pipe therefor; that appellant paid appellee $9, leaving a balance of $310.80 due appellee; that notice of intention to hold a lien was recorded in the recorder's office of the proper county, a copy of such notice being filed with the complaint.

The facts were found specially, and are, in substance, as follows: Appellant was the owner of real estate described in the complaint, on which there was a house, and a dug well about 16 feet deep, in the bottom of which was a bored hole; in June, 1925, appellant employed appellee to construct a driven well on such real estate and agreed to pay him $1.40 per foot for the work, including the cost of the necessary pipe; appellee did not agree or guarantee to discover or produce a supply of water; in July, 1925, he drilled such well, drilling the first hole near the center of the old well to a depth of 35 feet, when he struck stone, rendering it impractical to proceed farther; he then drilled a hole near the side of the bottom of the old well, to a depth of 128 feet, and had to abandon that hole because of rock; he attempted to remove the pipe, but was not able to remove 112 feet of such pipe; he then drilled a third hole outside of the old well to a depth of 34 feet, where he again encountered rock; a fourth hole was then drilled to a depth of 35 feet, and rock rendered it impractical to proceed further with the work; soon thereafter appellee notified appellant that it was not practical to construct a driven well of sufficient depth to furnish an adequate supply of water, after which he abandoned the work; the total number of feet drilled by appellee in his effort to strike water was 232, and he left pipe in the holes to the extent of 145 feet; there was due and owing appellee on the agreement $203, of which $9 had been paid. It is also found that, within 60 days from the time the work was done, appellee filed notice of his intention to hold a mechanic's lien. On these facts the court concluded appellee was entitled to recover $194, plus $75, attorney's fees, and to have a foreclosure of a mechanic's lien. Judgment followed the conclusion of law, hence this appeal.

The contentions in this court are that the court erred in overruling appellant's demurrer to the complaint, and in overruling her motion for a new trial.

Appellant's main objections to this complaint are: (1) That it fails to show that the labor and materials were performed and furnished for any structure or thing for which a mechanic's lien can be had: and (2) that it does not allege a performance by appellee of the condition required of him.

Section 9831 Burns 1926, Acts 1921 p. 135, provides, among other things, that contractors, subcontractors, laborers and persons furnishing material for the construction of a 1-3. well may have a lien on the interest of the owner of the land on which the well is located to the extent of any labor or materials furnished. It is appellant's contention that the statute does not allow a lien for "drilling" for a well, but for the erection and construction of a well. The statute allows a mechanic's lien for labor and materials used in the "erection, altering, repairing or removing" certain designated structures, and for "constructing, altering repairing, or removing" certain designated things, including a well. Under the allegations of the complaint in the instant case, we hold appellant was engaged to construct a well, and that, under the allegations of the complaint, he was entitled to a lien on the land on which the work was performed. Bouvier defines a well as "a hole dug in the ground in order to obtain water." The object may not be attained, but that does not prevent the hole so dug from being a well. The open or dug wells are, as a rule, a thing of the past. Instead of the dug well, we now have the driven or tubular well. If, in the instant case, appellee had dug a hole in the ground in order to obtain water, and, on reaching the rock formation, had abandoned the project, it could not be said he had not dug a well. The fact that he drilled the hole, instead of digging it, does not change the situation. Appellee, in the instant case, drilled four wells, and, under the agreement as set out in the complaint, was entitled to recover the agreed price from the appellee. There is no merit in the contention that the complaint does not allege performance. He did not agree or guarantee to drill a well that would furnish water in any quantity or of any quality. See Littrell v. Wilcox (1891), 11 Mont. 77, 27 P. 394; 9 C.J. 747, § 82, and authorities there cited. The court did not err in overruling the demurrer to the complaint.

The evidence is ample to sustain the finding, and the amount of the recovery is within the evidence.

Judgment affirmed.


Summaries of

Koch v. Fishburn

Court of Appeals of Indiana
Jan 29, 1929
164 N.E. 721 (Ind. Ct. App. 1929)

drilling of wells; well determined to be within statute

Summary of this case from Haimbaugh Landscaping, Inc. v. Jegen
Case details for

Koch v. Fishburn

Case Details

Full title:KOCH v. FISHBURN

Court:Court of Appeals of Indiana

Date published: Jan 29, 1929

Citations

164 N.E. 721 (Ind. Ct. App. 1929)
164 N.E. 721

Citing Cases

Hough v. Zehrner

The rule of ejusdem generis is that general words following an enumeration of particular cases apply only to…

Haimbaugh Landscaping, Inc. v. Jegen

Through the years, Indiana courts interpreted the mechanic's lien statute to include certain services and…