From Casetext: Smarter Legal Research

Jerome Distributors v. B. L. I. Construction Co.

Court of Appeals of Georgia
Jul 12, 1977
142 Ga. App. 776 (Ga. Ct. App. 1977)

Summary

affirming the finding that a subcontract clause requiring final payment within 30 days after completion of the work covered by the subcontract, "written acceptance by the architect, and full payment by owner" was a condition precedent to payment

Summary of this case from Associated Mechanical Corp. v. Martin K. Eby Construction Co.

Opinion

53908.

SUBMITTED MAY 2, 1977.

DECIDED JULY 12, 1977.

Action on account. Fulton State Court. Before Judge Ward.

Kaler, Karesh Frankel, John R. Grimes, for appellant.

Harland, Cashin, Chambers, Davis Doster, Harry L. Cashin, Jr., Thomas J. Venker, for appellee.


This is a suit in which plaintiff as subcontractor sought recovery for the balance due on a construction contract from defendant, the general contractor. The case was tried by the court. It was shown that Article X of the contract provided in part: ". . . Final payment shall be made within 30 days after the completion of the work included in this sub-contract, written acceptance by the architect, and full payment therefor by the owner," and that defendant has not been paid by the owner. The court made findings of fact that the above clause was a condition precedent to payment by the defendant to the plaintiff, that it had not occurred and concluded that plaintiff may not recover for the amount claimed. A judgment for defendant was entered. Held:

1. Plaintiff complains that the judgment is contrary to law and unsupported by evidence because Article X of the contract does not meet the test of clarity, unambiguity and definiteness which is the proper test for determining the existence of a condition precedent under Georgia law. In Peacock Const. Co. v. West, 111 Ga. App. 604 ( 142 S.E.2d 332), we held an identical contract provision to be "plain and unambiguous" and a condition precedent to defendant's liability for the final payment of the contract price. Peacock controls. The evidence authorized the findings of fact, conclusions of law, and the judgment.

2. The other enumerations have no merit.

Judgment affirmed. McMurray and Smith, JJ., concur.

SUBMITTED MAY 2, 1977 — DECIDED JULY 12, 1977.


Summaries of

Jerome Distributors v. B. L. I. Construction Co.

Court of Appeals of Georgia
Jul 12, 1977
142 Ga. App. 776 (Ga. Ct. App. 1977)

affirming the finding that a subcontract clause requiring final payment within 30 days after completion of the work covered by the subcontract, "written acceptance by the architect, and full payment by owner" was a condition precedent to payment

Summary of this case from Associated Mechanical Corp. v. Martin K. Eby Construction Co.
Case details for

Jerome Distributors v. B. L. I. Construction Co.

Case Details

Full title:JEROME DISTRIBUTORS, INC. v. B. L. I. CONSTRUCTION COMPANY, INC

Court:Court of Appeals of Georgia

Date published: Jul 12, 1977

Citations

142 Ga. App. 776 (Ga. Ct. App. 1977)
237 S.E.2d 13

Citing Cases

Associated Mechanical Corp. v. Martin K. Eby Construction Co.

Georgia courts have found that no payment was due a subcontractor where a subcontract was conditioned on…

Wallace v. Bock

The completion of the house, in other words, was a condition precedent to the release of the funds to Bock…