Industrial Engineering Co. v. Republic Storage Co.

Appellate Division of the Supreme Court of New York, First Department
Mar 18, 1927
220 App. Div. 178 (N.Y. App. Div. 1927)

Opinion

March 18, 1927.

Appeal from Supreme Court of New York County.

Leonard G. McAneny of counsel [ Harry N. French with him on the brief; McAneny Bacon, attorneys], for the appellant.

Outerbridge Horsey of counsel [ Thomas S. Fuller with him on the brief; Jackson, Fuller, Nash Brophy, attorneys], for the respondent.


The complaint in this action was dismissed on the defendant's

motion after plaintiff's counsel had opened to the jury. The motion appears to have been granted because in the opinion of the learned trial court the complaint demanded an erroneous measure of damages and the opening of counsel stated the measure of damages which he expected to prove, which the learned court deemed not awardable in this class of action.

The action was brought to recover damages for loss of profits arising out of a breach of a contract under which the plaintiff was to construct a building on the southeast corner of Forty-fifth street and Twelfth avenue, Manhattan, city of New York, and the defendant was to pay the plaintiff the sum of $205,000. After the contract was made, the defendant altered the form of the building somewhat, and, plaintiff claims, without regard to the provisions of the contract covering the rights of the plaintiff in case of such an alteration of the building, engaged another contractor to do the work and prevented the plaintiff from going on with the contract. The plaintiff claimed as damages the difference between the contract price of $205,000 that it would have received under the contract, and the cost it would have been put to in erecting the building as originally planned. The profit on the original job, it is claimed, would have been $15,000.

The exact allegation of the complaint as to damages is as follows: "By reason of defendant's said repudiation and breach of said building contract as modified, plaintiff has been damaged in the sum of Fifteen thousand ($15,000) Dollars, being the difference between the contract price of Two hundred and five thousand ($205,000) Dollars, less such deductions as might be made from said price as set forth in Paragraph VIII hereof, and what it would have cost the plaintiff to perform said building contract as modified."

Nothing is better settled, however, assuming that this be an incorrect measure of damages, than that, if a person has a legal cause of action for some relief, the mere fact that he alleges a wrong measure of damages will not justify a dismissal of his complaint. The defendant here claims, however, that plaintiff's counsel insisted on making proof on this rule of damages, and that, therefore, the learned court was justified in dismissing the complaint on the statement of the nature of the proof to be made of damages. But this seems to us an erroneous view. The learned trial court should have taken the proof, restricting the items to the proper rule, and if then no damages were shown, it might have dismissed the complaint.

Nevertheless, we think the measure of damages set forth in the complaint was, with slight modification hereafter described, the correct measure of loss sustained, and that the learned court, in setting forth what its notion was of the proof required as to damages, stated a correct rule as follows: "The contract which seems to have been breached is that sued upon and the damages to which the plaintiff thereby became entitled was the difference between the contract price and the actual cost of the construction of the building originally contracted for, without regard to the cost of construction of the building which was finally erected;" with the addition that deductions as provided for in Exhibit A annexed to the complaint should have been allowed to defendant. The plaintiff demanded the difference between the contract price of $205,000 (diminished by such deductions as might be made from that figure because of changes in construction that were agreed on at the time the contract was originally made, as set out in a memorandum which is annexed to the complaint) and what it would have cost the plaintiff to erect the structure as originally planned and thus modified. This we conclude is a proper basis for the award of damages.

The ruling dismissing the complaint on the opening of counsel, therefore, was error, and the judgment should be reversed and a new trial ordered, with costs to appellant to abide the event.

DOWLING, P.J., FINCH, O'MALLEY and PROSKAUER, JJ., concur.

Judgment reversed and new trial ordered, with costs to the appellant to abide the event.


Summaries of

Industrial Engineering Co. v. Republic Storage Co.

Appellate Division of the Supreme Court of New York, First Department
Mar 18, 1927
220 App. Div. 178 (N.Y. App. Div. 1927)
Case details for

Industrial Engineering Co. v. Republic Storage Co.

Case Details

Full title:INDUSTRIAL ENGINEERING COMPANY, Appellant, v. REPUBLIC STORAGE COMPANY…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Mar 18, 1927

Citations

220 App. Div. 178 (N.Y. App. Div. 1927)
220 N.Y.S. 623

Citing Cases

United States ex rel. N. Maltese & Sons, Inc. v. Juno Construction Corp.

Under this theory of recovery, Maltese was entitled to recover the contract price less the progress payments…

Prosper Contr. Corp. v. Bd. of Educ

In the interval between the letters plaintiff had performed a substantial amount of work. Defendant refused…