Before the Court in this chapter 11 case are (1) "Debtor's Second Motion for Extension of Time under 11 U.S.C. § 1129(e)," Doc. No. 63 ("Second Extension Motion"), filed by debtor in possession Doug Larsen Construction, Inc. ("Debtor") and (2) approval of Debtor's "Disclosure Statement Dated May 21, 2012," Doc. No. 51 ("Amended Disclosure Statement"). A hearing was held on June 25, 2012, after which the Court took both matters under advisement. Having evaluated the record and arguments presented, the Court enters this Memorandum of Decision, which constitutes the Court's findings of fact and conclusions of law on the matters. Fed. R. Bankr. P. 9014, 7052.

Unless otherwise indicated, all statutory citations in this Decision are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, and all rule references are to the Federal Rules of Bankruptcy Procedure, Rules 1001-9037.

FACTS

On August 22, 2011, Debtor Doug Larsen Construction, Inc., an Idaho corporation, filed a petition for relief under chapter 11 of the Bankruptcy Code. On its petition, Debtor checked the box designating that "Debtor is a small business debtor as defined in 11 U.S.C. § 101(51D)." Doc. No. 1 at 1. Section 101(51D) provides:

The term 'small business debtor' . . . means a person engaged in commercial or business activities . . . that has aggregate noncontingent liquidated secured and unsecured debts as of the date of the filing of the petition or the date of the order for relief in an amount not more than $2,343,300 . . . for a case in which the United States trustee has not appointed under section 1102(a)(1) a committee of unsecured creditors[.]

Debtor's schedules reflected a total amount of debt of $322,450.29. Doc. No. 18.

Debtor filed a disclosure statement and chapter 11 plan on February 26, 2012, Doc. Nos. 35 and 36, respectively. The following day, Debtor filed a "Motion for Extension of Time under 11 U.S.C. § 1129(e)," Doc. No. 40 ("Extension Motion"), requesting the Court extend the deadline for confirming Debtor's plan to July 2, 2012. Debtor noticed the disclosure statement and Extension Motion for an April 9, 2012, hearing. The United States Trustee ("UST") filed an objection to Debtor's disclosure statement. Doc. No. 45.

As discussed in more detail below, § 1129(e) imposes a 45-day deadline for confirming a plan, once filed, in a small business case. That deadline may be extended if certain requirements, found in § 1121(e)(3), are met.

The 45th day after the February 26, 2012, filing of the disclosure statement and plan was April 11, 2012.

Hearing on Debtor's disclosure statement and Extension Motion occurred on April 9. At that hearing, the Court ruled it would deny approval of the disclosure statement and grant the Extension Motion. The minute entry, reflecting the proceedings at the April 9 hearing, stated that "An order is forthcoming." A proposed order denying approval of the disclosure statement was submitted by the UST and subsequently entered by the Court on April 16, 2012. See Doc. No. 48. No order was ever submitted on the Extension Motion, and none was entered.

On May 24, 2012, Debtor filed the Amended Disclosure Statement along with an amended chapter 11 plan. The UST objected to the Amended Disclosure Statement. Doc. No. 60. Among the grounds for denying approval of the Amended Disclosure Statement, the UST asserted that the deadline for Debtor to confirm a plan had lapsed because no order was ever entered on Debtor's Extension Motion and, therefore, the case was subject to dismissal or conversion under this Court's decision in In re Roots Rents, Inc., 420 B.R. 28 (Bankr. D. Idaho 2009). Alternatively, the UST argued that even if Debtor had successfully extended the deadline for confirming its plan to July 2, 2012, there was insufficient time, given the applicable noticing requirements, for Debtor to confirm a plan by that date.

As part of its response to the UST's objection, Debtor filed on Saturday, June 23, the Second Extension Motion, in which it requested a further extension of time for confirming its plan to August 31, 2012. Debtor also filed a motion to shorten time so that the Second Extension Motion could be heard on June 25 in conjunction with the hearing on the Amended Disclosure Statement. Doc. No. 64. The Court granted Debtor's motion to shorten time, and at the June 25 hearing entertained argument on both the Amended Disclosure Statement and the Second Extension Motion.

DISCUSSION AND DISPOSITION

A. Motions for Extension of Time under 11 U.S.C. §§ 1129(e) and 1121(e)(3)

Section 1129(e) instructs that, "[i]n a small business case, the court shall confirm a plan that . . . is filed in accordance with section 1121(e) not later than 45 days after the plan is filed unless the time for confirmation is extended in accordance with section 1121(e)(3)." Section 1121(e)(3), in turn, sets forth the requirements for obtaining an extension of the 45-day deadline imposed by § 1129(e). It provides, in pertinent part:

the time period fixed in section 1129(e) within which the plan shall be confirmed, may be extended only if —
(A) the debtor, after providing notice to parties in interest (including the United States trustee), demonstrates by a preponderance of the evidence that it is more likely than not that the court will confirm a plan within a reasonable period of time;
(B) a new deadline is imposed at the time the extension is granted; and
(C) the order extending time is signed before the existing deadline has expired.
Section 1129(e) imposes a plainly worded, express deadline for confirming a plan in a small business case, which can only be extended by compliance with § 1121(e)(3). Roots Rents, 420 B.R. at 35-37. The three subparts to § 1121(e)(3) are stated in the conjunctive, meaning each must be satisfied. Id. at 36 (citing In re Jayo, 06.3 I.B.C.R. 71, 74, 2006 WL 2433451, at *5 (Bankr. D. Idaho July 28, 2006)).

As a threshold issue, the Court must first determine whether Debtor successfully extended the § 1129(e) deadline with its initial Extension Motion. The UST asserts Debtor failed to meet all the requirements for extending the time to confirm a plan in this small business case. Specifically, the UST contends an order extending time was not signed before the 45-day deadline had expired, as is required by § 1121(e)(3)(C). Therefore, argues the UST, the § 1129(e) deadline — which was never effectively extended — expired on April 11, 2012, leaving nothing for Debtor to extend with its Second Extension Motion. The Court finds the UST's argument persuasive.

Debtor satisfied the first two parts of § 1121(e)(3) at the April 9 Extension Motion hearing. Debtor demonstrated it was more likely than not that the court would confirm a plan within a reasonable period of time, and a new deadline of July 2, 2012, was imposed at that time. However, a proposed order extending the deadline was never submitted, much less signed by the Court and entered, before the existing deadline expired on April 11, 2012. Debtor failed to comply with § 1121(e)(3)(C).

As the party seeking relief from the deadline, it was incumbent upon Debtor to ensure an order came before the Court for signature before the existing deadline expired. Debtor failed to do so and must now bear the consequences under the Code that flow from its inaction. The language of § 1121(e)(3)(C) clearly requires the order extending time be signed before the existing deadline expires in order to extend time for confirming a plan under § 1129(e). That did not occur here. The statutory language is plain and thus must be enforced according to its terms. See Lamie v. United States Tr., 540 U.S. 526, 534 (2004); Roots Rents, 420 B.R. at 34.Because an order extending time was not signed before April 11, 2012, the time for Debtor to confirm its plan under § 1129(e) was never effectively extended in the first instance. Debtor's Second Extension Motion is therefore rendered moot.

See also Roots Rents, 420 B.R. at 37 ("failure to meet the pre-deadline order requirement of § 1121(e)(3)(C) is 'conclusive' on the issue of whether extension can be granted") (citing In re Caring Heart Home Health Corp., 380 B.R. 908 (Bankr. S.D. Fla. 2008)).

Accord Roots Rents, 420 B.R. at 36 (amended plan and amended disclosure statement do not negate failure to properly extend the initial 45-day deadline).

Debtor attempts to skirt the § 1121(e)(3)(C) issue by arguing the minute entry from the April 9 hearing, Doc. No. 47, satisfies that section's requirements. Debtor necessarily argues, then, that the minute entry constituted an "order extending time . . . signed before the existing deadline has expired." This argument is unavailing.

The Ninth Circuit has had occasion to evaluate whether a minute entry constitutes a final order. See Brown v. Wilshire Credit Corp. (In re Brown), 484 F.3d 1116, 1120-23 (9th Cir. 2007). "A disposition is final if it contains 'a complete act of adjudication, that is, a full adjudication of the issues at bar, and clearly evidences the judge's intention that it be the court's final act in the matter.'" Id. at 1120 (quoting In re Slimick, 928 F.2d 304, 307 (9th Cir. 1990)). "Evidence of intent consists of the Order's content and the judge's and parties [sic] conduct." Id. (quoting Slimick, 928 F.2d at 308).

It can also be noted that, in Brown, the bankruptcy judge had actually signed the minute entry - unlike the situation presented here - yet the Circuit still held it was not an order.

The Court's April 9 minute entry did not constitute an order for purposes of § 1121(e)(3), as it was not intended to be the Court's final act on Debtor's Extension Motion. The minute entry on its face contemplated the subsequent entry of a separate order on the Court's ruling. Further, the Court can, with confidence, state that it was not its intention that the minute entry be the final act on the Extension Motion.

The situation here is somewhat unique. Typically, the issue of whether a minute entry constituted a final order arises where one court is evaluating the minute entry of another court. For example, in Brown the Ninth Circuit was interpreting the minute entry of a bankruptcy court to determine whether that minute entry was a final, appealable order. 484 F.3d at 1120. In this case, however, the Court is being asked to consider its own minute entry.

Based on the reasons set forth above, Debtor's Second Extension Motion will be denied.

Additionally, even if the Court were to accept Debtor's arguments and treat the deadline to confirm a plan as having been extended, Debtor did not make on June 26 the showing required by § 1121(e)(3)(A) for the Second Extension Motion — i.e., that it is more likely than not that the Court would confirm a plan in a reasonable time.

B. Approval of Disclosure Statement

Based on the Court's foregoing conclusions regarding the failure to extend the time for confirming a plan in this small business case, the Court determines that approval of the Amended Disclosure Statement should be denied. Because Debtor's plan cannot be confirmed given the requirements of § 1129(e), there would be no utility to approving the Amended Disclosure Statement. Approval of the Amended Disclosure Statement will therefore be denied.

CONCLUSION

Based on the reasons set forth above, Debtor's Second Extension Motion and Debtor's Amended Disclosure Statement will be denied. The UST shall submit appropriate orders.

Finally, while expiration of the time for confirming a plan under § 1129(e) may create cause for dismissal or conversion under § 1112(b) — an issue alluded to in the briefs of both the UST and Debtor — there is no motion for conversion or dismissal under § 1112(b) currently pending before this Court. Issues regarding conversion or dismissal of this case will be addressed if and when such a motion is properly brought.

In Debtor's response to the UST's objection to the Amended Disclosure Statement, Debtor made a qualified or contingent request to dismiss this case should the Court find a violation of § 1121(e) and § 1129(e). See Doc. No. 62 at 2, 8. The request is denied. Debtor can file a proper motion to dismiss and provide notice of the same should it choose.
--------

_____________

TERRY L. MYERS

CHIEF U. S. BANKRUPTCY JUDGE


Summaries of

In re Doug Larsen Constr., Inc.

UNITED STATES BANKRUPTCY COURT DISTRICT OF IDAHO
Jun 29, 2012
Case No. 11-02567-TLM (Bankr. D. Idaho Jun. 29, 2012)
Case details for

In re Doug Larsen Constr., Inc.

Case Details

Full title:IN RE DOUG LARSEN CONSTRUCTION, INC., Debtor.

Court:UNITED STATES BANKRUPTCY COURT DISTRICT OF IDAHO

Date published: Jun 29, 2012

Citations