I. Perlis Sons v. Peacock Constr. Co.

Supreme Court of Georgia
Nov 10, 1966
152 S.E.2d 390 (Ga. 1966)

Opinion

23657.

ARGUED SEPTEMBER 12, 1966.

DECIDED NOVEMBER 10, 1966. REHEARING DENIED NOVEMBER 23, 1966.

Equitable petition. Tift Superior Court. Before Judge Gray.

Thad W. Gibson, Perry, Walters, Langstaff Lippitt, for appellant.

Maxwell A. Hines, C. James Jessee, Jr., Shoob, McLain Jessee, Benjamin Zeesman, Aaron L. Buchsbaum, Seymour S. Owens, for appellees.


The general demurrer to Counts 1 and 2 and 4 through 15 should have been sustained since the counts seek recovery under a contract and fail to allege compliance with conditions precedent. Count 3 based on quantum meruit was not subject to the general demurrer.

ARGUED SEPTEMBER 12, 1966 — DECIDED NOVEMBER 10, 1966 — REHEARING DENIED NOVEMBER 23, 1966.


Peacock Construction Company (hereinafter referred to as Peacock), appellee here, brought an equitable suit in Tift Superior Court against Louis D., Lamar J., Marvin A. and Isadore R. Perlis, individually and as members of the partnership I. Perlis Sons (hereinafter referred to collectively as Perlis), appellants here, and other named defendants. The petition contained 15 counts. The first three counts related to issues solely between Peacock and Perlis, and succinctly stated were as follows.

Count 1 alleged that Peacock by written contract agreed, for a stipulated sum, to constructed a shopping center for Perlis; that Peacock had fully performed all the work under the terms and conditions of the contract and delivered the shopping center to Perlis in a completed condition; that there was a balance of $20,000 due to Peacock under the contract; that Perlis had breached the contract by failing to pay Peacock the balance due. Prayers were for judgment in the amount of $20,000 plus interest.

Count 2 alleged the same written contract above mentioned; that due to the interference, delay and dilatory practices of Perlis, Peacock incurred damages in the nature of increased costs in the amount of $19,717.29; that Perlis was unduly litigious causing Peacock to incur attorney's fees in the amount of $3,500; and prayed for judgment in the amount of $23,217.29 plus interest.

Count 3 was on the basis of quantum meruit and prayed for judgment in the amount of $67,314.23 plus interest.

In each of Counts 4 through 15 Peacock joined a different subcontractor with Perlis as a co-defendant. In each of the counts, Peacock alleged that after entering into the contract to construct the shopping center for Perlis, Peacock then entered into a subcontract with the named co-defendant; that the particular co-defendant contends that he has fully completed the work required under the subcontract and has demanded the balance due under the subcontract; that Peacock can not pay the amount due the subcontractor under the contract without becoming a volunteer and assuming hazardous and inequitable risks; that Perlis found the work of the particular subcontractor incomplete and defective; that Perlis is wrongfully withholding money due the subcontractor; that in order to avoid a multiplicity of actions the court should try the allegations of all counts of the petition so that all parties will be bound by the finding of fact as to the alleged defective work performed; that the actions in Counts 4 through 15 were also brought under the provisions of Code Ann. § 3-110.1 (Ga. L. 1964, p. 140). The prayers of each of Counts 4 through 15 were that Perlis and each subcontractor be temporarily and permanently restrained from proceeding independently either in law or equity against Peacock; that if Perlis is entitled to recover judgment in any amount from Peacock for defective or improper work performed by a subcontractor then Peacock should be awarded judgment in like amount against that subcontractor.

The appellant Perlis filed demurrers to the plaintiff's petition. The trial judge entered an order overruling certain specified grounds of demurrer and reserving ruling on the remaining grounds of demurrer. Perlis appeals to this court from that judgment and enumerates as error the overruling of three grounds of demurrer to the petition.


1. The first ground of demurrer was: "To the petition as a whole and to each and every count therein on the ground that none of the counts of the petition set out a cause of action against these defendants." The main thrust of appellant's contention is that, construed most strongly against the plaintiff, Peacock, the allegations of the petition do not show that Peacock has complied with the terms of the contract so as to support an action against Perlis. It is argued that the contract provides as a condition precedent that the architect issue a certificate of completion before the entire balance is due and payable; that the petition failed to allege the architect's certificate has been obtained, which averment is essential to an action by the contractor for a breach of contract. It is also contended that the contract requires that the contractor submit evidence that all payrolls, material bills, and other indebtedness connected with the work have been paid or satisfied and that the petition affirmatively reveals the contractor has not fully paid his subcontractors.

To meet this deficiency the contractor included in his brief portions of a supplementary agreement and another agreement, consented to by both sides to be considered by this court, which it is contended had the effect of waiving the requirement for the architect's certificate and the payment of indebtedness. We do not pass upon the reviewability of stipulations as to the record made by counsel, under the Appellate Practice Act of 1965, for here it is admitted that the stipulated agreements were not part of the petition before the trial court on demurrer. "If upon the hearing of a demurrer to a petition the plaintiff make profert of a writing which is not the foundation of the suit and not set forth in the petition or exhibits thereto, it does not thereby become a part of the petition so as to be considered on demurrer, notwithstanding the order of the judge recites that it was agreed by counsel that the court might consider the same on demurrer." Rembert v. Ellis, 193 Ga. 60 ( 17 S.E.2d 165, 137 ALR 479); Holcombe v. Jones, 197 Ga. 825, 830 ( 30 S.E.2d 903). On general demurrer we consider only the "face" of the petition. Dowdy v. Dowdy, 187 Ga. 26, 28 ( 199 S.E. 191).

The contract between Perlis and Peacock, attached as an exhibit to the petition, provided: "Final payment shall be due 15 days after substantial completion of the work provided the work be then fully completed and the contract fully performed. Upon receipt of written notice that the work is ready for final inspection and acceptance, the architect shall promptly make such inspection, and when he finds the work acceptable under the contract and the contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the contractor, and noted in said final certificate, is due and payable. Before issuance of final payment the contractor shall submit evidence satisfactory to the architect that all payrolls, material bills, and other indebtedness connected with the work have been paid or otherwise satisfied."

The Court of Appeals has held that, where the certificate of an engineer or architect is required before final payment be made, such condition precedent must be alleged in order to support a recovery of the balance of the contract price. Southern Mfg. Co. v. Moss Mfg. Co., 13 Ga. App. 847 ( 81 S.E. 263); Hilton v. Taylor, 18 Ga. App. 647 ( 90 S.E. 223); Finn v. Carden, 100 Ga. App. 270, 274 ( 110 S.E.2d 693). Under a contract provision similar to the one in the instant case, this court required that the petition specifically allege that all payrolls, bills and other indebtedness have been paid to entitle the contractor to recover the final payment. Henderson v. Cochran, 213 Ga. 642 ( 100 S.E.2d 910). With these principles in mind, we now consider the allegations of the various counts.

2. Count 1 alleges: "That at all times your petitioner has fully and duly performed all of the work under the terms and conditions of said Stipulated Sum Contract on its part and has delivered the buildings and other appurtenances to the owner in a duly completed condition..." Under the rules pronounced in the cases above cited this is not sufficient, for the plaintiff must affirmatively allege compliance with conditions precedent or sufficient legal excuse for the lack of such performance. See Sellers v. City of Summerville, 208 Ga. 361 ( 67 S.E.2d 137); Griswold v. Scott, 13 Ga. 210.

Count 1 was subject to general demurrer.

3. Count 2 seeks to recover damages resulting from the interference, delay and dilatory practices of Perlis. However, averments as to compliance with the conditions of the contract on the part of Peacock are totally absent. Therefore, Count 2 is also subject to general demurrer.

4. It is unquestioned that the third count sets forth a cause for recovery on quantum meruit and the trial judge did not err in overruling the demurrer as to that count.

5. Counts 4 through 15, in essence, are dependent and predicated on Count 1. Each of them affirmatively reveals that Peacock, as contractor, has not paid the named subcontractors. Hence, the demurrer to those counts should have been sustained. See Henderson v. Cochran, 213 Ga. 642, supra.

In view of the rulings herein made, we need not consider grounds 2 and 3 of the demurrers.

Judgment affirmed in part; reversed in part. All the Justices concur.


Summaries of

I. Perlis Sons v. Peacock Constr. Co.

Supreme Court of Georgia
Nov 10, 1966
152 S.E.2d 390 (Ga. 1966)
Case details for

I. Perlis Sons v. Peacock Constr. Co.

Case Details

Full title:I. PERLIS SONS v. PEACOCK CONSTRUCTION COMPANY et al

Court:Supreme Court of Georgia

Date published: Nov 10, 1966

Citations

152 S.E.2d 390 (Ga. 1966)
152 S.E.2d 390

Citing Cases

Western Surety v. Apac-Southeast

Most important, the sureties themselves negotiated a new agreement with Matthews in April 2007. The new…

Houseboat Store, LLC v. Chris-Craft Corp.

It is undisputed that the mediation provision is a condition precedent to either party's right to file a…