Hunters Pointe Partners Ltd. Partnership v. United States Fidelity & Guaranty Co.

Michigan Court of Appeals
Jun 20, 1989
442 N.W.2d 778 (Mich. Ct. App. 1989)

Summary

In Hunters Pointe, the bond owner had assigned the bond and the underlying construction contract to a third party without the surety's consent.

Summary of this case from Lasalle Grp. Inc. v. JST Props. L.L.C.

Opinion

Docket No. 106664.

Decided June 20, 1989.

Dykema Gossett (by Nancy G. Edmunds and Maureen E. Thomas), for plaintiff.

Poling, McGaw Poling, P.C. (by D. Douglas McGaw and Gregory C. Hamilton), for defendant.

Before: MICHAEL J. KELLY, P.J., and GILLIS and CYNAR, JJ.


Plaintiff, Hunters Pointe Partners Limited Partnership, appeals as of right from a May 4, 1988, judgment entered by the trial court. Specifically, plaintiff challenges a February 5, 1988, order of summary disposition dismissing United States Fidelity Guaranty Company as a defendant. We reverse.

This action involves plaintiff's claim for damages resulting from various defects in the construction of an apartment complex located in Southfield, Michigan. On May 6, 1981, a construction contract was executed between Hunters Glen, Ltd., as owner, and Hoffman Construction Company, as contractor, for the construction of an apartment complex. As required by the construction contract, a performance bond was issued by USFG, as surety, naming Hoffman as the principal and Hunters Glen as obligee, guaranteeing Hoffman's performance under the construction contract. Article 2, ¶ B of the construction contract expressly required the contractor to correct any defects due to faulty materials or workmanship which might appear within one year from the date of completion. Article 2, ¶ D of the construction contract defined the date of completion as the date that the HUD representative's trip report is signed indicating construction is complete and which report is subsequently endorsed by the chief architect as being the final inspection report. The HUD representative's trip sheet was signed on September 29, 1982, and the chief architect's final inspection report was signed on October 14, 1982. In addition to the construction contract, part of the consideration Hoffman was to receive for construction of the apartment complex was a limited partnership interest in Hunters Glen which Hoffman was required to sell to Hunters Glen upon completion of construction. Although USFG was not a party to the supplemental agreement, an addendum to the supplemental agreement, dated May 6, 1981, was executed by Hoffman, Hunters Glen, and USFG indicating that the benefits inuring to Hoffman under the supplemental agreement would be extended to USFG as an inducement for USFG'S issuance of the payment and performance bonds.

As a result of financial instability, Hunters Glen filed for Chapter 11 bankruptcy in April, 1983. As part of Hunters Glen's plan of reorganization, a purchase agreement was entered into on June 30, 1983, between Hunters Glen and Northern Capital, Inc., as nominee for Hunters Pointe, which agreement was approved by the bankruptcy court by order dated August 15, 1983. Although the plan of reorganization was accepted by Hoffman, USFG was not a party to the bankruptcy proceedings, did not receive direct notice from the bankruptcy court as to any issue, and did not participate in any of the bankruptcy court hearings concerning the project. At a closing which took place on October 13, 1983, Hunters Pointe closed the HUD mortgage and acquired fee simple title to the project from Hunters Glen. Hunters Pointe concedes that Hoffman was never paid in full for its limited partnership interest in Hunters Glen. By assignment dated October 17, 1983, all assets of Hunters Glen were assigned to Hunters Pointe.

As a result of numerous alleged defects in the construction of the apartment complex, plaintiff filed suit, on November 28, 1984, against both Hoffman, as contractor, and USFG, as surety, under the performance bond. On February 5, 1988, the trial court granted summary disposition in favor of USFG on the basis that, as a surety, it was discharged from liability when the construction contract and performance bond were assigned from Hunters Glen to Hunters Pointe without the express consent of USFG. Plaintiff proceeded to trial against Hoffman and, on May 4, 1988, a judgment was entered awarding Hunters Pointe damages in the amount of $453,813 against Hoffman plus interest of $186,946.08 and costs of $12,448.77. Plaintiff now appeals, asserting that the lower court's order of summary disposition in favor of USFG was in error.

Plaintiff argues that the trial court erred in ruling that plaintiff's failure to obtain the consent of USFG to the assignment of the construction contract and performance bond operated to discharge USFG as surety under the performance bond. We agree.

USFG was not a party to the construction contract and its consent to an assignment of the contract by the original owner, Hunters Glen, was not necessary. Article 9, ¶ A provided for an assignment of the contract by Hoffman or Hunters Glen with the prior consent of the other party, but consent of the surety, USFG, was not required under the contract. Additionally, the performance bond contained no express prohibition against an assignment of rights under the bond by Hunters Glen. In fact, ¶ 5 of the bond contemplated the continuation of the surety's liability to an assignee of Hunters Glen.

A prejudicial change in obligations or duties is necessary to discharge a paid surety from liability. Chris Nelson Son, Inc v Atlas Concrete Pipe, Inc, 84 Mich. App. 29, 32-33; 269 N.W.2d 295 (1978), lv den 404 Mich. 818 (1979); Miller Industries, Inc v Cadillac State Bank, 40 Mich. App. 52, 59; 198 N.W.2d 433 (1972), lv den 387 Mich. 812 (1972).

In Chris Nelson Son, Inc, supra at 32, this Court, quoting 13 Couch, Insurance (2d ed), § 47:97, stated:

"A bond executed by a bonding company in business for profit, which guarantees the performance of a construction company contract in existence, is assignable where it contains no evidence that the right to have it performed shall not be assignable."

This Court held that, in the absence of prejudice to the defendant surety, the assignment of the performance bond by the promisee did not discharge the defendant's liability as surety. Id. at 32-33.

In the present case, the surety, USFG, was not a party to the construction contract and its consent to an assignment of the contract by Hunters Glen was not required. Also, the performance bond did not expressly prohibit an assignment by Hunters Glen. Furthermore, we find no prejudice to USFG as a result of the assignment by Hunters Glen to Hunters Pointe. In this case, the assignment of the construction contract and bond from a bankrupt obligee to a new obligee with available funds to fulfill the terms of the construction contract was in no way prejudicial to USFG. Therefore, we find that the trial court erred in granting summary disposition to USFG on the basis that USFG'S liability as surety was discharged by the assignment.

On appeal, defendant USFG argues that it should be relieved of its obligations under the bond due to a breach of contract by the owner in failing to make proper payments, due to the principal's full performance, and due to plaintiff's filing of the complaint after the period of limitation had expired. Plaintiff argues that USFG was not relieved of its bond obligations on these grounds. However, we do not address these remaining issues on appeal since the trial court made no determination on these issues in its disposition of the case. Our review is limited to issues actually decided by the trial court. Michigan Mutual Ins Co v American Community Mutual Ins Co, 165 Mich. App. 269, 277; 418 N.W.2d 455 (1987), lv den 430 Mich. 884 (1988). Accordingly, we remand to the trial court for further proceedings in which a determination shall be made on each of these remaining issues.

Reversed and remanded. We do not retain jurisdiction.


Summaries of

Hunters Pointe Partners Ltd. Partnership v. United States Fidelity & Guaranty Co.

Michigan Court of Appeals
Jun 20, 1989
442 N.W.2d 778 (Mich. Ct. App. 1989)

In Hunters Pointe, the bond owner had assigned the bond and the underlying construction contract to a third party without the surety's consent.

Summary of this case from Lasalle Grp. Inc. v. JST Props. L.L.C.

In Hunters Pointe, this Court concluded that the defendant, a surety company who was not a party to the contract and was "in no way prejudice[d]" by the assignment, was not entitled to summary disposition solely on the ground that a contracting party impermissibly assigned its contractual rights.

Summary of this case from Great Lakes Eye Inst., P.C. v. Krebs
Case details for

Hunters Pointe Partners Ltd. Partnership v. United States Fidelity & Guaranty Co.

Case Details

Full title:HUNTERS POINTE PARTNERS LIMITED PARTNERSHIP v UNITED STATES FIDELITY…

Court:Michigan Court of Appeals

Date published: Jun 20, 1989

Citations

442 N.W.2d 778 (Mich. Ct. App. 1989)
442 N.W.2d 778

Citing Cases

Lasalle Grp. Inc. v. JST Props. L.L.C.

LaSalle argues that its failure to satisfy the performance bond's conditions precedent is irrelevant unless…

Will H. Hall Son v. Capitol Indemnity Corp.

A prejudicial change or modification in duties or obligations is necessary to discharge a paid surety from…