From Casetext: Smarter Legal Research

Hall v. Long

Supreme Court, New York Special Term
Feb 1, 1901
34 Misc. 1 (N.Y. Sup. Ct. 1901)

Opinion

February, 1901.

Saul Bernstein, for plaintiff.

Walter I. McCoy, for Union Granite Company.

M.J. Earley, for Hallahan Ahearn.

Joseph A. Farley, for A.A. Murphy.

F.P. Hummel, for F. Brandt.

Bennet Silverman, for J. Jones Son Co.

Van Schaick, Norton Quinby, for Union Surety Guaranty Co.


The suit is in equity to foreclose certain mechanics' liens filed against five buildings on the north side of One Hundred and Sixteenth street, 200 feet easterly from Eighth avenue, in the borough of Manhattan, belonging to the defendant Long. Plaintiff filed a lien for $4,013, alleged to be due to him from the owner, and the Union Granite Company, a subcontractor employed by the plaintiff, filed a lien for $675, to enforce the payment of that sum out of the moneys due from the owner to the plaintiff. Four independent contractors with the owner also filed liens and joined in the action to enforce them, to-wit: Hallahan Ahearn, Alban A. Murphy, Frederick Brandt, and the J. Jones Son Company. Certain other liens filed by Messrs. Grimes, Mansfield Person, were settled and discharged of record. First. As to the plaintiff's lien: The plaintiff's contract was to do the ironwork of the five houses for $16,000, payable in seven installments, as the work progressed, upon the certificate of the architect that the payments had been earned. The owner claims that the work done and material furnished were not of the quality required by the contract and the plans and specifications. It is true that in some unimportant details the work was not technically up to the requirements, but the old rule of strict performance is somewhat relaxed (Woodward v. Fuller, 80 N.Y. 312; Nolan v. Whitney, 88 id. 648; Crouch v. Gutmann, 134 id. 45), and substantial performance only is required. "Substantial performance, as defined by these and other cases, permits only such omissions or deviations from the contract as are inadvertent and unintentional, are not due to bad faith, do not impair the structure as a whole, are remediable without doing material damage to other parts of the building in tearing down and reconstructing, and may without injustice be compensated for by deductions from the contract price." Spence v. Ham, 27 A.D. 379, 382. The contract was substantially performed within the rule laid down in the case cited, so far as the owner permitted performance thereof, and the plaintiff is entitled to recover the balance due him, less the reasonable expense of making the work literally answer the requirements of the contract. The owner had an architect and a superintendent in and about the buildings to protect his interests, and he was in and out of them occasionally himself. These persons saw what material was going into the work and how it was being put in, yet there was no objection or fault found until after the plaintiff pressed for the last payment due to him. The owner waived the necessity of getting the architect's certificate, and he made the payments without any certificate. When the last payment was demanded, the owner insisted for the first time upon a certificate, whereupon the plaintiff went to the architect, who refused to give the certificate because the plaintiff had filed a lien, and it might antagonize him with the owner. So that, whether the decision is placed on the ground of waiver of the certificate by the owner or wrongful refusal by the architect to give one, there is evidence enough to warrant a finding. Bowery Nat. Bank v. Mayor, 63 N.Y. 336; Flaherty v. Miner, 123 id. 382. Another feature of the case is presented by paragraph five of the contract between the plaintiff and the owner, which contains the usual clause allowing the owner to give three days' notice in case of failure by the contractor to furnish proper materials or perform the contract in any way, and permitting the owner to do so and to charge the cost to the contractor. The owner took advantage of this clause by serving the required notice and attempting to complete the work which he claimed was unfinished. The certificate of the architect is waived when the owner gives the notice and proceeds to complete, as the object of the certificate is to inform the owner of the fact of completion. Weeks v. O'Brien, 141 N.Y. 199; Ogden v. Alexander, 140 id. 356; Van Clief v. Van Vechten, 130 id. 571; New Jersey Steel Iron Co. v. Robinson, 33 Misc. 361. Such a provision acted on by the owner entitles the contractor to recover the difference between the last installment and the amount expended by the owner in completing the work. Weeks v. O'Brien; Ogden v. Alexander; Van Clief v. Van Vechten; New Jersey Steel Iron Co. v. Robinson, supra. The contract price was $16,000. The extra work furnished amounts to $468, aggregating $16,468; from which should be deducted payments, $12,400; allowance for deficiencies and work done by owner, $1,113; leaving as a balance due plaintiff, $2,955. The evidence given by the experts has been carefully weighed and considered according to the best judgment of the court upon the subject. Reeves v. Hyde, 14 N.Y. St. Rep. 689; Muller v. Ryan, 19 id. 109; Head v. Hargrave, 105 U.S. 45. That extra work was done is clear, for the owner's letters expressly call for certain extras. Second. As to the lien of the Union Granite Company. The lien filed was for $675, but it was conceded on the trial that the granite company was entitled to $575 only, and judgment will be ordered accordingly in favor of the granite company against the plaintiff, with a direction that it be paid out of the moneys coming to the plaintiff under the lien filed by him. Third. As to the lien filed by Hallahan Ahearn, independent contractors. This lien was for the lathing and plastering work. The contract price was $14,000, payable in three installments, as the work progressed. The owner was dilatory in his payments, and the contractors refused on that account to proceed until Charles Heidenheimer, a surety procured by the owner, guaranteed the payments provided by the contract. The contractors thereupon resumed work and continued thereon until a further default was made, whereupon they declined to proceed. Johnson v. Tyng, 1 A.D. 610; Canal Co. v. Gordon, 6 Wall. 561. At the time the contractors finally ceased their work, the plastering they agreed to perform was substantially finished, except what is known as patching, which is generally performed after the carpenters have finished their work. The contractors did not receive a balance due of $3,000 under the contract. They are entitled to receive this sum after deducting $500, the reasonable expense of the patching left undone, and the further sum of $400, the reasonable expense of completing certain details of work left incomplete and which would have been completed by the contractors if the payments agreed to be made by the owner had been promptly made and he had not completed the work himself, leaving a net balance of $2,100, which the lienors are entitled to recover. Fourth. As to the lien filed by Alban A. Murphy, an independent contractor. This lien was for the painting work. The contract price was $1,900. The owner paid on account in cash, $260, and gave the contractor promissory notes aggregating $717.58, on account of which $150 was paid. These notes were transferred to creditors of the contractor, and the transferees recovered judgments on the notes, which judgments have not been paid. The contractor proceeded with his work until Hallahan Ahearn filed their lien, whereupon he ceased to work and filed a lien for the balance claimed by him, including the amount of the three notes. The contractor proved that the work done by him up to the time he stopped was reasonably worth $1,200, on which the owner is entitled to credit for $410, leaving $790 now due. The decree must provide that out of this sum the judgments on the outstanding notes made by the owner and transferred to creditors of the contractor must be paid, to the end that said judgments be satisfied and notes returned. Fifth. As to the lien filed by the J. Jones Son Company, who held a contract for electrical appliances with John C. Francis, contractor under the owner. The evidence shows that John C. Francis did not complete his contract with the owner, attributing his failure to impecuniosity and inability to obtain the required material to complete the work, whereupon the owner, on February 1, 1900, gave to Francis a note for $400, payable in thirty days, upon the understanding that he should give it to the Jones Company to make his credit with that company good. Francis owed the Jones Company more than $400 at the time he gave the note to said company, which thereupon credited the amount thereof on Francis' account. The note having been made for the accommodation of Francis on his promise to perform his contract and without restriction as to its use further than that it should be given to the Jones Company for credit on his account, that company became a holder for value and entitled to recover thereon from the maker. Schepp v. Carpenter, 51 N.Y. 602; Grocers' Bank v. Penfield, 69 id. 502. The note not having been paid, the broken promise did not operate as payment (Schmidt v. Livingston, 16 Misc. 554), and the material of the Jones Company having gone. into the owner's house to aid in the construction thereof, Jones Company became entitled not only to the security of the note, but for the amount thereof to a lien which the statute affords to laborers and materialmen. Jones v. Moores, 67 Hun, 109; Miller v. Smith, 20 A.D. 507. It cannot be that such an obligation is enforceable against the maker in the common-law branch of the court, and unenforceable in a foreclosure tried at the equity branch, where technicalities are upon equitable principles disregarded. The court, therefore, holds that the Jones Company has a valid lien against the premises to the extent of $400 and interest. The lienors are not entitled to personal judgment against Francis because he is not a party to the action, nor is the owner entitled to any personal judgment against Francis for the same reason. No claim for such a personal judgment is made in the pleadings. Sixth. As to lien filed by Frederick Brandt, an independent contractor. This lien was for the roofing and cornice work. The contract price was $1,100. The lienor received $700, and claims the balance of $400. The owner contends: 1. That the cornice on the front of the buildings was bent, and that a crown molding which would cost $200 was necessary to correct the defect. 2. That the moldings over the doors were defectively set, and that it would cost $9 to correct the error. 3. That certain ornaments which the plaintiff contracted to supply were not furnished, and that these on the five houses were worth $50. The lienor answered this claim by proving: 1. That the cornice was properly put up by him, but was bent by other workmen employed on the building by the owner, and that the lienor (though not bound to do so) corrected the injury as far as he could. 2. That the moldings over the doors were properly set; that the alleged error was due to defective work by the mason. 3. That the particular ornaments said to have been omitted were not furnished because by a modification of the contract ornaments made by a different maker were substituted, the value being the same. This operated as a valid waiver by the owner. Close v. Clark, 30 N.Y. St. Rep. 671. The evidence so furnished by the lienor satisfactorily explains away the faults found by the owner. Some few articles called strainers were accidentally omitted, the highest value of which, according to the evidence offered by the defendant's expert, was $10, which sum will be deducted from the lienor's claim, leaving $390 due to him, with interest, for which he is entitled to judgment. No technical objections have been urged against the form or sufficiency of the notices of lien, which will, therefore, be assumed to be in proper form and to have been filed in due time. There should be but one decision and decree presented, embracing all the liens, covering substantially all the issues decided and declaring the priority of the different liens. The liens having been discharged upon a bond given by the Union Surety Guaranty Company, the judgments should be in accordance with Morton v. Tucker, 145 N.Y. 248, and Ringle v. Matthiessen, 10 A.D. 274; affd., 158 N.Y. 740. The amount of costs and allowances may be left blank in the proposed decision and decree; that question will be adjusted on the settlement of the decree, which should be on three days' notice.

Ordered accordingly.


Summaries of

Hall v. Long

Supreme Court, New York Special Term
Feb 1, 1901
34 Misc. 1 (N.Y. Sup. Ct. 1901)
Case details for

Hall v. Long

Case Details

Full title:JOHN HOLL, Plaintiff, v . WILLIAM S. LONG et al., Defendants

Court:Supreme Court, New York Special Term

Date published: Feb 1, 1901

Citations

34 Misc. 1 (N.Y. Sup. Ct. 1901)
68 N.Y.S. 522

Citing Cases

Stanton v. State of New York

This principle has been defined and limited, as above, in many other decisions. Spence v. Ham, supra; People…

Daly Sons v. New Haven Hotel Co.

In any case, the deduction is to be so determined that the owner's resultant payment will be fair and…