From Casetext: Smarter Legal Research

Guardian v. Bureau of Constr

Michigan Court of Appeals
May 13, 2008
279 Mich. App. 1 (Mich. Ct. App. 2008)

Opinion


755 N.W.2d 556 (Mich.App. 2008) 279 Mich.App. 1 GUARDIAN ENVIRONMENTAL SERVICES, INC., d/b/a Master Temperature Controls, Plaintiff-Appellee, v. BUREAU OF CONSTRUCTION CODES AND FIRE SAFETY, DEPARTMENT OF LABOR AND ECONOMIC GROWTH, State of Michigan, Defendant-Appellant. Docket No. 276564. Court of Appeals of Michigan. May 13, 2008

         Submitted May 7, 2008, at Detroit. [Copyrighted Material Omitted]           Dickinson Wright, PLLC (by Frank R. Mamat, Joseph W. DeLave, and Charles G. Goedert), Bloomfield Hills, for the plaintiff.

          Michael A. Cox, Attorney General, Thomas L. Casey, Solicitor General, Richard P. Gartner and Susan Przekop-Shaw, Assistant Attorneys General, for the defendant.

          Before: OWENS, P.J., and METER and SCHUETTE, JJ.

         PER CURIAM.

         [279 Mich.App. 2] Defendant, the Bureau of Construction Codes and Fire Safety (the Bureau), appeals by leave granted from the trial court's final order granting declaratory and injunctive relief to plaintiff Guardian Environmental Services, Inc. We affirm.

The Bureau of Construction Codes and Fire Safety is part of the Michigan Department of Labor and Economic Growth.

         This declaratory judgment action arose from a dispute between plaintiff, a licensed mechanical contractor, and the Bureau, which was charged with the enforcement of the Electrical Administrative Act (EAA), MCL 338.881 et seq. In August 2004, plaintiff [279 Mich.App. 3] contracted with the Allen Park School District to perform renovation work in five of the district's school buildings. Specifically, plaintiff was hired to replace existing pneumatic energy management systems with direct digital control energy management systems in four of the school buildings and to replace a hybrid energy management system with a direct digital control energy management system in the fifth school building. Replacement of the existing energy management systems required plaintiff to install low-voltage wiring and communications network cabling. Plaintiff intended to perform this work itself instead of subcontracting the work to a licensed electrical contractor. Plaintiff maintained that because it was a licensed mechanical contractor and because the work involved the “ replacement" and “ upgrading" of energy management systems that control existing mechanical systems, MCL 338.887(3)(i) permitted it to perform this work without an electrical contractor's license.

The question presented by the parties on appeal is one of statutory construction, the parties did not present extensive evidence regarding the nature, purpose, and makeup of the energy management systems that plaintiff planned to install, and the trial court did not engage in significant fact-finding. Therefore, we accept the allegations in the complaint as true for purposes of presenting pertinent background facts in this opinion.

Plaintiff subcontracted the high-voltage wiring associated with the project to a licensed electrical contractor.

          On March 17, 2005, William Fox, a state inspector for Wayne County, ordered plaintiff to cease installing low-voltage wiring at the Allen Park project. Concerned that Fox's action would affect its other projects, including work that it was performing for the Warren Consolidated School District, plaintiff contacted Virgil Monroe, chief of the Bureau's electrical division. Monroe determined that MCL 338.887(3)(i) did not allow plaintiff to install low-voltage wiring and forwarded to Chuck Goerlitz, plaintiff's manager, a May 1998 bulletin authored by Tom Kriegish, the former chief of the [279 Mich.App. 4] electrical division, which set forth the Bureau's position regarding what work was permissible without an electrical contractor's license pursuant to MCL 338.887(3)(i).

The May 1998 article provides in relevant part:

         Goerlitz requested an appeal of Monroe's decision that plaintiff was not allowed to install the low-voltage electrical wiring. He also noted that the term “ existing mechanical systems" required clarification and requested a statement of the Bureau's position on the meaning of the phrase. In response to Goerlitz's communications, Monroe confirmed that the May 1998 article set forth the Bureau's “ complete and final position" on work that may be performed without an electrical contractor's license pursuant to MCL 338.887(3)(i). With respect to the meaning of the phrase “ existing mechanical systems," Monroe explained:

Existing mechanical systems are not defined in the Act. According to Webster's New World Dictionary, Third College Edition, “ Existent" is defined as 1-having existence or being; existing, 2-existing now; present; immediate. Using this definition, the term “ existing mechanical systems" would be systems existing at the time of service, repair, replacement, etc. 7(3)(i) would cover these installations. It would not include systems removed then changed to a different type of system, such as, the replacement of an [279 Mich.App. 5] existing pneumatic controlled system with a new electrical controlled system. In this instance a licensed electrical contractor would be required.

This is the final position of the Electrical Division.

         Plaintiff requested that the Electrical Administrative Board overrule Monroe's decision. However, at its October 7, 2005, meeting, the Electrical Administrative Board unanimously upheld Monroe's interpretation of MCL 338.887(3)(i). Plaintiff then petitioned the Michigan Department of Labor and Economic Growth for declaratory relief, which the department denied.

         On February 27, 2006, plaintiff filed an action seeking a declaration from the trial court that an exception to the requirement that all electrical wiring be performed by an entity holding an electrical contractor's license set forth under MCL 338.887(3)(i) applied to the work plaintiff sought to perform, namely, the replacement of an existing pneumatic energy management system with a direct digital control energy management system. The trial court granted plaintiff's request for declaratory and injunctive relief on August 7, 2006.

The trial court's order stated in pertinent part,

          On appeal, the Bureau argues that the trial court's interpretation of MCL 338.887(3)(i) was contrary to the plain language of the statute. We disagree. We review de novo both questions of law arising from a declaratory judgment action and questions of statutory interpretation. [279 Mich.App. 6] Green Oak Twp. v. Munzel, 255 Mich.App. 235, 238, 661 N.W.2d 243 (2003); Dessart v. Burak, 252 Mich.App. 490, 494, 652 N.W.2d 669 (2002), aff'd 470 Mich. 37, 678 N.W.2d 615 (2004). We review the trial court's decision to grant or deny declaratory relief for an abuse of discretion. Gauthier v. Alpena Co. Prosecutor, 267 Mich.App. 167, 170, 703 N.W.2d 818 (2005). In the absence of fraud, findings of fact made or adopted by an administrative agency are conclusive on appeal if they are supported by competent evidence on the record; however, the decision of an administrative agency may be reversed if the agency's decision was based on erroneous legal reasoning or if the agency operated within the wrong legal framework. Schmaltz v. Troy Metal Concepts, Inc., 469 Mich. 467, 471, 673 N.W.2d 95 (2003).

          In interpreting a statute, the fundamental task of a court is to “ discern and give effect to the Legislature's intent as expressed in the words of the statute." Pohutski v. City of Allen Park, 465 Mich. 675, 683, 641 N.W.2d 219 (2002). Where the plain and ordinary meaning of the statutory language is clear, further judicial construction is unwarranted. Nastal v. Henderson & Assoc. Investigations, Inc., 471 Mich. 712, 720, 691 N.W.2d 1 (2005). See also DiBenedetto v. West Shore Hosp., 461 Mich. 394, 402, 605 N.W.2d 300 (2000). Judicial construction of a statute is proper only where reasonable minds could differ about the meaning of the statute. Adrian School Dist. v. Michigan Pub. School Employees' Retirement Sys., 458 Mich. 326, 332, 582 N.W.2d 767 (1998).

          We accord to every word or phrase of a statute its plain and ordinary meaning, unless a term has a special, technical meaning or is defined in the statute. Casco Twp. v. Secretary of State, 472 Mich. 566, 593 n. 44, 701 N.W.2d 102 (2005); MCL 8.3a. In ascertaining the plain and ordinary meaning of undefined statutory terms, we [279 Mich.App. 7] may rely on dictionary definitions. Halloran v. Bhan, 470 Mich. 572, 578, 683 N.W.2d 129 (2004).

         MCL 338.887 provides, in pertinent part:

(1) Except as otherwise provided in this act or in subsection (3), a person, firm, or corporation shall not engage in the business of electrical contracting unless the person, firm, or corporation has received from the board or from the appropriate municipality an electrical contractor's license.

(2) Except as otherwise provided in this act or in subsection (3), a person, other than a person licensed under this act and employed by and working under the direction of a holder of an electrical contractor's license, shall not in any manner undertake to execute any electrical wiring.

(3) A license under this act is not required in the execution of the following classes of work:

* * *

(i) Work performed by mechanical contractors licensed in classifications listed in section 6(3)(a), (b), (d), (e), and (f) of the Forbes mechanical contractors act, 1984 PA 192,MCL 338.976, plumbing contractors licensed under 1929 PA 266,MCL 338.901 to 338.917, and employees of persons licensed under those acts while performing maintenance, service, repair, replacement, alteration, modification, reconstruction, or upgrading of control wiring circuits and electrical component parts within existing mechanical systems defined in the mechanical and plumbing codes provided for in the Stille-DeRossett-Hale single state construction code act, 1972 PA 230,MCL 125.1501 to 125.1531, including, but not limited to, energy management systems, relays and controls on boilers, water heaters, furnaces, air conditioning compressors and condensers, fan controls, thermostats and sensors, and all interconnecting wiring associated with the mechanical systems in buildings which are on the load side of the unit [279 Mich.App. 8] disconnect, which is located on or immediately adjacent to the equipment, except for life safety systems wiring.

         Here, each party argues that the plain language of the statute supports its interpretation of MCL 338.887(3)(i). Plaintiff contends that under the plain meaning of MCL 338.887(3)(i), a mechanical contractor may replace an energy management system within an existing mechanical system. The Bureau, however, asserts that the statutory exception set forth under MCL 338.887(3)(i) unambiguously allows mechanical contractors only to replace wiring and other electrical components within existing energy management systems.

         In making this argument, the Bureau contends that the statute would allow a mechanical contractor to replace a pneumatic energy management system with another pneumatic energy management system. The Bureau also contends that the statutory exception provided under MCL 338.887(3)(i) allows plaintiff to remove a direct digital control energy management system, but it does not permit plaintiff to replace an existing pneumatic energy management system with a direct digital control energy management system. However, the Bureau's proposed interpretation of the term “ replacement" imposes the additional, extra-statutory requirement that the substituted system must be of like kind.

         Instead, we conclude that the Legislature intended to allow plaintiff to replace an existing pneumatic or hybrid energy management system with a direct digital control energy management system within an existing mechanical system. Random House Webster's College Dictionary (1997) defines “ replacement" as “ the act of replacing" and as “ a person or thing that replaces another," and defines “ replace" as “ to assume the [279 Mich.App. 9] function of; substitute for: to replace gas lights with electric lights. " Especially in light of the example of “ replace" included in this definition, we conclude that the proper interpretation of “ replacement" as used in MCL 338.887(3)(i) includes the abandonment or removal of a pre-existing defective or obsolete pneumatic energy management system and the installation of a new direct digital control system for an existing mechanical system.

          The statutory exception included in MCL 338.887(3)(i) provides that a mechanical contractor may “ perform[ ] maintenance, service, repair, replacement, alteration, modification, reconstruction, or upgrading of control wiring circuits and electrical component parts within existing mechanical systems...." According to the statute, an example of the “ electrical component parts" or “ control wiring circuits" “ include[es], but [is] not limited to, energy management systems...." MCL 338.887(3)(i). Thus, an energy management system is one example of an electrical component part of a pre-existing mechanical system that a licensed mechanical contractor is permitted to replace. The Legislature's choice of the term “ replacement" reflects its intent that an electrical contractor's license is not required for the removal of a pneumatic energy management system and the installation of a direct digital control energy management system in a pre-existing mechanical system. We conclude that the trial court's decision that the exception set forth under MCL 338.887(3)(i) allowed plaintiff to perform the disputed work was based on a correct, plain-language interpretation of the statute.

          Next, the Bureau argues that the trial court exceeded its authority when it improperly declined to defer to the Bureau's interpretation of the statute. We disagree. An administrative agency's interpretation of a statute it is charged with enforcing is entitled to great weight and [279 Mich.App. 10] we will overrule the interpretation only if it is clearly erroneous. Schmaltz, supra at 471, 673 N.W.2d 95. However, if an administrative agency's interpretation of a statute is contrary to the statute's plain meaning, the intent of the Legislature as expressed in the statutory language must prevail. By Lo Oil Co. v. Dep't of Treasury, 267 Mich.App. 19, 49-50, 703 N.W.2d 822 (2005).

Our Supreme Court has granted leave to appeal in another case involving the issues of: “ (1) what legal framework appellate courts should apply to determine the degree of deference due an administrative agency in its interpretation if a statute within its purview; [and] (2) whether the Court of Appeals erred in deferring to the Michigan Public Service Commission's interpretation of MCL 484.2502(1)(a)...." SBC Michigan v. Pub. Service Comm., 480 Mich. 977, 741 N.W.2d 834 (2007). See also In re Complaint of Rovas Against Ameritech Michigan, 276 Mich.App. 55, 740 N.W.2d 523 (2007). Our Supreme Court's decision in SBC Michigan could alter the common law regarding the deference that must be given to agency interpretations. However, under existing law, deference to an administrative agency's interpretation of a statute is proper only where reasonable minds could differ regarding the meaning of the statute, i.e., the statutory language is ambiguous. By Lo Oil Co. v. Dep't of Treasury, 267 Mich.App. 19, 49-50, 703 N.W.2d 822 (2005). Further, pursuant to the language of this Court in By Lo Oil Co, if an administrative agency's interpretation of a statute is contrary to the plain meaning of the statute, the agency's interpretation is clearly erroneous. Id. at 49-50, 703 N.W.2d 822. Where, as here, the statutory language is unambiguous, the statute must be applied as written. Pohutski, supra at 683, 641 N.W.2d 219.

          The Bureau asserts that the interpretation of a statute by an agency charged with enforcing the statute should not be overruled in the absence of “ cogent reasons." See Oakland Schools Bd. of Ed. v. Superintendent of Pub. Instruction, 401 Mich. 37, 41, 257 N.W.2d 73 (1977), quoting United States v. Moore, 95 U.S. 760, 763, 24 L.Ed. 588 (1877). However, an agency's interpretation of a statute contrary to the plain language of the statute constitutes a compelling, “ cogent" reason for overruling the agency's clearly erroneous interpretation. See Consumers Power Co. v. Pub. Service Comm., 460 Mich. 148, 157 n. 8, 596 N.W.2d 126 (1999) (“ An agency [279 Mich.App. 11] interpretation cannot overcome the plain meaning of a statute." ). Mindful that one branch of government may not exercise powers conferred to other branches of government, Const. 1963, art. 3, § 2, the Bureau's contention that the trial court's failure to defer to its construction of MCL 338.887(3) (i) violated the “ separation of powers" doctrine ignores the significant concepts of checks and balances and judicial review. The judiciary alone is the final authority on questions of statutory interpretation and must overrule administrative interpretations that are contrary to clear legislative intent. Office Planning Group, Inc. v. Baraga-Houghton-Keweenaw Child Dev. Bd., 472 Mich. 479, 491 n. 23, 697 N.W.2d 871 (2005). See also Chevron USA Inc. v. NRDC, Inc., 467 U.S. 837, 843 n. 9, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984).

          Because the Bureau's construction of MCL 338.887(3)(i) was contrary to the intent of the Legislature, as expressed in the unambiguous language of the statute itself, a cogent reason existed for the trial court not to defer to the Bureau's erroneous interpretation. Accordingly, the trial court neither violated the “ separation of powers" doctrine nor exceeded its authority in rejecting the Bureau's invitation to defer to its construction of MCL 338.887(3)(i).

         Affirmed.

Recently, several individuals have asked bureau staff whether a mechanical contractor or authorized master plumber may perform work relating to electrical installations, without an electrical license.

* * *

Existing pneumatic control systems may be modified, upgraded, or replaced by a mechanical contractor. However, when an existing pneumatic system is abandoned, and replaced with a new electrical control system, it must be installed by a licensed electrical contractor.

[P]ursuant to the exemption provided in MCL 338.887(3)(i), [plaintiff], a licensed mechanical contractor, may install low voltage electrical wiring when replacing, modifying or upgrading energy management systems within existing mechanical systems, including, but not limited to, the replacement of a pneumatic control energy management system with a direct digital control energy management system.


Summaries of

Guardian v. Bureau of Constr

Michigan Court of Appeals
May 13, 2008
279 Mich. App. 1 (Mich. Ct. App. 2008)
Case details for

Guardian v. Bureau of Constr

Case Details

Full title:GUARDIAN ENVIRONMENTAL SERVICES, INC., d/b/a MASTER TEMPERATURE CONTROLS…

Court:Michigan Court of Appeals

Date published: May 13, 2008

Citations

279 Mich. App. 1 (Mich. Ct. App. 2008)
279 Mich. App. 1

Citing Cases

San Marino Iron, Inc. v. Haji

When interpreting a statute, "the fundamental task of a court is to discern and give effect to the…

Wolfbauer v. City of Berkley

The trial court's ruling on a motion for summary disposition is reviewed de novo on appeal. Gillie v Genesee…