From Casetext: Smarter Legal Research

Greene v. Green Acres Const

Colorado Court of Appeals. Division I
Sep 23, 1975
36 Colo. App. 439 (Colo. App. 1975)

Opinion

No. 74-427

Decided September 23, 1975. Rehearing granted on original opinion announced June 17, 1975, withdrawn September 23, 1975. Petition for rehearing denied October 23, 1975. Certioraris denied both Greene and Green Acres Construction December 15, 1975.

In action to recover damages sustained allegedly as a result of faulty construction of house built and sold to plaintiffs by defendant, trial court, relying on 1969 two-year statute of limitations, granted defendant summary judgment.

Reversed

1. LIMITATION OF ACTIONSDamage to Land — Water Seepage — Limitation Period Begins — Property Visibly Affected — Not — Final Damages Known. In cases involving damage to land resulting from water seepage the claim for relief arises when the property is visibly affected by the seepage, and it is not necessary for the final or ultimate damages to be known or predictable before the limitation period commences.

2. Date of Claim — Determines Applicable Statute — Under Six-Year Statute — Action Timely — Issue Resolved — Against Moving Party — Summary Judgment Denied. In action seeking to recover as the result of the alleged faulty construction of a house built by defendant and sold by it to plaintiffs, if the claim for relief arose prior to the effective date of 1969 two-year statute of limitation, then the six-year statute of limitations would control, and action would, under that statute, be timely; therefore, since on the evidence before the court there is doubt as to date when the claim for relief arose, that date must be resolved against the defendant who moved for summary judgment and the motion should have been denied.

3. Defendant — "Contractor" — Protected — Two-Year Statute — Claim Arose — After Effective Date. Since the evidence discloses that plaintiffs admitted that they signed a contract with defendant to build a house for them, defendant was therefore a "contractor," and thus he would be protected by pertinent two-year statute of limitations if the claim for relief in fact arose after the effective date of the statute and more than two years prior to the commencement of the action.

Appeal from the District Court of the County of Jefferson, Honorable George G. Priest, Judge.

Frickey, Cairns, Wylder Gilliam, P.C., Earl S. Wylder, for plaintiffs-appellants.

Calkins, Kramer, Grimshaw Harring, Richard L. Harring, for defendant-appellee.


Plaintiffs seek recovery for damages as a result of faulty construction of a house built by defendant and sold by it to plaintiffs. Plaintiffs asserted three claims for relief, founded on negligence, strict liability, and breach of an implied warranty of fitness for habitability. All were predicated on improper design and construction of the house. Defendant in its answer asserted several affirmative defenses, and prior to trial moved for summary judgment on the ground that the action was barred by § 13-80-127, C.R.S. 1973 (1969 Perm. Supp., C.R.S. 1963, 87-1-28(1)) since the action was not brought within two years after the claims for relief arose. The trial court granted the motion. Plaintiffs appeal from the ensuing judgment of dismissal. We reverse.

The facts are undisputed that plaintiffs contracted with defendant to build a house for them on land owned by defendants and that the house was built according to plans and specifications submitted by defendant and accepted by plaintiffs with a few changes requested by plaintiffs. The title to the house and land was transferred to plaintiffs at a closing in February 1967. From the spring of 1967 through 1970 there were problems with surface drainage and puddling in the back yard, which plaintiffs solved by the installation of a tile drainage system. Also, during that period water leaked into the basement cracking the basement floor and spurting up as though under pressure. Although partially corrected by plaintiffs by application of a seal coating in 1971, this condition continued through 1973. In the spring of 1973 cracks began to appear in the first floor of the house. This action was begun on November 2, 1973.

The trial court found that the claims for relief arose in April 1970 when plaintiffs incurred expenses for the laying of the tile drain. It therefore concluded that the action was barred by § 13-80-127, C.R.S. 1973, which provides:

"All actions against any architect, contractor, engineer, or inspector brought to recover damages for injury to person or property caused by the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within two years after the claim for relief arises, and not thereafter . . . . "

Although it is clear from the evidence before the trial court that the claim for relief had arisen by April 1970, the evidence leaves in dispute the exact date when the claim did, in fact, arise. The exact date is significant here because the statute relied on by defendant and the court was not enacted until 1969, and there is nothing in that statute which indicates that it was to be given retroactive application. Therefore the statute of limitations in effect at the time the claim for relief arose controls. State Highway Department v. Stunkard, 115 Colo. 358, 174 P.2d 346; Valenzuela v. Mercy Hospital, 34 Colo. App. 5, 521 P.2d 1287.

Colo. Sess. Laws 1969, ch. 221, 87-1-28, at 697. "Section 2. Saving clause. — Nothing in this act shall apply to actions arising prior to its effective date. (June 1, 1969)"

[1,2] The law is well settled in Colorado that in cases involving damage to land resulting from water seepage the claim for relief arises when the property is first visibly affected by the seepage. Hankins v. Borland, 163 Colo. 575, 431 P.2d 1007; Housing Authority v. Leo A. Daly Co., 35 Colo. App. 244, 533 P.2d 937. "It is not necessary for the final or ultimate damages to be known or predictable before the limitation period commences." Housing Authority, supra. If the present claim for relief arose prior to the effective date of § 13-80-127, C.R.S. 1973, then the six year statute, § 13-80-110, C.R.S. 1973, controls. Since on the evidence before the court there is doubt as to the date when the claim for relief arose, that doubt must be resolved against the moving party, Abrahamsen v. Mountain States Tel. Tel. Co., 177 Colo. 422, 494 P.2d 1287, and the motion should have been denied.

[3] We do not agree with appellants' contention that defendant does not fall within the classes of persons protected by § 13-80-127 because defendant is a "builder-vendor." The evidence discloses that plaintiffs admitted that they signed a contract with defendant to build the house for them. Defendant was therefore a "contractor," and thus would be protected by the statute if the claim for relief in fact arose after the effective date of the statute and more than two years prior to the commencement of the action.

Judgment reversed and cause remanded for further proceedings not inconsistent herewith.

JUDGE COYTE and JUDGE PIERCE concur.


Summaries of

Greene v. Green Acres Const

Colorado Court of Appeals. Division I
Sep 23, 1975
36 Colo. App. 439 (Colo. App. 1975)
Case details for

Greene v. Green Acres Const

Case Details

Full title:Paul F. Greene and Sheryl L. Greene v. Green Acres Construction Co., a…

Court:Colorado Court of Appeals. Division I

Date published: Sep 23, 1975

Citations

36 Colo. App. 439 (Colo. App. 1975)
543 P.2d 108

Citing Cases

Yurcic v. City of Gallup

{33} Arguing again that Valdez is inapplicable, Defendants cite Colorado case law for the proposition that…

Villa Sierra v. Field Corp.

The limitations period began to run from the date that the claim for relief arose, while the repose period…