From Casetext: Smarter Legal Research

Federal Ins. Co. v. Starr Elec. Co.

Supreme Court of Virginia
Nov 8, 1991
242 Va. 459 (Va. 1991)

Opinion

47257 Record No. 901589

November 8, 1991

Present: Carrico, C.J., Compton, Stephenson, Lacy, Hassell, and Keenan, JJ., and Poff, Senior Justice

In a dispute between two insurance carriers concerning a subcontractor's claim against a general contractor seeking payment for electrical work performed and materials supplied in a building renovation project terminated by fire, the trial court's decision is affirmed. The general contractor is liable to the electrical subcontractor under the payment clause of the subcontract, and the insurer is liable to the subcontractor under the payment bond

Insurance — Construction Law — Performance Bonds — Creditors' Rights — Practice and Procedure — Equity — Estoppel — Surety — Contracts — Breaches — Misrepresentation — Limitation of Actions — Subrogation

The owner of a building entered into a renovation contract with a general contractor. An insurance agency furnished the parent corporation with an insurance policy listing the contractor as the named insured. The contractor subcontracted the electrical work to another company and obtained a performance bond and a payment bond issued by the defendant insurance company. The plaintiff subcontractor was insured under its own insurance policies. During the course of the renovation project, the building was destroyed by fire, and the project was abandoned. The electrical subcontractor had completed most of the work. In response to a fire-damage claim filed by the contractor, the contractor's insurer refused coverage and filed a suit for declaratory judgment. The suit was settled out of court. Three months after the fire, plaintiff subcontractor asked the contractor for a copy of the payment bond, "if any." The contractor did not respond. The contractor filed a claim under the contractor's installation floater policy and was paid for the loss of its work, the materials and equipment. A year later, the defendant payment bond insurer mailed the subcontractor a copy of the payment bond. The next month, the contractor's floater coverage carrier attached a copy of the payment bond to a motion for judgment against the defendant, as surety for the contractor, seeking payment, in the subcontractor's name, for the balance due under the subcontract. Page two of that copy contained a clause limiting the right to file suit on the bond to two years. A year later, the defendant payment bond insurer learned for the first time that it had been supplied with an incorrect copy of the payment bond, and that page two of the original executed by the parties contained a clause limiting the right to file suit to one year. The defendant so advised the court and opposing counsel and the court allowed the correct page to be substituted. The defendant made a motion to amend its grounds of defense in order to assert the one-year time limitation defense. The trial court ruled that such a defense must be pled specially, denied the motion to amend, and held that the defendant was estopped to plead that defense. The court rejected the defendant's several grounds of defense on the merits and entered judgment against the defendant insurer, which appeals.

1. In another case, an agent's initial response to the subcontractor's inquiry was not an act of fraud or one intentionally designed to mislead, but simply one that constituted negligence.

2. Yet, the subcontractor had a right to rely on a statement of fact made to him by the person in a position to know the facts, the subcontractor was prejudiced by the failure of the agent and the surety to provide correct information, the delay in bringing action can be attributed directly to the lack of knowledge by the subcontractor of the existence of the bond, and this was the fault of the surety's agent.

3. Because the negligence of the agent of the surety caused the failure of the subcontractor to bring appropriate action, the surety was estopped to avail itself to the one-year provision in the labor and material payment bond involved. Contee Sand v. Reliance Ins., 209 Va. 672, 166 S.E.2d 290 (1969).

4. Here, the conduct of the defendant, its bonding agent, and its insured over a period of more than two years following the fire constituted negligence.

5. The defendant was guilty of negligence in failing to investigate the conduct of its agent, and under the the doctrine of respondeat superior, is accountable to innocent third parties for the agents' negligence.

6. When a person under a duty to disclose facts within his knowledge makes no response to an inquiry posed by one entitled to know the facts, the response for purposes of estoppel in pais, is a representation. It is, in effect, a negative response, an implicit representation made by a person in a position to know the facts.

7. The electrical subcontractor, unable to collect payment from the contractor and unaware during the year following the fire that it had a cause of action against a surety on a payment bond, was prejudiced by the failure of the defendant and its agents to provide correct information. The plaintiff's delay in bringing action can be attributed directly to its lack of knowledge.

8. Because the negligence of the defendant and its agents caused the plaintiff's failure to bring action within a year following the fire, the defendant was estopped to invoke the contractual time limitation clause as a defense.

9. In some jurisdictions there is a rule that no right of subrogation can arise in favor of an insurer against its own insured, but that rule is not applicable in this case.

10. The contractor's claim for coverage under the subcontractor's insurance policy falls within the category of "claims which have been or could be asserted," and, as such, it was one of the claims the contractor released in its settlement agreement with its insurer.

11. Because the contractor was not an insured in either policy within the meaning of the rule the defendant urges, the trial court's ruling on the subrogation issue was correct.

12. At the time of the fire, the contractor had paid the subcontractor less than one tenth of the amount due under the subcontract. Hence, the contractor was in breach of its contractual obligation to pay past due installments in the sum of over two hundred thousand dollars.

13. In suits for specific performance, the plaintiff, to entitle himself to relief, must show full compliance with the terms of the contract on his part.

14. The rule in equity applies generally to actions at law for breach of contract and the party who commits the first breach of a contract is not entitled to enforce it.

15. The rule should apply here where the breach was failure to pay the major part of the contract consideration. The contractor, and derivatively the defendant insurer, cannot enforce either the assumption-of-risk clause or the waiver clause in the contractor-subcontractor ' contract.

16. The contractor is liable to the subcontractor under the payment clause of the subcontract, and the defendant is liable to the subcontractor under the payment bond.

Appeal from a judgment of the Circuit Court of the City of Richmond. Hon. Melvin R. Hughes, Jr., judge presiding.

Affirmed.

William A. Young, Jr. (John L. Walker; Williams, Mullen, Christian Dobbins, on briefs), for appellant.

Steven D. Hedges (Randall W. Reavis; Patton, Boggs Blow, on brief), for appellee.


The issues we consider in this appeal arise out of a dispute between two insurance carriers concerning a subcontractor's claim against a general contractor seeking payment for electrical work performed and materials supplied in a building renovation project.

In December 1986, the owner of the Cohen building entered into a renovation contract with Dixie Constructors, Inc. (Dixie). Corroon Black of Ohio, Inc., an insurance agency, furnished Dixie's parent corporation an installation floater insurance policy issued by Aetna Casualty and Surety Company (Aetna) listing Dixie as a named insured.

In a subcontract drafted by Dixie which incorporated the terms of the general contract and the conditions attached thereto, Dixie engaged Starr Electric Company, Inc. (Starr), to perform the electrical work and supply the materials required by the renovation project at a cost of $250,000. Dixie then obtained through Corroon Black a performance bond and a payment bond issued by Federal Insurance Company (Federal). Starr was insured under its own installation floater policy and a property package policy issued 18 years earlier by Aetna and sold by Corroon Black.

On January 13, 1987, during the course of the renovation, the Cohen building was destroyed by fire, and the project was abandoned. At that point, Starr had completed most of the work contemplated by the subcontract.

In response to a fire-damage claim filed by Dixie, Aetna refused coverage and filed a suit for declaratory judgment against Dixie, Corroon Black, the owner, the project lender, and others. Aetna asked the court to declare that its policy with Dixie did not cover the Cohen project. The suit was compromised and settled out of court by the parties.

On April 10, 1987, three months after the fire, Starr asked Dixie for a copy of the payment bond, "if any". Dixie did not respond to Starr's request. Starr then filed a claim under its own policies with Aetna, and Aetna paid Starr $201,280.56 for loss of its work and the electrical materials and equipment consumed in the fire.

On April 4, 1988, Federal mailed Starr a copy of the payment bond. On May 20, 1988, more than a year after the fire, Aetna attached Federal's copy of the payment bond to a motion for judgment against Federal, Dixie's surety, seeking payment in Starr's name of $206,074.38, the balance due under the subcontract. Page two of that copy contained a clause limiting the right to file suit on the bond to two years.

A year later, on June 2, 1989, Federal learned for the first time that Corroon Black had supplied it with an incorrect copy of the payment bond, and that page two of the original executed by the parties contained a clause limiting the right to file suit to one year. Federal so advised the court and opposing counsel, the court allowed the correct page to be substituted in the record, and Federal made a motion to amend its grounds of defense in order to assert the one-year time limitation defense.

The trial court ruled that such a defense must be pled specially, denied the motion to amend, and held that Federal was estopped to plead such a defense. Having considered the evidence stipulated by the parties, the court rejected Federal's several grounds of defense on the merits and entered judgment against Federal in the sum of $203,984.38. We granted Federal's petition for appeal.

I. ESTOPPEL

In its first two assignments of error, Federal contends that the trial court erred "in ruling that the contractual limitations period had to be specially pleaded"; that the court erred "in denying Federal's motion for leave to amend" its grounds of defense to plead that defense; and that the court erred "in ruling that Federal is estopped from asserting the contractual one (1) year limitations period defense". Because we conclude that the court's estoppel ruling was correct, we do not reach the other two rulings.

On brief, Federal argues that the estoppel ruling was in error "because Federal acted reasonably and in good faith in discovering that the parties were litigating an incorrect copy of the payment bond." The delay in the discovery, Federal says, was due to the fact that its own bonding agent "had sent incorrect copies to both Federal and Dixie after the bond was executed." As soon as Federal discovered the error, it continues, it "gave notice . . . more than five (5) months prior to the previously scheduled trial date." That notice, Federal submits, "was . . . adequate" and, once the trial court had agreed to substitute the correct page for the erroneous page, the court should have allowed Federal to assert the limitations defense.

In essence, Federal contends that its good faith excuses its delay in discovering the error in its own contract document. In response, Starr argues that the record shows "a negligent course of dealing by Federal which amply supports the trial court's . . . finding that Federal . . . is barred and estopped from raising any limitation defense." We agree with Starr.

In Contee Sand v. Reliance Ins., 209 Va. 672, 166 S.E.2d 290 (1969), a subcontractor sued a contractor's surety on a payment bond containing a time limitation clause like that in issue here. The evidence showed that the subcontractor, unable to collect from the contractor, had asked the surety's bonding agent whether the contractor had acquired a payment bond. The agent reported that the contractor had a performance bond but no payment bond. More than a year later, the agent discovered that he had overlooked the payment bond which he found " 'stuck ' in the file along with the performance bond" and that "the home office was never advised of the substituted [payment] bond". Id. at 674, 166 S.E.2d at 291-92. When the agent told the subcontractor of his mistake, the subcontractor filed its action against the surety. Invoking the one-year time limitation in the bond, the surety moved to dismiss, and the trial court granted the motion.

[1-2] On appeal, we recognized that the agent's initial response to the subcontractor's inquiry was not an act of "fraud" or one "intentionally designed to mislead" but simply one that "constituted negligence." Id. at 676, 166 S.E.2d at 293. Yet, we said that the subcontractor "had a right to rely on a statement of fact made to him . . . by the person in a position to know the facts"; that the subcontractor "was prejudiced by the failure of [the agent] and [the surety] to provide correct information"; that "[t]he delay in bringing action can be attributed directly to the lack of knowledge by [the subcontractor] . . . of the existence of the bond"; and that "[t]his was the fault of the [the surety's] agent". Id. at 675, 166 S.E.2d at 292.

Reversing the judgment below and remanding the case for further proceedings, we held that, because "the negligence of the agent of [the surety] . . . caused the failure of [the subcontractor] to bring appropriate action . . . [the surety] is estopped. . . to avail itself of the one-year provision in the labor and material payment bond involved here." Id. at 677, 166 S.E.2d at 293-94.

[4-7] We think the principles applied in Contee apply in this case. The facts in the two cases are not dissimilar in any material respect. The conduct of Federal, its bonding agent, and its insured over a period of more than two years following the fire "constituted negligence." Federal was guilty of negligence in failing to investigate the conduct of its agents and, under the doctrine of respondeat superior, Federal is accountable to innocent third parties for the agents' negligence. Jefferson Stand. Ins. Co. v. Hendrick, 181 Va. 824, 834, 27 S.E.2d 198, 202 (1943). Federal's bonding agent sent incorrect copies of the bond to Federal (its "home office") and to Dixie. Dixie, Federal's insured, failed to respond to Starr's inquiry about a payment bond, an inquiry posed three months after the fire. When a person under a duty to disclose facts within his knowledge makes no response to an inquiry posed by one entitled to know the facts, the response, for purposes of estoppel in pais, is a representation. See Chesapeake O.R. Co. v. Walker, 100 Va. 69, 91-92, 40 S.E. 633, 641 (1902); accord, Heath v. Valentine, 177 Va. 731, 737-38, 15 S.E.2d 98, 100 (1941). Although Dixie's failure may have been merely innocent inaction, it was, in effect, a negative response, an implicit representation made by a "person in a position to know the facts". Starr, which had not been a party to the payment bond, had a "right to rely" on such a response; Starr, unable to collect payment from Dixie and unaware during the year following the fire that it had a cause of action against a surety on a payment bond, "was prejudiced by the failure of [Federal and its agents] to provide correct information"; and "[Starr's] delay in bringing action can be attributed directly to the lack of knowledge by [the subcontractor]". Contee, 209 Va. at 675, 166 S.E.2d at 292.

"To establish equitable estoppel, it is not necessary to show actual fraud, but only that the person to be estopped has misled another to his prejudice or that the innocent party acted in reliance upon the conduct or misstatement by the person to be estopped. Elements necessary to establish equitable estoppel, absent a showing of fraud or deception, are a representation, reliance, a change of position, and detriment." T__________ v. T__________, 216 Va. 872-73, 224 S.E.2d 148, 152 (1976) (citations omitted).

Borrowing further from the language in Contee, we hold that, because the negligence of Federal and its agents caused Starr's failure to bring action within a year following the fire, Federal was estopped to invoke the contractual time limitation clause as a defense.

II. SUBROGATION

Next, Federal contends that "the trial court erred in holding that Aetna . . . can assert a right of subrogation against Dixie." Federal relies upon a rule sometimes applied in other jurisdictions which, in Federal's language, holds that "no right of subrogation can arise in favor of an insurer against its own insured." Federal points out that Dixie was a named insured under an installation floater policy issued to Dixie's parent corporation by Aetna. Alternatively, Federal maintains that Dixie "is deemed a co-insured, additional insured, or an intended third party beneficiary under Starr's Aetna policy." The rule "is equally applicable," Federal says, "where the party suffering the loss and the party causing the loss are not insured under the same policy but are, nonetheless, insured by the same insurer."

For purposes of this opinion only, we will accept the rule Federal urges. However, we find it inapplicable in this case.

Following the fire at the Cohen project, Dixie filed a claim under its installation floater policy with Aetna. Aetna denied coverage and filed suit for declaratory judgment against Dixie, Corroon Black, the owner, the project lender, and others. Aetna asked the court "[t]o declare that the Policy does not provide 'Builders Risk ' coverage for the Cohen project." The parties reached an extra-judicial settlement. The settlement agreement provided that Dixie was to receive $530,000 and the owner of the building and the project lender were to receive $1,170,000 from an escrow fund. Aetna had deposited $700,000 in that fund, and Corroon Black (which had issued incorrect certificates of insurance) had deposited $1,000,000.

The agreement did not directly address Aetna's contention that the installation floater policy did not cover the Cohen project. Indirectly, however, it supported that contention when it provided that "Dixie . . . hereby releases AETNA and CORROON BLACK . . . from any claims which have been or could be asserted . . . arising in any way from the fire at the Cohen Building and/or potential or actual insurance coverage for any aspect of the damages caused by that fire". Moreover, the agreement expressly provided that "Aetna does not release any party . . . with respect to the claims that it has arising through assignment, subrogation or otherwise from Starr".

Although, as Federal says, Dixie was named as an insured in the installation floater policy, at the time judgment was entered in the case at bar, Dixie no longer had an insurance claim under that policy, and Aetna, with Dixie's consent, had reserved its subrogation rights.

Yet, Federal insists that it was entitled to coverage as a co-insured under Starr's policy with Aetna. Federal invokes the rule applied in Walker v. Vanderpool, 225 Va. 266, 271, 302 S.E.2d 669, 672 (1983), that "where the plaintiff has contracted to protect the defendant from a loss by procuring insurance, the plaintiff (or his subrogee) may not recover for that loss from the defendant even if the loss is caused by the defendant's negligence."

Federal contends that Article 10 of the subcontract required Starr to procure and maintain fire insurance for the entire project and that, as in Walker, this requirement was intended "for the benefit of both Dixie and Starr." Consequently, Federal believes, Dixie was an additional insured under Starr's Aetna policy within the meaning of the rule that an insurer cannot subrogate against its own insured.

Starr maintains that Federal's interpretation of Article 10, which makes no mention of fire insurance, is contradicted by Paragraph 11.3.1 of the General Conditions which states in part that, "[u]nless otherwise provided, the owner shall purchase and maintain property insurance upon the entire work . . . [which] shall insure against the perils of fire". Because we decide this issue on other grounds, we need not resolve this dispute over interpretation of the contract language.

Starr argues that the facts of record permit no finding of such intent. Its policy with Aetna was not one procured for the Cohen project but one it had carried for 18 years. In the interpretation of ambiguous language in a contract, the construction put upon it by the contracting parties is entitled to great weight in the courts. Am. Realty v. Chase Manhattan, 222 Va. 392, 403, 281 S.E.2d 825, 831 (1981). Introduced as an exhibit, that policy showed that, whenever Starr and Aetna had intended to add a third party to coverage, they had done so by written endorsement appended to the original document. With respect to the Cohen project, they had not done so.

Moreover, we agree with Starr that Dixie's claim to coverage under Starr's policy with Aetna falls within the classification of "claims which have been or could be asserted". As such, it was one of the claims Dixie released in its settlement agreement with Aetna. Accordingly, we hold that the rule in Walker does not apply here.

Because we conclude that Dixie was not an insured in either Aetna policy within the meaning of the rule Federal urges, we will uphold the trial court's ruling on the subrogation issue.

III. ASSUMPTION OF RISK and WAIVER

Finally, Federal argues that, even if Aetna had the right to prosecute Starr's contractual claim against Dixie, the trial court erred in awarding damages to the plaintiff because "(A) Starr expressly assumed the risk of loss to all its work, labor, and materials involved in the project and (B) Starr waived any right to recover from Dixie." Federal refers to selective language in the subcontract and in the General Conditions to the general contract incorporated in the subcontract. We will assume, without deciding, that this language supports the interpretation Federal puts upon it.

At the time the Cohen building was destroyed by fire, Dixie had paid Starr only $21,150 of the $227,224.38 due under the subcontract. Hence, Dixie was in breach of its contractual obligation to pay past due installments in the total sum of $203,984.38.

[13-14] "[I]n suits for specific performance, the plaintiff to entitle himself to relief must show . . . full compliance with the terms of the contract on his part . . . ." Harman v. Moss, 117 Va. 676, 682, 86 S.E. 111, 113 (1915). "The general rule is, that a court of equity will not specifically enforce a contract at the suit of a party who is himself in default in respect thereto, or has himself violated its terms and obligations." Grubb v. Moore, 108 Va. 72, 83, 60 S.E. 757, 761 (1908) (citations omitted). The rule in equity applies generally to actions at law for breach of contract. "The party who commits the first breach of a contract is not entitled to enforce it . . . ." Hurley v. Bennett, 163 Va. 241, 253, 176 S.E. 171, 175 (1934).

While we have held that this rule does not apply when the breach "did not 'go to the root of the contract' " but "only to a minor part of the consideration", Neely v. White, 177 Va. 358, 366, 14 S.E.2d 337, 340 (1941) (failure to pay $1,000 of $15,000 consideration), we think the rule in Hurley should apply here where the breach was failure to pay $203,984.38 of the $227,224.38 contract consideration. We hold, therefore, that Dixie, and derivatively Federal, cannot enforce either the assumption-of-risk clause or the waiver clause in the Dixie-Starr contract. Accordingly, Dixie is liable to Starr under the payment clause of the subcontract, and Federal is liable to Starr under the payment bond.

Invoking another clause in the subcontract, Federal argues that Dixie was not in breach of its contract with Starr at the time of the fire because the owner of the project had not paid Dixie three monthly installments due at that time. So far as appears from the record before us, Dixie never pled this defense, submitted it by stipulation, or otherwise raised it for consideration by the trial court, and we will not consider it for the first time on appeal. Rule 5:25.

Finding no merit in Federal's assignments of error, we will affirm the judgment entered below.

Affirmed.

Page xi


Summaries of

Federal Ins. Co. v. Starr Elec. Co.

Supreme Court of Virginia
Nov 8, 1991
242 Va. 459 (Va. 1991)
Case details for

Federal Ins. Co. v. Starr Elec. Co.

Case Details

Full title:FEDERAL INSURANCE COMPANY v. STARR ELECTRIC COMPANY

Court:Supreme Court of Virginia

Date published: Nov 8, 1991

Citations

242 Va. 459 (Va. 1991)
410 S.E.2d 684

Citing Cases

Horton v. Horton

Generally, a party who commits the first breach of a contract is not entitled to enforce the contract.…

Countryside Orthopaedics, P.C. v. Peyton

[7-8] In doing so, we apply the principle that "[g]enerally, a party who commits the first breach of a…