From Casetext: Smarter Legal Research

Elm Haven Construction Ltd. Partnership v. Neri Construction LLC

United States Court of Appeals, Second Circuit
Jul 23, 2004
376 F.3d 96 (2d Cir. 2004)

Summary

holding that reasonable notice was not given to surety where replacement subcontractor was hired five weeks before default declared

Summary of this case from Flatiron-Lane v. Case Atl. Co.

Opinion

No. 03-7967.

Argued: June 10, 2004.

Decided: July 23, 2004.

Appeal from a judgment in the United States District Court for the District of Connecticut (Goettel, Judge) granting summary judgment against a bond obligee's claims under Performance and Payment Bonds. The district court held that the bond obligee failed to trigger the Performance Bond by declaring the principal in default, and that the bond obligee was not a proper claimant under the Payment Bond. We affirm.

JENNIFER A. OSOWIECKI, Pepe Hazard LLP, Hartford, Connecticut, for Plaintiff-Counter-Defendant-Appellant.

JAMES V. SOMERS, (Dennis C. Cavanaugh, Robert M. Barrack, Peter E. Striniste, Jr., on the brief) Halloran Sage LLP, Hartford, Connecticut, for Defendant-Appellee.

Before: WALKER, Chief Judge, WINTER, and JACOBS, Circuit Judges.


Elm Haven Construction L.P. ("Elm Haven") appeals from Judge Goettel's grant of summary judgment to United States Fidelity and Guaranty Company ("USFG") on Elm Haven's claims against Performance and Payment Bonds issued by USFG. The district court held that USFG was not liable on the Performance Bond because Elm Haven failed, as required by the bond, to declare a default and to allow USFG to cure that default before Elm Haven hired a replacement subcontractor. The court further held that USFG was not liable to Elm Haven on the Payment Bond because Elm Haven was not a "claimant" entitled to sue on the bond and had not been assigned the rights of any claimant. We affirm.

BACKGROUND

On January 26, 1999, Elm Haven and Neri Construction LLC ("Neri") entered into a subcontract agreement with Neri as subcontractor and Elm Haven as general contractor. Pursuant to the subcontract agreement, Neri purchased a Performance Bond and a Payment Bond from USFG on March 16, 1999. Connecticut law governs the subcontract agreement and the bonds.

The Performance Bond, which was in the amount of $3,642,600, imposed certain obligations and conferred certain rights on USFG ("Surety") if Elm Haven ("Obligee") declared Neri ("Principal") to be "in default," as follows:

Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee's obligations thereunder:

(1) Surety may promptly remedy the default subject to the provisions of paragraph 3 herein, or;

(2) Obligee after reasonable notice to Surety may, or Surety upon demand of Obligee, may arrange for the performance of Principal's obligation under the subcontract subject to the provisions of paragraph 3 herein;

(3) The balance of the subcontract price, as defined below, shall be credited against the reasonable cost of completing performance of the subcontract.

The subcontract agreement between Neri and Elm Haven was made a part of the Performance Bond by reference. The subcontract agreement outlined procedures to be followed in the event of a default by Neri. Elm Haven was required to give Neri 72 hours written notice to cure a default, and if Neri did not cure, Elm Haven could perform the work itself, withhold payment from Neri, and/or terminate its subcontract agreement with Neri and hire another subcontractor. Thus, a partial default under the subcontract agreement did not require a termination of that agreement.

The Payment Bond was for $3,642,600 "for the use and benefit of claimants." The bond defined a "claimant" as "one having a direct contract with the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract." Under the bond, only claimants who were not paid within 90 days of performance could sue USFG for the amount due. The subcontract agreement was incorporated into the Payment Bond by reference. That agreement gave Elm Haven several rights with respect to Neri's subcontractors — the potential claimants under the Payment Bond — including the right to ask sub-subcontractors if they were being paid, to refuse progress payments to Neri if such payments were necessary to satisfy liens filed by third parties, and to issue joint progress payment checks to Neri and its subcontractors if Elm Haven believed that the sub-subcontractors were not being paid. The subcontract agreement also included the following sentence, handwritten and initialed by both Neri and USFG, in three places: "No payments will be made to subcontractors sub-subcontractors or suppliers without prior approval of this subcontractor [Neri] and its bonding company [USFG]."

About two months after work began on the project, Neri and Elm Haven began complaining about each other's performance. Elm Haven sent several letters to Neri, copied to USFG, detailing its complaints about Neri's performance and failure to respond to inquiries from Elm Haven. It also sent letters to USFG requesting its "assistance in this matter." Beginning in April, several letters informed USFG and Neri that certain portions of the work for which Neri was responsible would be performed by others because Neri had either failed to perform, or claimed that it was not contractually required to perform, that work. For example, the April 30 letter stated that, because Neri had failed to perform certain parts of its work, Elm Haven "hereby provides notice to [Neri] that this work will be performed by others in accordance with" the default provisions of the subcontract agreement. On May 17, 2001, Elm Haven contracted with another subcontractor — Sweeney Excavation — to replace Neri. Moreover, two of Neri's sub-subcontractors or suppliers made payment claims against Elm Haven, and one of them filed a mechanic's lien against Elm Haven. Elm Haven paid the lienholder claimant directly, without seeking approval from Neri or USFG.

Finally, on June 26, 2001, Elm Haven wrote directly to USFG, noting that it had been "forced to supplement NERI forces in completing the balance of contract work," that Neri had "virtually abandoned" the project as of April 30, and that Elm Haven had incurred an estimated loss of $942,102. USFG responded by stating that it was not liable to Elm Haven under the Performance Bond.

The Performance Bond issued by USFG in connection with this matter clearly sets forth the requirements for notice of default necessary to trigger any obligation on the part of the surety. The language of the Performance Bond clearly requires that, in order to trigger the surety's obligations, the principal shall be in default and that the obligee shall affirmatively declare the principal in default. Review of the file reveals that there has been no declaration of default which would trigger the surety's obligations. Elm Haven's unilateral actions have precluded USFG from performing an investigation and exercising its options under the bond.

Elm Haven replied that it had declared Neri in default at least by April 30, 2001, and that USFG therefore was liable on the Performance Bond.

Elm Haven also sought payment from USFG under the Payment Bond, which was denied. Elm Haven then brought the instant suit against USFG and Neri on July 11, 2001, alleging in pertinent part that USFG breached its obligations under both bonds and under the implied covenant of good faith and fair dealing.

DISCUSSION

The district court granted USFG's motion for summary judgment on August 22, 2003. Relying primarily on L A Contracting v. Southern Concrete Services, Inc., 17 F.3d 106 (5th Cir. 1994), the court held that the "declaration of default term" of the Performance Bond was unambiguous and was satisfied only by a "sufficiently clear, direct, and unequivocal or precise declaration of default." Elm Haven Constr. L.P. v. Neri Constr., LLC, 281 F. Supp.2d 406, 413 (D. Conn. 2003). In the court's view, no such declaration occurred prior to Elm Haven's June 26, 2001 letter, by which time Elm Haven had hired Sweeney Excavation, thus "preclud[ing] USFG from exercising its options" under the bond and rendering the bond void. Id. at 414.

The court also granted summary judgment against Elm Haven's claim on the Payment Bond. Id. at 415-16. The court held that Elm Haven was not a "claimant" within the meaning of the Payment Bond and therefore not entitled to recover under it. Id. at 414-15. Furthermore, Elm Haven had never sought approval from Neri or USFG before paying any claimants, as required by the subcontract agreement, and no claimant had assigned its rights under the Payment Bond to Elm Haven. Id. Finally, the court granted summary judgment against Elm Haven on its implied covenant of good faith and fair dealing claim because that claim was "inextricably tied" to its claim on the Performance Bond. Id. at 415. The grant of summary judgment resolved only the disputes between Elm Haven and USFG, leaving Elm Haven's case against Neri intact, and the district court certified the partial judgment for appeal under Rule 54(b).

We review the district court's grant of summary judgment de novo. Brody v. Village of Port Chester, 345 F.3d 103, 108 (2d Cir. 2003). A bond is a contract, and "we look to standard principles of contract interpretation to determine the rights and obligations of a surety under a bond." United States Fid. Guar. Co. v. Braspetro Oil Servs. Co., 369 F.3d 34, 51 (2d Cir. 2004). "One of those principles is that, before a surety's obligations under a bond can mature, the obligee must comply with any conditions precedent." Id.

In order to trigger USFG's liability under the Performance Bond, two conditions had to be met. First, Neri had to be "in default" under the subcontract agreement, and second, Elm Haven had to "declare [Neri] to be in default under the" subcontract agreement. Such a declaration of default had to be made to USFG in precise terms. See id. at 57 (a "condition precedent to the Sureties' obligations under the Bonds was a clear notice of default terminating the [principal's] rights under the Contracts."); L A Contracting Co., 17 F.3d at 111 ("A declaration of default sufficient to invoke the surety's obligations under the bond must be made in clear, direct, and unequivocal language. The declaration must inform the surety that the principal has committed a material breach or series of material breaches of the subcontract, that the obligee regards the subcontract as terminated, and that the surety must immediately commence performing under the terms of its bond."). In Braspetro, this court quoted L A Contracting for the proposition that "`evidence [is] insufficient as a matter of law to establish a declaration of default' where `[n]one of the letters [obligee-general contractor] sent to [principal-subcontractor] and [surety] even contained the word `'default`' and where `other items of correspondence' did not contain an `unequivocal declaration of default.'" Braspetro, 369 F.3d at 57 (quoting L A Contracting, 17 F.3d at 111).

The notice of default requirement of the Performance Bond was not met in this case prior to the June 26, 2001 letter. None of Elm Haven's previous letters "even contained the word `default'" or an "unequivocal declaration of default." Id. At best, the earlier letters notified Neri and USFG that Elm Haven was exercising its rights under the default provisions of the subcontract agreement. However, the letters clearly evidenced Elm Haven's desire to continue its arrangements with Neri and to keep the subcontract agreement in force. If Elm Haven wanted to trigger the Performance Bond at that point, it would have had to terminate its relationship with Neri and give USFG an opportunity to complete the project itself or hire others to do so. None of Elm Haven's pre-June 26 letters demonstrates an intent to end its relationship with Neri and allow USFG to take over the project; to the contrary, these letters provided notice that part of Neri's work would be performed by others, indicating only that Neri would continue to perform some work under the agreement and requesting USFG's help in improving the ongoing relationship with Neri.

USFG concedes that the June 26 letter functioned as a declaration of default. By that date, however, Elm Haven had breached its obligation to USFG under the Performance Bond to give USFG the option to cure Neri's default. As noted, Elm Haven hired a replacement subcontractor five weeks before declaring default in the June 26 letter, and incurred further payment obligations in hiring replacement subcontractors before actually defaulting Neri. Thus, Elm Haven failed to meet the requirements of the Performance Bond, excusing USFG from its performance.

Summary judgment was also properly granted against Elm Haven on its Payment Bond claim. It is undisputed that Elm Haven is not a "claimant" within the meaning of the bond and was not assigned the rights of any claimant. In fact, on this appeal Elm Haven asserts its right to payment only on the theory of equitable subrogation. However, Elm Haven forfeited any argument based on this theory by failing to raise it at any time in the district court. See Leyda v. Allied Signal, Inc., 322 F.3d 199, 207 (2d Cir. 2003).

Even if Elm Haven's equitable subrogation claim were preserved, it is meritless. Under Connecticut law, "the doctrine of equitable subrogation is broad enough to include every instance in which one person, not acting as a mere volunteer or intruder, pays a debt for which another is primarily liable, and which in equity and good conscience should have been discharged by the latter." Westchester Fire Ins. Co. v. Allstate Ins. Co., 236 Conn. 362, 371 (1996) (internal quotation marks and citation omitted). Equitable subrogation benefits only those who have some obligation, however indirect, to pay the debt at issue. For example, it applies to an insurer who pays its insured's medical bills before a suit against the party who caused the injury has been completed, id. at 372-73, or to a surety who pays its obligee and then sues its principal to vindicate the rights of that obligee, Pa. Nat'l Mut. Cas. Ins. Co. v. City of Pine Bluff, 354 F.3d 945, 951 (8th Cir. 2004).

In paying a claimant, Elm Haven must be deemed an "intruder" because the subcontract agreement explicitly prohibited Elm Haven from paying any of Neri's sub-subcontractors or suppliers without express permission from Neri and USFG. Furthermore, the agreement set forth alternatives for Elm Haven if it believed that a claimant was not being paid on time — for example, the issuance of joint checks. Elm Haven argues that it is entitled to equitable subrogation due to the language of the Payment Bond, which "firmly bound" USFG to Elm Haven for the benefit of the "claimants." Elm Haven has it backwards; if Elm Haven were "firmly bound" to do something for the benefit of the claimants, it would be entitled to equitable subrogation and would not be a mere volunteer or intruder. The fact that USFG is so bound does not mean, however, that Elm Haven had any obligation that distinguished it from a volunteer or intruder.

We also affirm the grant of summary judgment against Elm Haven's claim for breach of the implied covenant of good faith and fair dealing underlying the Performance Bond. Under Connecticut law, "[e]very contract carries an implied covenant of good faith and fair dealing requiring that neither party do anything that will injure the right of the other to receive the benefits of the agreement." Habetz v. Condon, 224 Conn. 231, 238 (1992). "Bad faith means more than mere negligence; it involves a dishonest purpose." Id. at 237. By the time Elm Haven declared Neri to be in default in the June 26 letter, Elm Haven had already taken actions sufficient to nullify its own rights to the benefits of the Performance Bond — namely, it had hired a replacement subcontractor. USFG did nothing, and could have done nothing at that point, to breach the implied covenant of good faith and fair dealing; by the time it learned of the default, Elm Haven had already breached the terms of the Performance Bond. Furthermore, USFG did not breach the implied covenant by failing to respond to Elm Haven's earlier letters; none of them constituted a declaration of default, and USFG was entitled to take action only after such a declaration had been made. See L A Contracting, 17 F.3d at 111 ("Before a declaration of default, sureties face possible tort liability for meddling in the affairs of their principals.").

CONCLUSION

For the foregoing reasons, the judgment of the district court is affirmed.


Summaries of

Elm Haven Construction Ltd. Partnership v. Neri Construction LLC

United States Court of Appeals, Second Circuit
Jul 23, 2004
376 F.3d 96 (2d Cir. 2004)

holding that reasonable notice was not given to surety where replacement subcontractor was hired five weeks before default declared

Summary of this case from Flatiron-Lane v. Case Atl. Co.

finding surety's performance under the bond was excused where the plaintiff "hired a replacement subcontractor five weeks before declaring default . . ., and incurred further payment obligations in hiring replacement subcontractors before actually defaulting" the subcontractor

Summary of this case from United States ex rel Agate Steel, Inc. v. Jaynes Corp.

finding that obligee that hired a replacement subcontractor five weeks before declaring a default breached its obligation to surety under performance bond to give surety the option to cure the default and that surety was therefore excused from performing under the bond

Summary of this case from RLI Insurance v. St. Patrick's Home for the Infirm & Aged

concluding that a surety was "excus[ed] ... from its performance" under a bond because the general contractor "hired a replacement subcontractor five weeks before declaring [the original subcontractor's] default ... and incurred further payment obligations in hiring replacement subcontractors before actually defaulting [the original subcontractor]"

Summary of this case from Cornerstone Pavers, LLC v. Zenith Tech Inc. (In re Cornerstone Pavers, LLC)

upholding requirement that obligee formally declare default

Summary of this case from Colorado Structures v. Insurance Co.

noting that one of the "standard principles of contract interpretation" applicable to surety bonds "is that, before a surety's obligations under a bond can mature, the obligee must comply with any conditions precedent" (quoting U.S. Fid. & Guar. Co. v. Braspetro Oil Servs. Co., 369 F.3d 34, 51 (2d Cir. 2004) )

Summary of this case from Arch Ins. Co. v. The Graphic Builders LLC

In Elm Haven, a general contractor and a subcontractor entered into a subcontract which required the subcontractor to obtain a performance bond and a payment bond.

Summary of this case from Curtiss-Manes-Schulte, Inc. v. Safeco Ins. Co. of Am.

In Elm Haven, the Second Circuit, applying Connecticut law, held that summary judgment was "properly granted against [the obligee] on its Payment Bond claim" because the obligee was neither a "claimant" under the bond, nor "was [it] assigned the rights of any claimant."

Summary of this case from Travelers Casualty Surety Company v. Dasny

In Elm Haven, the court held that certain of the obligee's letters failed to give notice of the subcontractor's default sufficient to trigger the surety's obligations under the bond where those letters merely sought the surety's "assistance" with its complaints about the subcontractor's performance of its obligations, and provided "notice" to the subcontractor that its work would be performed by others in accordance with subcontract's default provisions.

Summary of this case from CC-Aventura, Inc. v. Weitz Company, LLC

stating an obligee's declaration of a principal's default sufficient to trigger a surety's obligations on a performance bond must be made in "precise terms"

Summary of this case from CC-Aventura, Inc. v. Weitz Company, LLC

In Elm Haven Constr. Ltd. P'ship v. Neri Const. LLC, 376 F.3d 96, 100 (2d Cir. 2004), the Second Circuit confronted the issue of what constituted a declaration of default in the context of a performance and payment bond and chose to adopt the Fifth Circuit approach as articulated in L A Contracting Co. v. S. Concrete Servs., Inc., 17 F.3d 106 (5th Cir. 1994).

Summary of this case from John A. Russell Corporation v. Fine Line Drywall, Inc.
Case details for

Elm Haven Construction Ltd. Partnership v. Neri Construction LLC

Case Details

Full title:ELM HAVEN CONSTRUCTION LIMITED PARTNERSHIP…

Court:United States Court of Appeals, Second Circuit

Date published: Jul 23, 2004

Citations

376 F.3d 96 (2d Cir. 2004)

Citing Cases

CC-Aventura, Inc. v. Weitz Company, LLC

Further, "[t]he declaration must inform the surety that the principal has committed a material breach or…

Travelers Casualty Surety Company v. Dasny

"`[B]efore a surety's obligations under a bond can mature, the obligee must comply with any conditions…