From Casetext: Smarter Legal Research

Eason Oil Company v. Federal Power Commission

United States Court of Appeals, Tenth Circuit
Dec 19, 1961
298 F.2d 468 (10th Cir. 1961)

Opinion

No. 6667.

December 19, 1961.

Robert J. Emery, Oklahoma City, Okla. (Edward E. Soule and Lytle Johnston Soule, Oklahoma City, Okla., of counsel, on the brief), for petitioner.

Arthur H. Fribourg, Washington, D.C. (Ralph S. Spritzer, Howard E. Wahrenbrock and Robert L. Russell, Washington, D.C., on the brief), for respondent.

Before LEWIS and BREITENSTEIN, Circuit Judges, and CHRISTENSON, District Judge.


Petitioner is an independent producer selling natural gas in interstate commerce from the Laverne Field in the Oklahoma Panhandle area. It has contracted with Michigan Wisconsin Pipe Line Company for sale of gas at 17¢ per Mcf with an upward adjustment for the heating value of the gas and submitted the contract as a gas rate schedule to the Federal Power Commission with a request for temporary authorization under emergency conditions, Natural Gas Act, § 7(c), 15 U.S.C.A. § 717f(c).

Both the contract and the facts of concern in this case are similar to those treated and disposed of in the companion case of Sohio Petroleum Company v. Federal Power Commission, 298 F.2d 465. For the reasons therein stated this case is remanded to the Commission for further proceedings.


Summaries of

Eason Oil Company v. Federal Power Commission

United States Court of Appeals, Tenth Circuit
Dec 19, 1961
298 F.2d 468 (10th Cir. 1961)
Case details for

Eason Oil Company v. Federal Power Commission

Case Details

Full title:EASON OIL COMPANY, Petitioner, v. FEDERAL POWER COMMISSION, Respondent

Court:United States Court of Appeals, Tenth Circuit

Date published: Dec 19, 1961

Citations

298 F.2d 468 (10th Cir. 1961)

Citing Cases

Hunt v. Federal Power Commission

Both as to the specific reduction in the initial sales price and in the related problem of requiring a price…