From Casetext: Smarter Legal Research

Dutchess Quarry v. Firemen's

Appellate Division of the Supreme Court of New York, Third Department
Apr 29, 1993
190 A.D.2d 36 (N.Y. App. Div. 1993)

Summary

In Dutchess Quarry, the bond imposed a certified mailing condition precedent to the notice provision that defendant relied upon in seeking to dismiss the claim under the bond.

Summary of this case from Bricklayers Ins. & Welfare Fund v. Speranza Brickwork, Inc.

Opinion

April 29, 1993

Appeal from the Supreme Court, Dutchess County, Ralph A. Beisner, J.

Steven G. Rubin, Mineola, for appellant-respondent.

Gellert Cutler, P.C., Poughkeepsie (Terry D. Horner of counsel), for respondent-appellant.


In December 1989 defendant executed as surety a $5,497,000 labor and materials payment bond on behalf of its principal, BIB Construction Company, Inc. (hereinafter BIB), the general contractor on a construction project in the City of Poughkeepsie, Dutchess County, for renovation of its City Hall building. Plaintiff was a concrete supplier for Jonel Associates, Ltd., the masonry contractor on the project.

Plaintiff brought this action on the bond to recover the unpaid balance allegedly due from Jonel for 88 cubic yards of concrete delivered to the project site. Defendant's answer interposed affirmative defenses, inter alia, that the concrete furnished by plaintiff was not in conformity with the contract specifications for the project and that plaintiff "did not comply with the condition precedent certified mail notice provisions of the bond". After issue was joined, plaintiff moved for summary judgment. Defendant cross-moved for the same relief based upon its affirmative defense of noncompliance with the notice provision of the bond requiring 90 days' registered or certified mail notice to any two of the owner, general contractor or surety, plaintiff having only served notice on BIB, the general contractor.

Supreme Court denied plaintiff's motion, concluding that triable issues existed as to whether the concrete delivered on the job conformed to the design mix approved by the engineer and to the specifications. The court also denied defendant's cross motion on the ground that plaintiff's notice to BIB satisfied the notice requirement of State Finance Law § 137 (3), which was controlling. These cross appeals followed.

There should be an affirmance. On its appeal, defendant contends that its labor and materials payment bond was not a statutory bond pursuant to State Finance Law § 137 but a common-law bond, providing broader coverage than a statutory bond. As a common-law bond, defendant argues, the payment bond herein is only enforceable according to its own terms and, thus, the notice provision contained therein, and not that of State Finance Law § 137, is controlling (citing, e.g., Sullivan Highway Prods. Corp. v Edward L. Nezelek, Inc., 52 A.D.2d 986, lv denied 40 N.Y.2d 806). We disagree. Subsequent to Sullivan Highway Prods. Corp. v Edward L. Nezelek, Inc. (supra), State Finance Law § 137 was amended to mandate the furnishing of a labor and materials payment bond on local municipal public works projects such as that undertaken here by the City of Poughkeepsie (see, L 1985, ch 137, § 10; see also, Mem of sponsoring Senator and Member of Assembly, Bill Jacket, L 1985, ch 137).

Thus, by the foregoing amendment, the Legislature extended to municipal public works contracts the strong public policy underlying the original enactment of State Finance Law § 137 regarding State public projects, i.e., to provide protection to persons furnishing labor and materials on such projects by guaranteeing payment even where there is no fund or insufficient funds due the general contractor or subcontractor against which a labor or materials lien could be filed (see, Chittenden Lbr. Co. v Silberblatt Lasker, 288 N.Y. 396, 404; State Bank v Dan-Bar Contr. Co., 23 Misc.2d 487, 491, affd 12 A.D.2d 416, affd 12 N.Y.2d 804). The remedy on the payment bond guaranteed by State Finance Law § 137 "`is in the nature of a third-party beneficiary recovery. It is dependent neither on the existence of a lien fund or a Lien Law trust fund for its utilization or enforcement'" (Syracuse Supply Co. v Seaboard Sur. Co., 167 A.D.2d 830, quoting Tri-City Elec. Co. v People, 96 A.D.2d 146, 150, affd 63 N.Y.2d 969).

Prior to the foregoing 1985 amendment to State Finance Law § 137, it was discretionary on the part of a local municipal government whether to require a payment bond and, if so, either a statutory or common-law bond (see, Triple Cities Constr. Co. v Dan-Bar Contr. Co., 285 App. Div. 299, 304, affd 309 N.Y. 665). By virtue of the 1985 amendment, municipalities no longer have the option to deny persons furnishing labor and materials on local public projects the protection of State Finance Law § 137, or to provide less protection to such persons. This being so, at least as to the furnishing of labor and materials on public projects covered by State Finance Law § 137, we are of the view that a labor and materials payment bond cannot dilute the protection of the statute by imposing notice conditions precedent to payment which are more onerous than that required by State Finance Law § 137 (3). The Federal courts have held, in construing the Miller Act (40 U.S.C. § 270a et seq.), the model for State Finance Law § 137 (see, Russo Trucking Excavating v Pennsylvania Resource Sys., 169 A.D.2d 239, 243), that the purpose of the statutory notice provision is secondary and subordinate to the primary statutory objective of protecting persons furnishing labor and materials on Federal public works projects (see, United States v Andrews, 406 F.2d 790, 794; Noland Co. v Allied Contrs., 273 F.2d 917, 920-921). Thus, any such more burdensome notice provision having the effect of weakening the financial protection afforded statutory beneficiaries would be void as violative of the public policy embodied in State Finance Law § 137 as amended (see, Loomis v Maguire's Equip. Sales, 124 A.D.2d 82, 85, lv denied 70 N.Y.2d 606; Rivers v Ben Constr. Corp., 29 A.D.2d 1048; Matter of Dobbs Ferry Union Free School Dist. [Dobbs Ferry United Teachers], 90 Misc.2d 819, 828).

Because the furnishing of concrete for the Poughkeepsie City Hall renovation project clearly fell within the scope of State Finance Law § 137, and concededly plaintiff complied with the notice required under that section, plaintiff's right to recover on the payment bond cannot be defeated because it failed to meet the additional notice requirement of the bond; Supreme Court therefore properly denied defendant's motion for summary judgment based on that ground.

We also agree with Supreme Court's conclusion that an outstanding issue of fact is presented here as to whether the concrete plaintiff delivered met the requirements of plaintiff's contractual obligations. Hence, Supreme Court's denial of the cross motions for summary judgment should be upheld in all respects.

MERCURE, MAHONEY, CASEY and HARVEY, JJ., concur.

Ordered that the order is affirmed, without costs.


Summaries of

Dutchess Quarry v. Firemen's

Appellate Division of the Supreme Court of New York, Third Department
Apr 29, 1993
190 A.D.2d 36 (N.Y. App. Div. 1993)

In Dutchess Quarry, the bond imposed a certified mailing condition precedent to the notice provision that defendant relied upon in seeking to dismiss the claim under the bond.

Summary of this case from Bricklayers Ins. & Welfare Fund v. Speranza Brickwork, Inc.

referring to noncompliance with the notice provision in the state's "little Miller Act" as an affirmative defense

Summary of this case from Paul Reed Constr. & Supply, Inc. v. Arcon, Inc.

In Dutchess Quarry Supply Co. (190 AD2d at 39), the Appellate Division, Third Department, held that a payment bond cannot dilute the protection of State Finance Law § 137 (3) "by imposing notice conditions precedent to payment which are more [*14]onerous than that required by [that statute]."

Summary of this case from American Architectural, Inc. v. Marino
Case details for

Dutchess Quarry v. Firemen's

Case Details

Full title:DUTCHESS QUARRY SUPPLY COMPANY, INC., Respondent-Appellant, v. FIREMEN'S…

Court:Appellate Division of the Supreme Court of New York, Third Department

Date published: Apr 29, 1993

Citations

190 A.D.2d 36 (N.Y. App. Div. 1993)
596 N.Y.S.2d 898

Citing Cases

Bricklayers Ins. & Welfare Fund v. Speranza Brickwork, Inc.

Prior to 1985, municipalities had discretion to decide whether they would require a bond in accordance with…

Scaccia Corp v. Hartford Ins. Co.

However, in a case decided in 1993, the Third Department apparently threw out all of the above distinctions…