From Casetext: Smarter Legal Research

County of Nassau v. H. Sand Co., Inc.

Appellate Division of the Supreme Court of New York, Second Department
Nov 28, 1988
144 A.D.2d 619 (N.Y. App. Div. 1988)

Summary

upholding trial court's determination that “evidence of the routine recalibration of temperature controls was not proof that actual construction had not already been completed ... but merely disclosed that an incidental punch list item relating to the project remained open”

Summary of this case from Shawnlee Constr., LLC v. J.K. Scanlan Co.

Opinion

November 28, 1988

Appeal from the Supreme Court, Nassau County (Robbins, J.).


Ordered that the order is affirmed, with costs.

The defendant constructed heating, ventilating and air-conditioning systems in the plaintiff's utilities plant. On December 4, 1979, the plaintiff commenced this breach of contract action against the defendant to recover damage for defective construction. Thereafter, the defendant moved for summary judgment dismissing the complaint as time barred.

A cause of action predicated upon defective construction accrues upon completion of "actual physical work" on the construction contract (Cabrini Med. Center v. Desina, 64 N.Y.2d 1059, 1061; Phillips Constr. Co. v. City of New York, 61 N.Y.2d 949; State of New York v. Lundin, 60 N.Y.2d 987). In this case, the key date for Statute of Limitations purposes is December 4, 1973. In accordance with a prior decision and order of this court, a trial was conducted pursuant to CPLR 3212 (c) to determine if actual physical work under the contract was completed prior to December 4, 1973 (see, County of Nassau v Sand Co., 114 A.D.2d 483).

The admissible evidence proffered by the plaintiff did not suffice to controvert the defendant's testimonial and documentary proof that the only work performed after December 4, 1973 was its subcontractor's routine recalibration of temperature controls. The fact that the defendant did not certify the temperature controls, an open punch list item, 100% complete until the submission of its final requisition for payment covering the period from April 16, 1973 to September 30, 1974, did not suffice to create a genuine triable issue of fact that ongoing construction occurred after December 4, 1973. The two prior requisitions for payment (No. 21, covering the period June 7, 1972 to July 1, 1972; and No. 22, covering the period July 1, 1972 to June 5, 1973) indicated that the temperature control item was already 99% complete, leaving only a small amount, valued at less than one tenth of 1% of the total contract, which was done between April 15, 1973 and September 30, 1974. Furthermore, the only rational inference to be drawn is that the temperature controls were fully installed and calibrated as of May 7, 1973, when the defendant's project manager notified the plaintiff that all punch list items had been completed but requested an extension of time to process the paper work needed to enable the defendant to obtain payment for completed change order work could be processed. The defendant's project manager John Quinn explained that the temperature control item was left open on requisition No. 22, which covered the period ending June 5, 1973, in order to keep the contract open so the paper work pertaining to payment for completed change order work. The defendant's project manager John Quinn explained that the temperature control item was left open on requisition No. 22, which covered the period ending June 5, 1973, in order to keep the contract open so the paper work pertaining to payment for completed change order work could be processed. Moreover, the plaintiff's project manager Walter Strauss conceded that Quinn's letter of August 26, 1974, which notified the county with respect to an open item that its subcontractor had completed the calibration of the Bristol systems and BTU meters, was, as testified by Quinn, a reference to recalibration work. The recalibration of operational temperature controls, which had been calibrated when initially installed before the key Statute of Limitations date, was done over two years after the county had accepted beneficial occupancy of the heating, ventilating and air-conditioning systems and after the guarantee period for those systems had expired. The recalibration of the temperature controls at issue merely consisted of turning an "Allen screw" while checking the flow rate of chill water, hot water, and steam with a portable flow meter. Quinn characterized the recalibration of temperature controls as a routine adjustment necessitated by change in load use by the county, as when the county placed in operation 2, rather than 1, boilers.

Based upon the probative evidence adduced at the trial, the trial court correctly found, as a matter of law, that evidence of the routine recalibration of temperature controls was not proof that actual construction had not already been completed prior to December 4, 1973, but merely disclosed that an incidental punch list item relating to the project remained open (see, State of New York v. Lundin, 60 N.Y.2d 987, supra; see also, Phillips Constr. Co. v. City of New York, 61 N.Y.2d 949, 951, supra).

Even if the recalibration of latently defective temperature controls is characterized as repair work in light of the testimony of the plaintiff's project manager that the temperature control panel never functioned "acceptably" prior to December 4, 1973, such repair work was at most incidental to the construction of the heating, ventilating and air-conditioning systems and cannot serve to extend the accrual date of the plaintiff's cause of action (see, Cabrini Med. Center v. Desina, 64 N.Y.2d 1059, 1061, supra; Yeshiva Univ. v. Fidelity Deposit Co., 116 A.D.2d 49, 53-54).

Since "by no rational process could the trier of the facts base a finding in favor of the [plaintiff] upon the evidence * * * presented" (see, Blum v. Fresh Grown Preserve Corp., 292 N.Y. 241, 245; Lipsius v. White, 91 A.D.2d 271, 277), the court properly discharged the jury at the close of all the evidence upon finding, as a matter of law, that no physical work on the construction contract was completed on or after December 4, 1973. Accordingly, the court did not err in granting the defendant's motion for summary judgment dismissing the complaint as barred by the six-year Statute of Limitations. Kunzeman, J.P., Weinstein, Rubin and Kooper, JJ., concur.


Summaries of

County of Nassau v. H. Sand Co., Inc.

Appellate Division of the Supreme Court of New York, Second Department
Nov 28, 1988
144 A.D.2d 619 (N.Y. App. Div. 1988)

upholding trial court's determination that “evidence of the routine recalibration of temperature controls was not proof that actual construction had not already been completed ... but merely disclosed that an incidental punch list item relating to the project remained open”

Summary of this case from Shawnlee Constr., LLC v. J.K. Scanlan Co.
Case details for

County of Nassau v. H. Sand Co., Inc.

Case Details

Full title:COUNTY OF NASSAU, Appellant, v. H. SAND CO., INC., Respondent

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Nov 28, 1988

Citations

144 A.D.2d 619 (N.Y. App. Div. 1988)

Citing Cases

Shawnlee Constr., LLC v. J.K. Scanlan Co.

Nor is this a case where the nature of the work performed was solely and indisputably incidental. Cnty. of…

Matter of Rcdolner, LLC v. 271 Mullberry St.

The scope of the work described in the Agreement indicated that Dolner's correction of conditions related to…