Coalinga Mohawk Oil Company v. R. H. Herron Co.

Court of Appeal of California, First District, Division Two
Jun 7, 1921
53 Cal.App. 75 (Cal. Ct. App. 1921)

Opinion

Civ. No. 3830.

June 7, 1921.

APPEAL from a judgment of the Superior Court of Los Angeles County. J. P. Wood, Judge. Affirmed.

The facts are stated in the opinion of the court.

C. W. Durbrow, F. B. Austin and W. I. Gilbert for Appellant.

Geo. Whitaker and R. W. Kemp for Respondents.


Plaintiff appeals from a judgment in favor of defendants in a suit to recover damages for breach of contract. The complaint alleged that on the fifth day of March, 1917, plaintiff and defendants entered into a written contract whereby defendants agreed to sell to plaintiff and plaintiff agreed to purchase from defendants certain quantities of oil-well casing and that defendants agreed to make deliveries thereof on certain specified dates. It was then alleged that defendants had failed to make deliveries, that the price of such casing had greatly increased over the price fixed in the contract; that when the contract was executed the defendants knew that plaintiff intended to use the casing for the purpose of drilling oil wells; and that by reason of the failure in delivery of the casing plaintiff had been damaged to the extent of $102,660, segregated as follows: Increased cost of casing $12,350; interest on other equipment purchased by plaintiff but remaining idle on account of failure to deliver casing $1,750; anticipated profits from oil wells if they had been sunk as contemplated $88,560.

Demurrers to the complaint were overruled and separate answers were filed by each defendant. The Oil Well Supply Company denied the execution of any contract with plaintiff, and as the trial court found in accordance with this denial, this defendant may be dismissed from further consideration. The defendant R. H. Herron Co. denied the execution of the contract pleaded in the complaint and set forth in haec verba the full contract entered into between the parties; it then set forth facts upon which it relied to excuse performance of the contract so pleaded.

Consideration should first be given to the pleadings. If the plaintiff had fully pleaded the contract which was in fact executed, without any further allegation than those appearing in its complaint, the action would have fallen on demurrer. By an incomplete statement of the transaction plaintiff was able to put forth a complaint for breach of contract to deliver certain specified quantities of casing on specific dates, whereas the contract actually made contained the specific proviso: "We cannot guarantee deliveries, but have promise for shipment as near to the dates you mention as it is possible for the mill to ship. We will do all we possibly can to have the goods shipped." This is far different from the contract pleaded by plaintiff "that defendants agreed to deliver 3500 feet of . . . casing on October 1, 1917; 3500 feet . . . on January 1, 1918," etc.

Plaintiff failed to sustain the allegations of its complaint that the contract pleaded was either executed or breached. [1] The defendant could have rested upon its denial of the execution of such a contract. [2] The finding of the trial court that the contract pleaded was never entered into was amply supported by the evidence and is in itself sufficient to warrant an affirmance of the judgment. [3] However, the defendant R. H. Herron Co. elected to go further and put in issue another contract and alleged facts to excuse its failure to perform it. This issue was tried and the bulk of the testimony related to the circumstances surrounding the transaction between the parties and the conditions which prevented said defendant from making the deliveries at the time requested by plaintiff.

In this connection evidence was offered to prove that this particular kind of casing could be procured from a single manufacturer in Pittsburg, Pennsylvania; that about the time the contract was executed the United States government placed large orders with this concern for war materials; that such orders had precedence over all other orders from private concerns, both as to manufacture in the mills and transportation over railroad lines; that defendant R. H. Herron Co. did not neglect or refuse to deliver the casing described, but did all in its power reasonably to procure shipment and make deliveries as requested by plaintiff.

The court found these facts to be true. The finding is supported by the evidence and is sufficient to sustain the judgment. [4] The alleged conflict in the findings in reference to the damages suffered and the failure to find on the issue of special damages are alike immaterial, since no damages were recoverable.

The judgment is affirmed.

Sturtevant, J., and Langdon, P. J., concurred.

A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on August 4, 1921.

All the Justices concurred, except Angellotti, C. J., and Wilbur, J., who were absent.


Summaries of

Coalinga Mohawk Oil Company v. R. H. Herron Co.

Court of Appeal of California, First District, Division Two
Jun 7, 1921
53 Cal.App. 75 (Cal. Ct. App. 1921)
Case details for

Coalinga Mohawk Oil Company v. R. H. Herron Co.

Case Details

Full title:COALINGA MOHAWK OIL COMPANY (a Corporation), Appellant, v. R. H. HERRON…

Court:Court of Appeal of California, First District, Division Two

Date published: Jun 7, 1921

Citations

53 Cal.App. 75 (Cal. Ct. App. 1921)
199 P. 813

Citing Cases

Central Heights Improvement Co. v. Memorial Parks

The evidence was relevant and material as showing respondents' effort to comply with the condition set forth…