From Casetext: Smarter Legal Research

CNY Mechanical Associates v. Fidelity & Guaranty Insurance

Appellate Division of the Supreme Court of New York, Fourth Department
Feb 3, 1995
212 A.D.2d 989 (N.Y. App. Div. 1995)

Opinion

February 3, 1995

Appeal from the Supreme Court, Onondaga County, Mordue, J.

Present — Denman, P.J., Balio, Lawton, Callahan and Doerr, JJ.


Order unanimously affirmed without costs. Memorandum: McKinley Mechanical, Inc. (McKinley) was hired as a heating, ventilation and air conditioning subcontractor in connection with construction of a building on the Syracuse University campus. Defendant, Fidelity Guaranty Insurance Company (FG), issued a Labor and Material Payment Bond (Bond) in the sum of $1,193,908 for McKinley's performance on that contract. McKinley hired CNY Mechanical Associates, Inc. (CNY Mechanical) to perform certain work on its behalf. Upon completion of performance, CNY Mechanical made a claim upon the Bond, asserting that McKinley refused to pay $225,000 that was owing to CNY Mechanical for its work. FG refused to pay, and CNY Mechanical commenced this action to recover on the Bond.

CNY Mechanical moved for summary judgment, and FG cross-moved pursuant to CPLR 3211 to dismiss the complaint upon the ground that CNY Mechanical had failed to satisfy two conditions precedent. Specifically, FG asserted that, because CNY Mechanical essentially agreed to perform all of McKinley's work, McKinley's subcontract was assigned to CNY Mechanical, and thus, CNY Mechanical was not a "claimant" within the meaning of the Bond; it also asserted that the action was not commenced within one year from the date that McKinley ceased work. Supreme Court held that, by failing to assert the affirmative defenses of lack of capacity to sue and Statute of Limitations in its answer, FG waived those defenses.

On appeal, FG contends that qualifying as a claimant and satisfying the contractual Statute of Limitations pursuant to the terms of the Bond are conditions precedent to recovery and that CNY Mechanical was required to allege compliance with those conditions precedent in its complaint. We disagree.

A party is not required to plead the performance or occurrence of a condition precedent contained in a contract (CPLR 3015 [a]). If a plaintiff fails to allege the performance or occurrence of such a condition precedent, the defendant must deny compliance with the condition precedent specifically and with particularity (CPLR 3015 [a]), and the defendant's failure to assert a specific denial constitutes a waiver of that defense (see, Igbara Realty Corp. v. New York Prop. Ins. Underwriting Assn., 63 N.Y.2d 201, 218). In this case, however, CNY Mechanical alleged compliance with the conditions set forth in the Bond, and FG's general denial of those allegations obviated the need for a specific denial (see, Allis-Chalmers Mfg. Co. v. Malan Constr. Corp., 30 N.Y.2d 225, 233; Siegel, Practice Commentaries, McKinney's Cons Laws of N.Y., Book 7B, CPLR C3015:2). The general denial was sufficient to cast upon CNY Mechanical the burden of proving at trial that it complied with the conditions of the Bond (see, CPLR 3015 [a]), and amendment of the answer to assert the failure to comply with those conditions is unnecessary (see, Allis-Chalmers Mfg. Co. v. Malan Constr. Corp., supra). Because pleading noncompliance with those conditions is unnecessary, the court did not err in denying FG's motion for leave to amend the answer.


Summaries of

CNY Mechanical Associates v. Fidelity & Guaranty Insurance

Appellate Division of the Supreme Court of New York, Fourth Department
Feb 3, 1995
212 A.D.2d 989 (N.Y. App. Div. 1995)
Case details for

CNY Mechanical Associates v. Fidelity & Guaranty Insurance

Case Details

Full title:CNY MECHANICAL ASSOCIATES, INC., Respondent, v. FIDELITY GUARANTY…

Court:Appellate Division of the Supreme Court of New York, Fourth Department

Date published: Feb 3, 1995

Citations

212 A.D.2d 989 (N.Y. App. Div. 1995)
624 N.Y.S.2d 700

Citing Cases

ROEL PARTNERSHIP v. AMWEST SURETY INS. CO

If a plaintiff fails to allege performance of a contractual condition precedent, then a defendant must…

Metropolis v. Natl. Envirn

The appellants' remaining contentions are not properly before this Court ( see Parr v Ronkonkoma Realty…