From Casetext: Smarter Legal Research

Chastain v. Atlanta Gas Light Co.

Court of Appeals of Georgia
Jun 25, 1970
176 S.E.2d 487 (Ga. Ct. App. 1970)

Opinion

45320.

ARGUED MAY 6, 1970.

DECIDED JUNE 25, 1970.

Action for damages. Cobb Superior Court. Before Judge Ravan.

Shoob, McLain Jessee, C. James Jessee, Jr., for appellants.

Raymond M. Reed, J. Dudley McClain, Jr., Nall, Miller Cadenhead, Lowell S. Fine, Woodruff, Savell, Lane Williams, Edward L. Savell, Gerald C. Friedlander, Custer Smith, Lawrence B. Custer, Dennis Fain, Douglas Dennis, Troutman, Sams, Schroder Lockerman, Robert L. Pennington, Wm. H. Schroder, Jr., O'Kelley, Hopkins Van Gerpen, Earl J. Van Gerpen, John M. Bobis, for appellees.


1. Since an appeal may be taken under Code Ann. § 81A-156(h) where a summary judgment is granted on any issue or as to any party, the motion to dismiss the appeal as premature is denied. See Code Ann. § 6-701(4) (Ga. L. 1965, p. 18; 1968, pp. 1072, 1073); McLeod v. Westmoreland, 117 Ga. App. 659 (1) ( 161 S.E.2d 335); Levy v. G.E.C. Corp., 117 Ga. App. 673 ( 161 S.E.2d 339). Nor is the motion to dismiss because of laches and delay meritorious since there was no transcript (the delay was in the preparation of the record), and the delay is explained by (1) the request of one of the appellees to include the entire record in the transmittal of the appeal; and (2) the further certification by the clerk that the delay was not due to "any fault on the part of counsel for the appellants but to the stress of business."

2. Questions of negligence, as to cause and proximate cause, and as to what negligence or whose negligence constitutes the proximate cause of the damages incurred in tort cases, except in plain and palpable cases, are solely for the jury. Long Constr. Co. v. Ryals, 102 Ga. App. 66 (1) ( 115 S.E.2d 726); Malcom v. Malcolm, 112 Ga. App. 151, 153 ( 144 S.E.2d 188).

3. A party who moves for summary judgment in a case premised on negligence has a considerable burden, and if the moving party is defendant, sometimes he cannot obtain a summary judgment when he might be able to secure a directed verdict at the trial of the case. A motion for summary judgment may be denied a defendant in such case because he is not simply weighing his evidence against the evidence of the plaintiff, but each and every allegation of negligence in the plaintiff's complaint must be negated, with all presumptions being in favor of the plaintiff (the party opposing the motion for summary judgment), and the complaint of plaintiff thereby being elevated to the dignity of evidence. See Southern Bell Tel. Tel. Co. v. Beaver, 120 Ga. App. 420 (3) ( 170 S.E.2d 737). This court has repeatedly held, and particularly in negligence cases, that it is permissible to grant a motion for summary judgment only when there is no genuine issue of material fact, and the moving party is entitled to a judgment as a matter of law. See Holland v. Sanfax Corp., 106 Ga. App. 1, 4 ( 126 S.E.2d 442); Malcom v. Malcolm, 112 Ga. App. 151, supra. The burden to establish the lack of a genuine issue of fact and the right to a judgment as a matter of law is upon the moving party, and any and all reasonable doubts as to the existence of such issue are resolved against the movant, with the trial court giving the party opposing the motion "the benefit of all favorable inferences that may be drawn from the evidence." Holland v. Sanfax Corp., supra. Thus, in negligence cases, it must be plainly and palpably shown that the defendants in no way contributed to the proximate cause of the damages incurred in order for the trial court to sustain a motion for summary judgment in their favor.

4. Where, as here, the defendants sought summary judgment, and the plaintiff submitted an affidavit of an expert in the field of professional engineering who stated his qualifications and knowledge of the interrelated practice of architecture, engineering, and land surveying as each pertains to the planning, designing and supervision of the construction of apartment and housing projects, together with his knowledge of and familiarity with design and construction of utility distribution systems, and his testimony conflicts with the testimony of the movants, it cannot be said that a plain and palpable case of no negligence exists in favor of these defendants. He states positively that he examined all the maps, plats and drawings related to the construction project on which the plaintiff as a subcontractor was damaged; that he observed the work site, which includes all the projects of the owner, including contiguous roads, streets, and easements for utilities, areas used for storage of materials, rights of way used for access to and from work areas; all borrow and spoil areas for securement and disposal of earth-fill materials, which specifically included reference to the southeast corner of the work area as being a part thereof, and none of the plot plans, plats or documents prepared by or for the architect showed the existence of "the subject twelve-inch high pressure gas line on the premises and work site." He further deposed that "by omission ... from each of the drawings or specifications and with no notations on any of these drawings or specifications to the effect that some or part of the utility locations might be omitted therefrom" each of the various engineers and consultants who were jointly sued, and the architect, had furnished incorrect and improper advice "for safe construction including moving of earth materials in the borrow area in and around the existing twelve-inch gas line." He also deposed that when any utility installations are omitted from a topographical survey, "it is conventional to note the survey drawing in order to alert the users of that drawing that all utilities have not been shown on the drawing"; that these locations normally are marked in some manner to warn the public of the presence of hazard, particularly in populated areas or rapidly developing areas; and that experience has shown that large high-pressure gas pipeline installations are inherently dangerous and require protection from casual contact by the public and that these must be adequately marked or protected from direct contact with construction operations. He further deposed that both utilities involved occupied a common easement through the work site and borrow area; that in accordance with good, proper and customary practice within the utility industry, it was his expert opinion that it was the responsibility of both and each to periodically and regularly patrol the areas of their utilities and easements in order to detect and prevent dangerous conditions from resulting in injuries to the public from their installations, "including construction activities on or about these easements." There was also testimony that the gas line was not marked in any manner on the surface.

(a) A general rule of law is that persons performing architectural, engineering and other professional and skilled services assume an obligation to exercise a reasonable degree of care, skill and ability, which, generally, is taken and considered to be that degree of care and skill as under similar conditions and like surrounding circumstances, is ordinarily employed by their respective professions. See Block v. Happ, 144 Ga. 145 (2) ( 86 S.E. 316); Housing Authority of City of Carrollton v. Ayers, 211 Ga. 728, 733 ( 88 S.E.2d 368); Bodin v. Gill, 216 Ga. 467 (1) ( 117 S.E.2d 325). This standard of care properly is the subject of expert opinion. The plaintiff having offered the affidavit of an expert in this instance showing his examination of the premises, including the maps, plats, drawings and specifications, and his expert opinion based hypothetically on the facts of the case from his examination thereof, creates a conflict with the other evidence in the record. See Shea v. Phillips, 213 Ga. 269 (2) ( 98 S.E.2d 552); Howell v. Jackson, 65 Ga. App. 422, 423 ( 16 S.E.2d 45); Hayes v. Brown, 108 Ga. App. 360, 363 ( 133 S.E.2d 102); Covil v. Robert Co. Associates, 112 Ga. App. 163, 167 ( 144 S.E.2d 450).

(b) There was evidence that the architect required the owner to furnish a survey of the area; that the preparatory survey was made with the power line and a water line shown thereon, but the gas line was not shown on such survey; and that if it had been shown thereon it would have been utilized by the other concerned professionals. There was conflicting testimony as to whether or not an expert surveyor could have located the gas pipeline. The above evidence is sufficient to deny summary judgment as to the surveyor preparing the preparatory survey for the project, and a jury question remains as to whether or not he was negligent.

(c) The architect contends that his contract does not hold him liable to the plaintiffs; but as the chief artificer, master builder and superintendent of the execution of his own designs, plans and specifications drawn for the owner, he is, in effect, the alter ego of the owner on the job site as a professional to carry out the construction about which the owner has little knowledge and for which the architect has been employed. The conflicting evidence here was sufficient to deny summary judgment, and to hold the architect in the case for trial. Cox v. Ray M. Lee Company, Inc., 100 Ga. App. 333 ( 111 S.E.2d 246); Covil v. Robert Co. Associates, 112 Ga. App. 163, supra.

(d) Summary judgment, for the same reasons stated above, should have been denied each and every one of the professional and mechanical engineers employed in their professional capacities to perform services on this project.

(e) The evidence shows, although conflicting, that the 12-inch pipeline as constructed was less than 24 inches below the surface at the fire location and in other places, and without any markings as to its location, although on the trial other reasons may be offered why it was less than 24 inches below the surface. Thus the evidence was in dispute as to both the construction and maintenance of this gas pipeline. The court erred in granting summary judgment in favor of the construction company which constructed the pipeline for the gas company, and, erred in granting summary judgment in favor of the gas company which maintained the gas pipeline in this manner, knowing of its inherent and intrinsic danger to others. See Hand v. Harrison, 99 Ga. App. 429, 430 ( 108 S.E.2d 814); Cox v. Ray M. Lee Co., 100 Ga. App. 333, 335, supra; Covil v. Robert Co. Associates, 112 Ga. App. 163, 166, supra.

(f) The easements of record fail to show the power company had any power to control and limit the use of the gas company's easement or to mark its location. Indeed, the evidence is conflicting as to whether the explosion and fire occurred on the easement of the power company, although occurring when the excavation equipment struck the pipeline of the gas company. The power company's only connection with this occurrence is that it holds an easement for power lines over the same land as the gas company's easement for a pipeline. The power company does not have the duties of an owner or occupier of this land. The grantee of an easements does not have such a status. Donalson v. Ga. Power c. Co., 175 Ga. 462 ( 165 S.E. 440). While the power company may or may not have had knowledge about the construction through its regular patrols of the power line, it would not be required to warn the public of hidden dangers and perils on a neighbor's property. Indeed, there is no evidence it had such knowledge. The only testimony as to its knowledge is that of an expert who states that in accordance with good, proper and customary practices of utilities making periodic and regular inspections, required in the utility industry, it was the responsibility of both and each of these utilities "to detect and prevent dangerous conditions from resulting in injury to their installations and the public, including construction activities on or about these easements." This testimony cannot be construed to create a duty of each of these utilities to protect the other. The power company did not contribute in any manner to the proximate cause of the damages occurring to the plaintiffs whether or not it had knowledge of the proposed construction.

(g) The court erred in granting the motions for summary judgment against all of the appellees except the Georgia Power Company. The motion for summary judgment was properly granted as to it.

Judgment reversed in part; affirmed in part. Hall, P. J., and Deen, J., concur.

ARGUED MAY 6, 1970 — DECIDED JUNE 25, 1970.


Briefly stated, this is a damage suit arising out of an explosion and fire when the plaintiff's earth-moving equipment, used on a construction site for the Marietta Housing Authority, struck a 12-inch concealed natural gas pipeline of the Atlanta Gas Light Company, causing the subsequent explosion and fire from the release of gas from the ruptured pipe. The plaintiff, a partnership, was a subcontractor under the general contractor, Marietta Construction Co., Inc., for the grading, excavation and earth movement and demolition portions of the general contract. Plaintiff sued the Marietta Housing Authority; the general contractor; Georgia Power Company o whose easement extending across the southeast corner of the Housing Authority property the explosion and fire and subsequent damage allegedly occurred; the Atlanta Gas Light Company which had placed the pipe in a covered ditch or trench thereon; Lockheed-Georgia Co., the plant to which the pipeline was extended, and who agreed to indemnify the Gas Light Company for any damages arising therefrom; the architect involved in the general construction contract; the surveyor of the project whose alleged duty it was to prepare topography information, location of utility lines and easements for the architect; the subsoil engineer whose alleged duty it was to make a survey and investigation for the purpose of determining all construction problems in connection with the soil mechanics development of the site; and the consulting electrical-mechanical engineer of the project whose alleged duty it was to investigate the premises and prepare a survey for the location of buildings to be erected, the location of utilities, including all gas pipelines which were buried underground upon the project property. All of these defendants were sued jointly and severally, plaintiff contending it was their duty to have notified the plaintiff before he entered into the subcontract for the grading, excavation and demolition work on the project of the location of the gas line which he struck, causing the explosion; and contending it was the legal duty of the general contractor to determine the accuracy and reliability of the engineering data reports furnished to the owner by the surveyor, subsoil engineer, the architect and the consulting electrical-mechanical engineer. The petition alleges that numerous conferences were held with the Atlanta Gas Light Company, but that the existence of the 12-inch gas pipeline was not by said company called to the attention of the defendants responsible for determining the exact location of said gas pipeline, and, as a result thereof, none of the defendants, in the exercise of ordinary care, made any notice of or marking of the existence of said pipeline upon the maps, plats, and blueprints or other vital material, information and data which were gathered by them for the architect. The Atlanta Gas Light Company allegedly failed to notify the other defendants of the existence of the line; the line should have been buried at least five feet deep, whereas it was only two feet below the surface, and it also failed to mark the location of the line on the surface which was beneath the surface only two feet. By amendment the defendant Concrete Construction Company was made a party since it was employed by Atlanta Gas Light Company allegedly to lay the 12-inch gas line which is the subject of the lawsuit, based upon the fact that it was to lay the gas line at an average depth of four feet and in no case less than two and a half feet, and yet it failed to properly lay the pipe which resulted in it being put down in a dangerous and defective manner, which was inherently and intrinsically dangerous.

On earlier motions for summary judgment the Marietta Construction Co., Inc., the general contractor, and Lockheed-Georgia Co. were dismissed, and no appeal was taken from the orders granting judgment in favor of these two defendants. The appeal here is from the granting of motions for summary judgment in favor of the Georgia Power Company, Atlanta Gas Light Company, Cleveland M. Cail, Jr. (the architect), Charles H. Sack (the consulting engineer), G. Trenholm Baker (the original surveyor), Benjamin S. Persons (a partner in the firm of subsoil engineers), and Concrete Construction Co.


Summaries of

Chastain v. Atlanta Gas Light Co.

Court of Appeals of Georgia
Jun 25, 1970
176 S.E.2d 487 (Ga. Ct. App. 1970)
Case details for

Chastain v. Atlanta Gas Light Co.

Case Details

Full title:CHASTAIN et al. v. ATLANTA GAS LIGHT COMPANY et al

Court:Court of Appeals of Georgia

Date published: Jun 25, 1970

Citations

176 S.E.2d 487 (Ga. Ct. App. 1970)
176 S.E.2d 487

Citing Cases

Weems v. Association Life Ins. Co.

Under the evidence presented the finder of fact would be authorized, but not required, to determine that some…

Turner v. Noe

]" Werbin Tenenbaum, Inc. v. Heard, 121 Ga. App. 147 (2) ( 173 S.E.2d 114). "A party who moves for summary…