From Casetext: Smarter Legal Research

Centre Great Neck Co. v. Penn Encord, Inc.

Appellate Division of the Supreme Court of New York, Second Department
Oct 30, 2000
276 A.D.2d 735 (N.Y. App. Div. 2000)

Summary

In Centre Great Neck Co. v. Penn Encord, Inc., 715 N.Y.S.2d 71 (N.Y.Sup.Ct. 2000), a landlord sued a tenant and guarantor to recover for breach of a lease.

Summary of this case from Fortune Funding v. Ceridian Corporation

Opinion

Submitted September 28, 2000.

October 30, 2000.

In an action to recover damages for breach of a lease, the defendant Rite Aid Corporation appeals, as limited by its brief, from so much of a judgment of the Supreme Court, Queens County (Leviss, J.H.O.), dated June 21, 1999, as is in favor of the plaintiff and against it in the principal sums of $24,650 for roof repairs, and $7,500 for foundation repairs.

Robert C. Crimmins, Riverhead, N.Y. (Linda D. Calder and Donna M. Spicer of counsel), for appellant.

Morton Povman, Forest Hills, N.Y., for respondent.

Before: MYRIAM J. ALTMAN, J.P., WILLIAM D. FRIEDMANN, GABRIEL M. KRAUSMAN, NANCY E. SMITH, JJ.


DECISION ORDER

ORDERED that the judgment is modified, on the law, by (1) deleting the provision thereof awarding damages for roof repairs in the principal sum of $24,650 and substituting therefor a provision awarding damages for roof repairs in the principal sum of $1,953, and (2) deleting the provision thereof awarding the principal sum of $7,500 for foundation repairs; as so modified, the judgment is affirmed insofar as appealed from, with costs to the appellant.

The defendant Penn Encord, Inc. (hereinafter the tenant), leased commercial space from the plaintiff, Centre Great Neck Co., pursuant to a 10-year lease commencing in 1991. Approximately five years later, in 1996, the tenant vacated the premises. The plaintiff commenced a summary nonpayment proceeding and obtained a warrant of eviction. It initiated this action against the tenant and the defendant Rite Aid Corporation (hereinafter Rite Aid), as the guarantor on the lease, seeking rents and taxes for the balance of 1996, as well as an award of an attorney's fee and various repair costs. The plaintiff moved for summary judgment and was awarded judgment as a matter of law on both liability and damages on its cause of action for rent and property taxes. The plaintiff was awarded judgment as a matter of law on liability on its causes of action for repairs, legal fees, and costs, and those causes of action were referred to a Judicial Hearing Officer (hereinafter the JHO) for an inquest on damages. The JHO concluded that Rite Aid was responsible to pay, inter alia, the costs of a complete roof replacement in the sum of $24,650, and foundation repairs in the form of a "Vulcan" sump-pump system in the sum of $7,500.

Where, as here, a lease contains clauses requiring the tenant to maintain the premises in "good condition" and to surrender the premises in the same condition as at the commencement of the lease, the two clauses must be read together (see, Bushwick Realty Co. v. Sanitary Fire Proofing Contracting Co., 129 AD 533) to determine the intent of the parties. Reading the clauses together, the subject lease required the tenant to keep the premises in a state of repair such that it could be returned to the plaintiff in as good a condition as it was in at the commencement of the lease (see, Norman S. Riesendfeld, Inc. v. R-W Realty Co., 223 AD 140).

If the plaintiff had intended the tenant to put the property in a condition better than it was in at the commmencement of the lease, it could have expressly contracted for that result. "The law is well settled that changes in a lease are not to be presumed or implied; and no additional liability will be imposed upon a tenant unless it is clearly within the provisions of the instrument under which it is claimed" (455 Seventh Ave. v. Frederick Hussey Realty Corp., 295 N.Y. 166, 172).

Under these circumstances, the plaintiff cannot be awarded any more than the cost of patching the roof. In this regard, the record supports an award of $1,953. The plaintiff is not entitled to an award which includes costs related to the installation of a "Vulcan" sump-pump system to prevent future water damage to the foundation, since these repairs would unquestionably put the premises in a better condition than it was in at the commencement of the lease (see, Novendstern v. Mt. Kisco Med. Group, 177 A.D.2d 623).


Summaries of

Centre Great Neck Co. v. Penn Encord, Inc.

Appellate Division of the Supreme Court of New York, Second Department
Oct 30, 2000
276 A.D.2d 735 (N.Y. App. Div. 2000)

In Centre Great Neck Co. v. Penn Encord, Inc., 715 N.Y.S.2d 71 (N.Y.Sup.Ct. 2000), a landlord sued a tenant and guarantor to recover for breach of a lease.

Summary of this case from Fortune Funding v. Ceridian Corporation
Case details for

Centre Great Neck Co. v. Penn Encord, Inc.

Case Details

Full title:CENTRE GREAT NECK CO., RESPONDENT, v. PENN ENCORD, INC., DEFENDANT, RITE…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Oct 30, 2000

Citations

276 A.D.2d 735 (N.Y. App. Div. 2000)
715 N.Y.S.2d 71

Citing Cases

Fortune Funding v. Ceridian Corporation

Chergosky, 463 N.W.2d at 526; Brookfield, 584 N.W.2d at 394. In Centre Great Neck Co. v. Penn Encord, Inc.,…

Wanich v. Bitter

Both Paragraph 3 of the lease and the common law require the tenant to surrender possession of the Premises…