From Casetext: Smarter Legal Research

Bd. of Commrs. v. Pub. Util. Comm

Supreme Court of Ohio
Aug 4, 1982
1 Ohio St. 3d 125 (Ohio 1982)

Summary

In Bd.of Commrs. v. Pub. Util. Comm. (1982), 1 Ohio St.3d 125, the commission was confronted, upon rehearing, with unique circumstances calling for a post-test year expense adjustment.

Summary of this case from Columbus Southern Ohio Elec. Co. v. P.U.C

Opinion

No. 81-1680

Decided August 4, 1982.

Public Utilities Commission — Rate increase — Post-test-year adjustments — Authorized, when.

APPEAL from the Public Utilities Commission of Ohio.

On October 9, 1980, intervening appellee, Dayton Power and Light Company ("DP L"), filed an application for a permanent rate increase with appellee Public Utilities Commission ("commission"). In its application, DP L requested that September 30, 1980 be fixed as the date certain and that the calendar year 1981 be established as the test period. The commission approved September 30, 1980 as the date certain; however, it disapproved the requested test year and set the period from April 1, 1980 through March 31, 1981 as the test year.

Hearings were held on DP L's application. Relevant to the present appeal is the testimony of Dennis Holewinski, concerning the need for DP L to upgrade its line clearance, or vegetation management, program. Holewinski testified that in the recent past DP L had failed to maintain a sufficient line clearance program. As a result of this deficiency, there was an increased danger of power outages due to the proximity of trees to DP L's lines. Further, if DP L did not institute the line clearance program soon, the cost of such a program would be greater in the future.

Holewinski is manager of the Environmental Services Division of Asplundh Environmental Services, a consulting company retained by DP L to help plan its line clearing program.

The growth of trees near power lines can cause power outages either by growth directly into the conductor or by falling trees or limbs caused by high winds or storms.

To institute this program, Holewinski recommended adopting a three-cycle plan. Each cycle would last three years. During the first cycle, Holewinski recommended spending $7 million a year.

The commission agreed with Holewinski and, pursuant to R.C. 4905.06, ordered DP L to implement Holewinski's recommendations. The commission next considered the question of how to fund the program. As DP L had expenditures of $3,543,000 for line clearance in the test year, that amount was allowed as a recoverable expense. To assure that DP L had revenues corresponding to the required $7 million dollar annual expenditure, the commission allowed DP L to recover an additional $3,256,000.

This was the amount allocable to DP L's jurisdictional customers which was necessary to reach $7 million in revenue.

Upon application for rehearing, appellants argued, before the commission, that this court's decision in Consumers' Counsel v. Pub. Util. Comm. (1981), 67 Ohio St.2d 372 [21 O.O.3d 234], (" Consumers' Counsel [EOG]") precluded adjustments to a utility's rate base for post-test-year expenditures. The commission disagreed and affirmed its earlier decision.

The appellants are the Board of Commissioners of Montgomery County and the cities of Dayton, Kettering and Moraine, all located within Montgomery County.

The commission reached its initial decision allowing the inclusion of the additional $3.2 million prior to this court's decision in Consumers' Counsel (EOG), supra.

The cause is now before this court as an appeal of right.

Mr. Lee C. Falke, prosecuting attorney, Mr. Henry W. Eckhart and Mr. Herbert C. Hunt, for appellants.

Mr. William J. Brown, attorney general, Mr. Marvin I. Resnik and Mr. Jonathan L. Heller, for appellee.

Mr. Stephen F. Koziar, Jr., Smith Schnacke Co., L.P.A., Mr. Charles J. Faruki, Mr. Paul L. Horstman and Mr. D. Jeffrey Ireland, for intervening appellee.


Before this court, appellants' sole challenge to the commission's order is the propriety of allowing DP L to recover the additional expenses for line clearance. Appellants argue that the inclusion of the additional sum violates the test year concepts contained in R.C. 4909.15. In support of its position, appellants rely on Consumers' Counsel (EOG), supra.

In Consumers' Counsel (EOG), the commission allowed a post-test-year adjustment to East Ohio Gas for increased labor expenses due to the signing of a new labor contract. Upon appeal, this court reversed. We held that R.C. 4909.15(A) precluded East Ohio Gas from recovering post-test-year expenses. However, we recognized that: "In certain circumstances, of course, inclusion of costs not incurred in the test year is proper." 67 Ohio St. 2d at 376.

Here, the commission, upon applications for rehearing, found that because of the unique circumstances present, Consumers' Counsel (EOG) was not a bar to the additional allowance. We agree; therefore, we affirm.

This court has consistently held that we will not disturb the final order of the commission absent a showing of misapprehension, mistake or willful disregard of duty. Columbus v. Pub. Util. Comm. (1979), 58 Ohio St.2d 103, 104 [12 O.O.3d 112]; Consumers' Counsel v. Pub. Util. Comm. (1981), 67 Ohio St.2d 153, 156 [21 O.O.3d 96]. Consequently, we must decide whether allowing the post-test-year adjustment in this case, given these unique circumstances constituted mistake, misapprehension or willful disregard of duty by the commission.

As a starting point, the above-quoted language from Consumers' Counsel (EOG) makes it clear that we did not adopt a per se rule which would preclude all post-test-year adjustments. Rather, while not elaborating, we stated that adjustments would be allowed in certain circumstances. Are these proper circumstances? For reasons that follow, we hold that this is a proper case for the allowance of a post-test-year adjustment.

The uncontroverted testimony, here, was that DP L had not kept its lines as clear as necessary to provide safe, efficient service. If DP L does not improve its performance in this area, more power lines will be damaged with a consequent increase in power outages. This will lead to safety hazards for both DP L's customers and its employees. See R.C. 4905.06. Additionally, costs will increase with delay. DP L will be forced to spend more money on repairs, and delay in implementing the recommended plan will render it more expensive.

Further, R.C. 4909.15(D) provides for adjustments in a utility's rates when they are "insufficient to yield reasonable compensation for the service rendered." In Consumers' Counsel v. Pub. Util. Comm., supra, we stated that R.C. 4909.15(D) gives the commission the authority to "smooth out anomalies in the ratemaking equation that tend to make the test year data unrepresentative for ratemaking purposes." 67 Ohio St. 2d at 166.

R.C. 4909.15(D) provides, in pertinent part:
"When the public utilities commission is of the opinion, after hearing and after making the determinations under divisions (A) and (B) of this section * * * that the maximum rates * * * chargeable by any such public utility are insufficient to yield reasonable compensation for the service rendered, and are unjust and unreasonable, the commission shall:
"* * *
"(2) With due regard to all such other matters as are proper, according to the facts in each case,
"* * *
"(b) * * * fix and determine the just and reasonable rate * * * that will provide the public utility the allowable gross annual revenues under division (B) of this section, and order such just and reasonable rate * * * to be substituted for the existing one. * * *"

Where, as here, the commission orders a utility to adopt a specific plan to assure continued safe, efficient service, R.C. 4909.15(D) provides sufficient statutory authority for post-test-year adjustments. To disallow this adjustment would result in an anomaly in the ratemaking equation, making the test year unrepresentative for ratemaking purposes.

Accordingly, the commission's order is affirmed.

Order affirmed.

CELEBREZZE, C.J., W. BROWN, SWEENEY, HOLMES, C. BROWN and KRUPANSKY, JJ., concur.


The majority opinion turns its back on our holding in Consumers' Counsel v. Pub. Util. Comm. (1981), 67 Ohio St.2d 372 [21 O.O.3d 234]. Therefore, I dissent.

In Consumers' Counsel, supra, the commission had ordered that the utility's rate could include increased expenses arising under a labor contract which was to take effect after the test year. We reversed the commission and concluded that to permit its order to stand "would emasculate the test period concept and abrogate the principle forming the basis of the ratemaking structure." 67 Ohio St. 2 d, at 376. This was in spite of the fact that the utility's request was "based upon a fixed legal obligation * * *." 67 Ohio St. 2 d, at 377 (Holmes, J., dissenting). In reasoning to our holding in that case, we observed:

"Under the provisions of R.C. 4909.15, the commission is to base any grant of a rate increase for utilities on a fair and reasonable rate of return on capital investment, and the costs incurred by the utility during the test period, a 12 month span typically determined by the date of filing of the application.

"* * *

"The language of R.C. 4909.15 is unequivocal. Rate increases are based on costs of rendering utility service during the test period. The dates of the test year follow directly from the date the utility chooses to file for its rate increase. * * *" (Emphasis sic.) 67 Ohio St. 2d, at 374. Those same principles apply to this case and require our reversal of the commission.

Tree-trimming has the laudable aim of minimizing the risk of disruptions in service. Nevertheless, DP L failed to keep current with the challenges of nature. All utilities should stay even, at the very least, with the ravages of the elements and the demands of growing vegetation. Yet, DP L chose when to file its rate request just as the utility had in Consumers' Counsel, supra. DP L also exacerbated the hazard by trimming only nine percent of the trees in each of the prior five years rather than 33 1/3 percent per year. This is not the type of anomaly against which R.C. 4909.15(D) was intended to protect, and we should not permit a utility to turn this kind of conduct into an economic advantage. This is particularly so in light of the fact that DP L's net income increased in 1980 to over $64 million, over $3 million higher than its net income in the previous year. Its net income in the first quarter of 1981 was over $32 million, an increase of $8 million over its forecasted net income for that period.

The holding of the majority, therefore, discourages timely tree-trimming rather than encouraging it. A utility may now receive an early return for tree-trimming expenditures if it delays making them long enough. This serves neither the consuming public nor the purposes of the statutory scheme for ratemaking. R.C. 4909.15.

Accordingly, I would reverse the commission's order and remand the cause to the commission with instructions to decrease the total rate of DP L in an amount consistent with this opinion and our holding in Consumers' Counsel, supra ( 67 Ohio St.2d 372 [21 O.O.3d 234]).


Summaries of

Bd. of Commrs. v. Pub. Util. Comm

Supreme Court of Ohio
Aug 4, 1982
1 Ohio St. 3d 125 (Ohio 1982)

In Bd.of Commrs. v. Pub. Util. Comm. (1982), 1 Ohio St.3d 125, the commission was confronted, upon rehearing, with unique circumstances calling for a post-test year expense adjustment.

Summary of this case from Columbus Southern Ohio Elec. Co. v. P.U.C

In Bd. of Commrs. v. Pub. Util. Comm. (1982), 1 Ohio St.3d 125, 127, we recognized that in certain instances "* * * R.C. 4909.15(D) provides sufficient statutory authority for post-test-year adjustments."

Summary of this case from Ohio Water Service Co. v. Pub. Util. Comm
Case details for

Bd. of Commrs. v. Pub. Util. Comm

Case Details

Full title:BOARD OF COMMISSIONERS OF MONTGOMERY COUNTY ET AL., APPELLANTS, v. PUBLIC…

Court:Supreme Court of Ohio

Date published: Aug 4, 1982

Citations

1 Ohio St. 3d 125 (Ohio 1982)
438 N.E.2d 111

Citing Cases

Ohio Water Service Co. v. Pub. Util. Comm

"* * * R.C. 4909.15(D)(2) authorizes departures from the test-year concept only when necessary to smooth out…

Columbus Southern Ohio Elec. Co. v. P.U.C

This court has never held that the test-year concept is inviolable. In Bd.of Commrs. v. Pub. Util. Comm.…