From Casetext: Smarter Legal Research

Bausenwein v. Allison

Supreme Court, Appellate Division, Fourth Department, New York.
Mar 27, 2015
126 A.D.3d 1466 (N.Y. App. Div. 2015)

Opinion

2015-03-27

John H. BAUSENWEIN, III, Plaintiff–Appellant–Respondent, v. Timothy ALLISON, Defendant–Respondent, Thomas J. Welsh, Individually and doing Business as TJW Custom Homes, Inc., TJW Custom Homes, Inc., and 299 Main Street EA, Inc., Individually and doing Business as TJW Custom Homes, Defendants–Respondents–Appellants.

Hogan Willig, PLLC, Amherst (Allison Bozinski of Counsel), for Plaintiff–Appellant–Respondent. Hiscock & Barclay, LLP, Rochester (Robert M. Shaddock of Counsel), for Defendants–Respondents–Appellants.



Hogan Willig, PLLC, Amherst (Allison Bozinski of Counsel), for Plaintiff–Appellant–Respondent. Hiscock & Barclay, LLP, Rochester (Robert M. Shaddock of Counsel), for Defendants–Respondents–Appellants.
Burgio, Kita, Curvin & Banker, Buffalo (Steven P. Curvin of Counsel), for Defendant–Respondent.

PRESENT: SCUDDER, P.J., CENTRA, PERADOTTO, LINDLEY, AND WHALEN, JJ.

MEMORANDUM:

Plaintiff commenced this action seeking damages for injuries he sustained while working on a construction project on property owned by defendant Timothy Allison, asserting causes of action for common-law negligence and the violation of Labor Law §§ 200, 240(1) and 241 (6). We initially conclude that Supreme Court properly granted Allison's motion for summary judgment dismissing the amended complaint against him. Labor Law §§ 240(1) and 241(6) exempt from liability “owners of one[-] and two-family dwellings who contract for but do not direct or control the work” ( see byrd v. roneker, 90 a.d.3d 1648, 1649, 936 n.y.s.2d 434; Pfaffenbach v. Nemec, 78 A.D.3d 1488, 1489, 911 N.Y.S.2d 520), i.e., homeowners of such dwellings who do not give “ ‘specific direction as to how the injured plaintiff was to accomplish’ ” the injury-producing work (Ledwin v. Auman, 60 A.D.3d 1324, 1325, 875 N.Y.S.2d 711; see Rosenblatt v. Wagman, 56 A.D.3d 1103, 1104, 867 N.Y.S.2d 780). Here, Allison met his initial burden by establishing as a matter of law that he did not direct or supervise plaintiff's work. In support of his motion, Allison submitted, inter alia, the deposition testimony of plaintiff, who, when asked if he knew the identity of the owner of the house on which he was working, answered: “I met him once or twice, but I don't recall his name.” Plaintiff further testified that Allison did not give him any direction as to how to do his work. Allison also submitted his own deposition testimony wherein he asserted that he visited the construction site occasionally “just to find out what stage they were at,” and he never told any worker how to perform his or her job. Allison's testimony is consistent with that of plaintiff's employer, who testified that Allison did not supervise any of the work and did not tell any of the workers how to do their jobs.

The burden of proof thus shifted to plaintiff to raise an issue of fact whether Allison directed or controlled his work, and plaintiff failed to do so. Plaintiff relies primarily on the fact that Allison is identified in the construction contract as the general contractor, but that title is not by itself dispositive ( see McNabb v. Oot Bros., Inc., 64 A.D.3d 1237, 1239, 882 N.Y.S.2d 792). Plaintiff does not identify a single incident in which Allison supervised him or told him how to perform his work. Although Allison, based on his prior experience as a plaintiff in an unrelated Labor Law action, was aware of the need for safety devices at the work site, his actions at the construction site “were those of a ‘legitimately concerned homeowner’ and not those of a supervisor” (Peck v. Szwarcberg, 122 A.D.3d 1216, 1219, 997 N.Y.S.2d 816, quoting Rosenblatt, 56 A.D.3d at 1104, 867 N.Y.S.2d 780). Moreover, because Allison did not direct or control plaintiff's work, the court also properly dismissed the Labor Law § 200 claim and common-law negligence cause of action against Allison ( see id. at 1219–1220, 867 N.Y.S.2d 780).

With respect to the cross appeal of the remaining defendants (collectively, 299 Main Street defendants), we conclude that the court properly denied their motion for summary judgment insofar as it sought dismissal of the Labor Law §§ 240(1) and 241(6) claims against them. Although 299 Main Street EA, Inc., individually and doing business as TJW Custom Homes (299 Main Street), which is owned by defendant Thomas J. Welsh, is identified in the contract with Allison as the “construction manager,” not the general contractor, a construction manager “may be vicariously liable as an agent of the property owner ... where the manager had the ability to control the activity which brought about the injury” (Walls v. Turner Constr. Co., 4 N.Y.3d 861, 863–864, 798 N.Y.S.2d 351, 831 N.E.2d 408; see Campoverde v. Sound Hous., LLC, 116 A.D.3d 897, 897–898, 983 N.Y.S.2d 817; Titus v. Kirst Constr., Inc., 43 A.D.3d 1324, 1325, 843 N.Y.S.2d 878, lv. denied9 N.Y.3d 817, 851 N.Y.S.2d 126, 881 N.E.2d 222). The evidence submitted by the 299 Main Street defendants in support of their motion raised an issue of fact whether they had the ability to control plaintiff's work ( see Reed v. NEA Residential, Inc., 64 A.D.3d 1148, 1149, 881 N.Y.S.2d 345). We note that the contract between 299 Main Street and Allison provided that 299 Main Street would be “an agent” for Allison. The contract further provided that 299 Main Street would select and schedule subcontractors, and was responsible for “[d]ay to day construction activities.” We agree with the 299 Main Street defendants, however, that the court erred in denying their motion insofar as it sought dismissal of the Labor Law § 200 claim and common-law negligence cause of action against them, inasmuch as they established as a matter of law that they did not actually direct or control the work that brought about plaintiff's injuries, and in response plaintiff failed to raise an issue of fact ( see Peck, 122 A.D.3d at 1219–1220, 997 N.Y.S.2d 816). We therefore modify the order accordingly.

Because, as noted, there are issues of fact whether the 299 Main Street defendants acted as Allison's agent, we reject plaintiff's contention that the court erred in refusing to search the record and grant summary judgment in his favor against those defendants under Labor Law §§ 240(1) and 241(6). Finally, we conclude that the court properly denied that part of the 299 Main Street defendants' motion for summary judgment on their cross claim against Allison for contractual and common-law indemnification ( see generally Syracuse Univ. v. Games 2002, LLC, 71 A.D.3d 1531, 1531, 897 N.Y.S.2d 343).

It is hereby ORDERED that the order so appealed from is unanimously modified on the law by granting in part the motion of defendants Thomas J. Welsh, individually and doing business as TJW Custom Homes, Inc., TJW Custom Homes, Inc. and 299 Main Street EA, Inc., individually and doing business as TJW Custom Homes, and dismissing the common-law negligence cause of action and Labor Law § 200 claim against them, and as modified the order is affirmed without costs.


Summaries of

Bausenwein v. Allison

Supreme Court, Appellate Division, Fourth Department, New York.
Mar 27, 2015
126 A.D.3d 1466 (N.Y. App. Div. 2015)
Case details for

Bausenwein v. Allison

Case Details

Full title:John H. BAUSENWEIN, III, Plaintiff–Appellant–Respondent, v. Timothy…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Mar 27, 2015

Citations

126 A.D.3d 1466 (N.Y. App. Div. 2015)
126 A.D.3d 1466
2015 N.Y. Slip Op. 2593

Citing Cases

Wadlowski v. Cohen

& Renovations, Inc., 97 A.D.3d 737, 738, 948 N.Y.S.2d 671 ; see Chowdhury v. Rodriguez, 57 A.D.3d 121, 126,…

Stiegman v. Barden

" An entity is a contractor within the meaning of Labor Law § 240 (1) and § 241 (6) if it had the power to…