Appeal from those parts of an order of Supreme Court, Erie County (Whelan, J.), entered September 24, 2001, that, inter alia, granted in part defendants' motion for summary judgment and dismissed the Labor Law §§ 200, 240(1) and § 241(6) claims.

PAUL WILLIAM BELTZ, P.C., BUFFALO (RUSSELL T. QUINLAN OF COUNSEL), FOR PLAINTIFF-APPELLANT.

ALTREUTER HABERMEHL, BUFFALO (MARI A. MOORMAN OF COUNSEL), FOR DEFENDANTS-RESPONDENTS.

SLIWA LANE, BUFFALO (STEPHEN M. SORRELS OF COUNSEL), FOR THIRD- PARTY DEFENDANT-RESPONDENT.

PRESENT: WISNER, J.P., HURLBUTT, SCUDDER, AND KEHOE, JJ.


MEMORANDUM AND ORDER

It is hereby ORDERED that the order so appealed from be and the same hereby is unanimously modified on the law by granting that part of defendants' motion with respect to the common-law negligence cause of action and dismissing that cause of action and by denying those parts of the motions of defendants and third-party defendant with respect to the claim under Labor Law § 241(6) and reinstating that claim and as modified the order is affirmed without costs.

Memorandum:

Plaintiff was injured at a construction site when a piece of glass fell from a window that he was dismantling, striking and lacerating his left arm. Plaintiff commenced this action against defendant Westfield Academy Central School, the owner of the site, and defendant Concept Construction Corp., the general contractor on the project, alleging causes of action for common-law negligence and the violation of Labor Law §§ 200, 240(1) and § 241(6). Each defendant then commenced a third-party action against plaintiff's employer, Arric Corporation (Arric), seeking contribution or common-law indemnification. Defendants moved for summary judgment dismissing the complaint against them, Arric joined in that motion to the extent that it sought summary judgment dismissing the claims under Labor Law § 240(1) and § 241(6), and plaintiff cross-moved for partial summary judgment on liability on the Labor Law § 240(1) claim. Supreme Court granted those parts of defendants' motion seeking summary judgment dismissing the Labor Law claims, granted Arric's motion in its entirety and denied plaintiff's cross motion. Although the court did not explicitly rule on that part of defendants' motion with respect to the common-law negligence cause of action, the failure to rule is deemed a denial of that part of the motion ( see Brown v. U.S. Vanadium Corp., 198 A.D.2d 863, 864).

Plaintiff concedes on appeal that the court properly dismissed the claim under Labor Law § 240(1). We conclude that the court properly granted that part of defendants' motion seeking summary judgment dismissing the claim under Labor Law § 200 but also should have granted that part of the motion with respect to the common-law negligence cause of action. Defendants established that they had no authority to supervise or control the work being performed by plaintiff at the time of his accident, that the alleged defect or dangerous condition arose out of the subcontractor's own methods of work, and that they lacked actual or constructive notice of the alleged defect or dangerous condition ( see Lombardi v. Stout, 80 N.Y.2d 290, 295; Matter of Fischer v. State of New York, 291 A.D.2d 815, 816; cf. Perry v. City of Syracuse Indus. Dev. Agency, 283 A.D.2d 1017), and plaintiff failed to raise a triable issue of fact. Thus, no liability may be imposed against defendants under principles of common-law negligence or under Labor Law § 200 ( see Comes v. New York State Elec. Gas Corp., 82 N.Y.2d 876, 877, citing Lombardi, 80 N.Y.2d at 295).

We further conclude that the court erred in granting those parts of the motions of defendants and Arric seeking summary judgment dismissing the claim under Labor Law § 241(6). Plaintiff was engaged in "construction * * * or demolition work" protected under that statute ( id.; see 12 NYCRR 23-1.4 [b] [13]), and 12 NYCRR 23-3.3 (b)(3) and (c) are both sufficiently specific and applicable to the facts of this case to support the claim under Labor Law § 241(6) ( see Sponholz v. Benderson Prop. Dev., 273 A.D.2d 791, 791-792; Gawel v. Consolidated Edison Co. of N.Y., 237 A.D.2d 138; cf. Quinlan v. City of New York, 293 A.D.2d 262).

We therefore modify the order by granting that part of defendants' motion with respect to the common-law negligence cause of action and dismissing that cause of action and by denying those parts of the motions of defendants and Arric with respect to the claim under Labor Law § 241(6) and reinstating that claim.


Summaries of

Bald v. Westfield Academy & Central School

Appellate Division of the Supreme Court of New York, Fourth Department
Oct 1, 2002
298 A.D.2d 881 (N.Y. App. Div. 2002)
Case details for

Bald v. Westfield Academy & Central School

Case Details

Full title:JOSEPH BALD, III, PLAINTIFF-APPELLANT, v. WESTFIELD ACADEMY CENTRAL SCHOOL…

Court:Appellate Division of the Supreme Court of New York, Fourth Department

Date published: Oct 1, 2002

Citations

298 A.D.2d 881 (N.Y. App. Div. 2002)
747 N.Y.S.2d 623

Citing Cases

Verdugo v. Fox Bldg. Grp.

We therefore modify the order by denying those parts of defendants' motions seeking summary judgment…

Taylor v. Williams Communications, Inc.

However, the testimony of Neil Silvarole and Mr. Orlando established that the Silvarole defendants did not…