From Casetext: Smarter Legal Research

Bailey v. Martin

Court of Appeals of Georgia
Jan 21, 1960
112 S.E.2d 807 (Ga. Ct. App. 1960)

Opinion

38012.

DECIDED JANUARY 21, 1960.

Action on contract. Chattooga City Court. Before Judge Boney. September 2, 1959.

Robert Edward Surles, for plaintiff in error.

Cook Palmour, A. Cecil Palmour, contra.


The petition in this case stated a cause of action for extra work over and above that stipulated in the contract which was performed by the plaintiff in building a house for the defendants, and the trial court erred in sustaining the general demurrers to the petition.

DECIDED JANUARY 21, 1960.


Lawson Bailey filed suit against W. G. Martin and his wife to recover an amount alleged to be due him on account of certain work performed by him in constructing a house for the defendants. The defendants filed general and special demurrers to the petition, the plaintiff amended and the defendants filed additional general and special demurrers and renewed the original grounds of demurrer. The trial court entered an order sustaining the general demurrers, and the assignment of error here is on that judgment.

The petition as amended alleged substantially that the plaintiff entered into a contract with W. G. Martin to construct a residence on his property; that pursuant to the contract the plaintiff undertook to construct the dwelling; that during the construction the defendants directed the plaintiff to make certain additions of materials, to install certain listed utilities, and to make certain changes in the specifications for materials and labor as per the following itemization:

"[Additions to Job] Labor installation Materials cost. cost. a. Extra lavatory $ 36.00 b. Extra heater 21.60 $ 2.00 c. Wiring for extra heater 3.60 d. Soap and glass holder 6.00 e. 3 outside receptacles 15.00 5.00 f. 6 pull chains (in excess of $50.00 light fixture allowance) 4.20 g. Basement drain 8.00 h. Extra steel post on back porch 8.00 i. Lumber and paint for ceiling and finishing of utility room 15.00 25.00 j. Painting basement room 4.00 8.00 k. Broom closet 4.00 8.00 l. Extra door in basement 7.14 2.50 m. Cement floor for extra room with well pump 22.40 20.00 n. Window for well house 13.10 2.00 o. Putting shelves in closets 2.00 6.00 _________ ________ Totals $170.04 $78.50 Plus sales tax 5.10 _________ Paid on Materials 175.14." "[Changes] Item Changed Extra materials Extra labor cost. cost. a. Substitute 12 inch concrete blocks for 8 inch concrete blocks in foundation walls $300.00 b. Substitute tile flooring for wood flooring in hall and den 126.00 c. Substitute stainless steel sink in kitchen for white steel sink 23.00 d. Substitute exhaust hood and fan equipped with an electric light in kitchen for plain exhaust hood and fan 15.00 e. Changed and moved fireplace to location other than originally specified 3.60 $15.00 f. Cutting hole for air conditioner not originally specified 1.50 ________ ______ $467.60 $16.50 Plus sales tax paid on materials 14.03 ________ $481.63;" that these changes and additions were made pursuant to express directions of the defendants; that petitioner furnished and installed said items and made said changes in reliance upon said express representations that they would pay the cost thereof, that the defendants and petitioner mutually disregarded the provision in the contract requiring such changes and substitutions to be reduced to writing and mutually substituted oral approval of the defendants for written approval referred to in said contract; that these changes and additions to the job entailed additional costs and expense, and that the defendants were informed by the plaintiff that the changes could not be made for the contract price and that the additional and requested items would require the payment of additional sums and that the defendants agreed and promised to pay for the additional costs required in making the changes and additions to the job which totalled $751.77; that the plaintiff completed the house, including the extras sued for, which was accepted by the defendants who upon completion thereof moved into it and paid the plaintiff the sum of $11,927.62, which was the contract price; that the plaintiff had made demand upon the defendants for payment of the additional amount and that they had refused.

A copy of the contract originally entered into between the parties was attached to the petition as an exhibit. In the contract the plaintiff, who was described therein as the contractor, agreed to furnish all materials and perform all work as shown on certain drawings and specifications referred to therein for the total contract price of $11,927.62. The contract further provided that no deviations from the drawings and specifications referred to, or changes or substitutions of material, "shall be made without prior written approval of the owner."


All that a petition needs to allege in order to state a cause of action and to withstand a general demurrer is facts showing the existence of a duty on the part of the defendant, the violation of that duty by the defendant, and the damages accruing to the plaintiff as a result thereof. Vickers v. Georgia Power Co., 79 Ga. App. 456, 458 ( 54 S.E.2d 152); Hogan v. Young Men's Christian Association, 82 Ga. App. 372 ( 61 S.E.2d 161); 41 Am. Jur. 345, Pleading, § 78. After the owner and a builder have entered into a written contract for the construction of a building, they may thereafter, by mutual consent, alter or modify the original contract. Jacksonville A. R. Co. v. Woodworth, 26 Fla. 368 ( 8 So. 177); Cornish v. Suydam, 99 Ala. 620 ( 13 So. 118). Under this rule they may, by subsequent agreement, modify the contract and require thereby deviations and departures from the original contract and enter into a new and completely different agreement. West Haven Water Co. v. Redfield, 58 Conn. 39 ( 18 A. 978); Greene v. Paul, 155 Pa. 126 ( 25 A. 867). When the facts alleged in the petition, reasonably construed, show that the parties have thus entered into a new and distinct agreement, they will be held to have waived by such a course of conduct any right contradictory to the new agreement embodied in the original contract. Cornish v. Suydam, supra; Edmonds v. Welling, 57 Ore. 103 ( 110 P. 533); McDaniel v. Mallary Bros. Machinery Co., 6 Ga. App. 848 ( 66 S.E. 146); Greene County Oil Co. v. McCaw Mfg. Co., 9 Ga. App. 39 ( 70 S.E. 201); Meredith v. Fay Egan Co., 36 Ga. App. 506 ( 137 S.E. 409); Eaves v. Georgian Co., 47 Ga. App. 37 (4) ( 169 S.E. 519); Kennesaw Guano Co. v. Miles Co., 132 Ga. 763 ( 64 S.E. 1087). Thus, where a written contract for the construction of a building is on its face complete within itself and contains therein a stipulation that no changes or alterations or modifications thereof will be allowed unless in writing, the parties may by mutual assent disregard this provision of the contract and enter into a new agreement regarding the same subject matter, and if such new agreement is supported by a sufficient consideration be bound thereby even though its terms may be at variance with the original contract and not in writing. Evans v. Henson, 73 Ga. App. 494 (3) ( 37 S.E.2d 164); Langenback v. Mays, 205 Ga. 706 (1) ( 54 S.E.2d 401, 11 A.L.R. 2d 1221); Fisher v. J. A. Jones Constr. Co., 87 Ga. App. 317, 318 (1) ( 73 S.E.2d 587). It has been held that the sole purpose and effect of stipulations against changes in a building contract except in writing is to prevent the builder from recovering for extras by showing that they were not included in the original contract but were necessary for the completion of the building as thus originally contracted for and that they were furnished by him. Michaud v. MacGregor, 61 Minn. 198 (3) ( 63 N.W. 479). In such a situation where the builder makes alterations which entail the outlay of additional expenses and costs pursuant to the owner's promise to pay therefor and the owner thereafter accepts the building as thus altered and occupies the same, there is sufficient consideration to authorize the recovery by the builder from the owner for such additional expenses and costs shown to have been incurred as the result of such changes. Code § 20-304. Retailer's Service Bureau v. Newman, Frierson McEver Co., 40 Ga. App. 185 (2) ( 149 S.E. 89).

In the instant case, the petition alleges that the defendants requested the changes and additions to the job and expressly promised to pay therefor and that the plaintiff made the changes and supplied the additional items and that the defendants accepted the house as thus changed. His petition does not allege or show that the items sued for were necessary to the completion of the original job in accordance with the original specifications. If the plaintiff can prove the facts alleged, he ought to be entitled to recover his additional costs as set forth in his petition.

In McDaniel v. Mallary Bros. Machinery Co., 6 Ga. App. 848, supra, it was pointed out that the invoking of a stipulation in a contract similar to the one here relied on by the defendant, after the performance of the contract by the plaintiff and the performance of extra work on the promise of the defendant to pay therefor, in effect, works a forfeiture of the plaintiff's rights to recover for such extras. As there said (headnote 1), "forfeiture of rights is not favored and the courts will readily seize upon circumstances arising in the subsequent conduct or transactions of the parties and imply a waiver, in order to prevent a forfeiture because of noncompliance with formal prerequisites." Applying these principles to the instant case, the defendants ought not to be allowed to rely on the requirement of the original contract that changes in the specifications and additions to the contract must be in writing where by a course of conduct consisting of entering into an oral agreement with the plaintiff for changes they induced the plaintiff to make the changes in reliance upon their contemporaneous promise that they would pay therefor, and where they thereafter accepted the building as thus changed. To permit them to thus lull the plaintiff into a false sense of security by a reliance upon their promise to pay and their acceptance of the work and then to invoke the defense that the plaintiff had failed to comply with the formal prerequisites before making the changes and that they were not, therefore, bound to pay therefor would be unconscionable, and the court should seize upon these very circumstances to imply a waiver by the defendants of the formal requirement that such changes be in writing.

The defendants rely on four cases in support of their contention that the plaintiff ought not to recover in this case; they are: Heard v. Dooly County, 101 Ga. 619 ( 28 S.E. 986); Town of Decatur v. Jaudon, 136 Ga. 854 ( 72 S.E. 351); Cobb v. Bond, 39 Ga. App. 637 ( 148 S.E. 411); Grahn Construction Co. v. Pridgen, 49 Ga. App. 720 ( 176 S.E. 656). In all of these cases, with the exception of the Cobb case, the petition did not allege any facts showing an express agreement by the defendant to the changes, or that the changes were not necessary to the completion of the original job. In the Cobb case, the decision turned on the fact that the contractor entered into a contract to construct the building which expressly provided that the owner might make changes therein during the course of the construction and contained no provision for the payment of any additional sums on account of such changes. The owner made changes which were within the purview of that provision of the contract and thus could not be recovered for by the contractor as extras. These cases do not require a different ruling from that now made.

The petition in the instant case alleged that the defendants procured the plaintiff to make the specified changes and additions to the house and that they promised to pay therefor, and that, in reliance on the promise, the plaintiff performed the agreement by making the specified changes and additions. These facts established the existence of a duty on the part of the defendants to pay the plaintiff the cost of such changes and additions. The allegation that the defendants failed and refused to pay for such changes and additions upon demand by the plaintiff established the violation of that duty, and the damages accruing to the plaintiff as the result thereof were shown by the fact that the plaintiff had furnished the labor and materials for such changes and had not received compensation therefor. The petition, therefore, was not subject to general demurrer, and the trial court erred in sustaining the general demurrers of the defendants. See generally in this connection: 9 C. J. 717, Building and Construction Contracts, § 51; 17 C. J. S. 843, Contracts, § 371.

Judgment reversed. Gardner, P. J., and Townsend, J., concur.


Summaries of

Bailey v. Martin

Court of Appeals of Georgia
Jan 21, 1960
112 S.E.2d 807 (Ga. Ct. App. 1960)
Case details for

Bailey v. Martin

Case Details

Full title:BAILEY v. MARTIN et al

Court:Court of Appeals of Georgia

Date published: Jan 21, 1960

Citations

112 S.E.2d 807 (Ga. Ct. App. 1960)
112 S.E.2d 807

Citing Cases

Wood v. Yancey Brothers

Even if the contract provides it may not be changed except by writing, parties may subsequently by mutual…

Mion Chemical Brick Corp. v. Daniel Construction Co.

1. Where a prime contractor, without claiming that the work is covered by the subcontract, orally orders…