From Casetext: Smarter Legal Research

Afran Transport Co. v. the Bergechief

United States Court of Appeals, Second Circuit
Dec 28, 1960
285 F.2d 119 (2d Cir. 1960)

Summary

stating that a district court's discretion to deny prejudgment interest is "a legal discretion, rather than merely one at will."

Summary of this case from Cement Div. v. City of Milwaukee

Opinion

Nos. 86, 87, Dockets 26373, 26374.

Argued December 6, 1960.

Decided December 28, 1960.

Stanley R. Wright, of Burlingham, Hupper Kennedy, New York City (H. Barton Williams and John S. Rogers, of Burlingham, Hupper Kennedy, New York City, on the brief), for Afran Transport Co., appellant.

MacDonald Deming, of Haight, Gardner, Poor Havens, New York City (Richard G. Ashworth and Terence J. Creighton, of Haight, Gardner, Poor Havens, New York City, on the brief), for A/S Sneffon, appellee.

Before CLARK, WATERMAN, and FRIENDLY, Circuit Judges.


Libelant and claimant's vessels were involved in a collision which has been adjudicated as one of mutual fault requiring the division of damages, although the fault of the libelant's vessel was gross and that of claimant's vessel less clear. Afran Transport Co. v. The Bergechief, D.C.S.D.N.Y., 170 F. Supp. 893, affirmed 2 Cir., 274 F.2d 469. Libelant's vessel sustained the greater damage, so that on the stipulated amounts a balance was due libelant of $69,203. It therefore sought interest to run prior to the final decree, but Judge Dimock declined to award any interest prior to its entry, holding as authorities therefor The Wright, 2 Cir., 109 F.2d 699, and Canadian Aviator, Ltd. v. United States, 2 Cir., 187 F.2d 100, certiorari denied 342 U.S. 813, 72 S.Ct. 27, 96 L.Ed. 615, with a reference also to Moore-McCormack Lines, Inc. v. The Esso Camden, 2 Cir., 244 F.2d 198, 202, certiorari denied 355 U.S. 822, 78 S.Ct. 29, 2 L.Ed.2d 37.

Apparently libelant seeks interest only from the time it paid its repair bills, not from the date of the collision.

Possibly Judge Dimock in his brief memorandum may have stated the rule too rigidly; in The Wright, supra, 2 Cir., 109 F.2d 699, we cited the usual rule that interest in admiralty was a matter of the court's discretion and stressed that it must be a legal discretion, rather than one merely at will. So normally the award of interest may await the court's judgment which fixes the amount due. But we would not exclude all discretion in the mutual fault collision case; thus if one vessel is grossly at fault the award of interest to the other may ameliorate somewhat the harsh American rule that division of damages must be equal without reference to the degree of fault. Here under the circumstances shown in our opinion in Afran Transport Co. v. The Bergechief, supra, 2 Cir., 274 F.2d 469, we think denial of pre-decree interest was right.

Affirmed.


Summaries of

Afran Transport Co. v. the Bergechief

United States Court of Appeals, Second Circuit
Dec 28, 1960
285 F.2d 119 (2d Cir. 1960)

stating that a district court's discretion to deny prejudgment interest is "a legal discretion, rather than merely one at will."

Summary of this case from Cement Div. v. City of Milwaukee

suggesting that an award of prejudgment interest to the less culpable party in a case involving mutual fault would be appropriate to "ameliorate somewhat the harsh American rule that division of damages must be equal without reference to the degree of fault."

Summary of this case from Cement Div. v. City of Milwaukee

In Afran Transport we noted that, although under The Wright prejudgment interest is not usually awarded in mutual fault collision cases, a district court might nonetheless award it in the exercise of its discretion if the party to whom it is awarded is only slightly at fault, in order to ameliorate the harshness of the equal division of damages rule.

Summary of this case from Iberian Tankers Co. v. Gates Construction Corp.

In Afran Transport Co. v. The Bergechief, 2 Cir., 285 F.2d 119, 120, we stated that "normally the award of interest may await the court's judgment which fixes the amount due.

Summary of this case from Skibs A/S Siljestad v. Luckenbach

In Afran Transport, supra, the Second Circuit observed that "Normally the award of interest may await the court's judgment which finds the amount due" (285 F.2d at 120).

Summary of this case from Iberian Tankers Co. v. Gates Construction Corp.
Case details for

Afran Transport Co. v. the Bergechief

Case Details

Full title:AFRAN TRANSPORT CO., as owner of The S.S. Burgan, etc.…

Court:United States Court of Appeals, Second Circuit

Date published: Dec 28, 1960

Citations

285 F.2d 119 (2d Cir. 1960)

Citing Cases

Iberian Tankers Co. v. Gates Construction Corp.

The Wright (2nd Cir. 1940) 109 F.2d 699, 702. This qualification is important, because having found that…

Iberian Tankers Co. v. Gates Construction Corp.

The court's interpretation of The Wright is perhaps plausible enough in light of the language of that…