From Casetext: Smarter Legal Research

530 East 89 Corp. v. Unger

Court of Appeals of the State of New York
Dec 15, 1977
43 N.Y.2d 776 (N.Y. 1977)

Summary

dealing with architects

Summary of this case from Gilliland v. Elmwood Properties

Opinion

Argued November 10, 1977

Decided December 15, 1977

Appeal from the Appellate Division of the Supreme Court in the First Judicial Department, SAMUEL R. ROSENBERG, J.

Benedict Ginsberg for appellant.

Nathaniel Rothstein for respondent.


MEMORANDUM.

The order of the Appellate Division should be affirmed, without costs.

It is incumbent upon the plaintiff to present expert testimony to support allegations of malpractice (McDermott v Manhattan Eye, Ear Throat Hosp., 15 N.Y.2d 20, 24; Nauman v Beecher Assoc., 24 Utah 2d 172; 7 Wigmore, Evidence [3d ed], § 2090), except where the alleged act of malpractice falls within the competence of a lay jury to evaluate (Hammer v Rosen, 7 N.Y.2d 376). This case is unusual in that the alleged architectural malpractice involves protracted delays in responding to objections raised by the New York City Department of Buildings, rather than the submission of defective plans per se. Whether the allegedly inordinate delays of defendants in complying with objections of the building department constituted architectural malpractice is not within the competence of an untutored layman to evaluate. Common experience and observation offer little guidance. Absent a standard of competent architectural practice based on expert testimony, it would be difficult, if not impossible, to form a reasoned opinion as to whether, given the nature and number of objections raised as well as other relevant attendant circumstances, a delay of two years constituted incompetent architectural practice.

While plaintiff did elicit expert testimony from an architect, we agree with the Appellate Division that his testimony "is not sufficient to support a claim of negligence". When asked to comment upon the elapsed time between the issuance of and responses to building department objections, the expert witness stated that there had generally been "an unusually long delay", and that he "would say that there was an undue delay between some or many of the objections and the responses to these objections". By limiting his opinion to "some or many" of the objections, the witness left it to conjecture whether those unduly delayed responses in particular proximately caused the failure of the construction project. The demise of the project may have been the result of defendants' failure to comply with objections to which even the most diligent and competent architect would not have satisfactorily responded within the existent time constraints. Put another way, the expert testimony does not so much as imply that a competent architect would have timely complied with all the building department objections. While plaintiff, at the close of its case, is entitled to all favorable inferences reasonably drawn from the evidence (Patterson v Proctor Paint Varnish Co., 21 N.Y.2d 447), the fact finder may not render a factual determination devoid of support. We do not believe that the expert testimony in this case is sufficient to enable the jury to infer reasonably that defendants' undue delays proximately caused plaintiff's injury.

Insofar as the breach of contract cause of action is concerned, we agree with the Appellate Division that defendants never guaranteed plaintiff that they would provide plans acceptable to the department of buildings.

Chief Judge BREITEL and Judges JASEN, GABRIELLI, JONES, WACHTLER and COOKE concur in memorandum; Judge FUCHSBERG taking no part.

Order affirmed.


Summaries of

530 East 89 Corp. v. Unger

Court of Appeals of the State of New York
Dec 15, 1977
43 N.Y.2d 776 (N.Y. 1977)

dealing with architects

Summary of this case from Gilliland v. Elmwood Properties

In 530 E. 89 Corp. v Unger (43 NY2d 776 [1977]), a case where it was alleged that defendants architect had committed malpractice, the court held that the failure to present expert evidence on the issue of defendants’ inordinate delays in complying with objections of the building department was fatal (id. at 777).

Summary of this case from Escabi v. Twins Contracting, LLC

In Unger, the plaintiff-builder alleged the defendants-architects committed malpractice by his failure to respond in a timely manner to objections raised by the New York City Department of Buildings; there was no allegation that the plans submitted by the defendant were defective.

Summary of this case from Cortland Apts., LLC v. Simbari Design Architecture, PLLC
Case details for

530 East 89 Corp. v. Unger

Case Details

Full title:530 EAST 89 CORP., Appellant, v. ARTHUR A. UNGER et al., Doing Business as…

Court:Court of Appeals of the State of New York

Date published: Dec 15, 1977

Citations

43 N.Y.2d 776 (N.Y. 1977)
402 N.Y.S.2d 382
373 N.E.2d 276

Citing Cases

Chicago Col. of Ost. Med. v. George A. Fuller

Other courts also have applied the professional standard of care to supervisory and administrative activities…

Michael v. He Gin Lee Architect Planner, PLLC

A motion pursuant to CPLR 4404(a) to set aside a jury verdict and for judgment as a matter of law will be…